This is a Questions and Answers document clarifying key aspects of the Chem Latrine BPA solicitation (FA466126Q0029) for sanitation services at Dyess Air Force Base. The document addresses ten substantive inquiries regarding contract scope, service frequency, equipment quantities, and operational requirements. Key clarifications include: the contractor is responsible for water provision and historical disposal facilities; there is no guaranteed service frequency as calls will be made by authorized personnel on an as-needed basis; relocation services for grey water storage tanks and VIP trailers will be separately priced line items with 24-hour completion for routine requests and 4-hour completion for emergency requests; equipment quantities and service frequency depend on monthly mission needs with no historical data provided; electrical power will be location-dependent, determined at the call level; and the specification reference to "potable water" will be revised to "non-potable water" in the Performance Work Statement.

The BPA structure is an estimated five-year ordering period rather than a multi-year contract, allowing the government flexibility in ordering based on operational requirements at Dyess Air Force Base. The government confirmed it will not provide disposal facilities, water, or guarantee service frequency, placing these responsibilities on the contractor. The Q&A document does not address pricing terms, specific award dates, or set-asides, but provides critical operational and performance guidance that contractors must understand when submitting quotes. Questions deadline was April 3, 2026 at 10:00 a.m. CDT, with offer receipt deadline of April 10, 2026 at 10:00 a.m. CDT.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Is there an historical disposal facility being used for this contract?

a. No this is the contractor’s responsibility.

2. Will water be provided by the government?

a. No this will fall under the contractor.

3. Could you please confirm the anticipated start date for the period of performance?

a. Ordering period will depend on when the award decision is made. Individual period of performance for calls will be determined at the call level.

4. Could you please confirm the required frequency of services under the contract for the grey water storage tanks and VIP trailers? If service is expected can we list it out separately from CLINs 1001,1002,1003,1004,1005?

a. There is no guaranteed, or estimated frequency of service. Services will be based on individual calls made by authorized callers.

5. Can you confirm if this is a multi year contract?

a. No this is a BPA. Ordering period is estimated for a five year period.

6. Could you please confirm the required relocation services under the contract for the grey water storage tanks and VIP trailers? If relocations is expected can we list it out separately from CLINs 2001, 2002?

a. Relocation of Units: At the Government's request, the Contractor shall relocate units. Routine relocation requests require completion within 24 hours. Emergency relocation shall be completed within 4 hours. Relocation shall be a separately priced line item.

7. How many units of each different type of equipment is required on a month to month basis? Are there any historical data you can share?

a. It greatly depends on what is happening on the base each month. No current historical data is provided.

8. Will electrical be provided or are the trailers expected to be run off of generator power?

A. This would depend on the location of services, if the trailer is placed near a facility we can utilize electricity if the trailers are placed away from facilities it would have to have an alternative source of power. This will be determined at the call level.

9. How many ADAs and Standard Portable Restrooms will be needed throughout the year? If you are unable to give an answer, can you provide historical reference or an estimate?

a. Depends on the mission needs each month can vary.No historical data is provided.

10. Potable water is not the industry standard. Will the federal government strike "potable" on section 3.1.1.3.1.?

a. Yes. Will change to Non-Potable.

File details come from the government source that posted it. Updated .