This document contains Questions and Answers (Q&A) for solicitation FA466125Q0153 for a Dyess Fitness Center Bleacher Replacement project. The Q&A addresses two key points: the number of bleacher banks to be replaced and the contract period of performance. Specifically, the government clarifies that the project requires replacement of 4 total bleacher banks (2 banks on each side), not just 1 bank per side as initially questioned. The period of performance for the contract is 120 days once the contract is awarded.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA466125Q0153 Dyess Fitness Center Bleacher Replacement Questions

1. In 1.1 it details that the contractor shall provide a total of four banks for the bleachers, but drawing provided is for one bank of bleachers on each side(2 Total).

Will one bank of bleachers per side suffice if it meets criteria?

a. No, per the pictures I sent, we have 2 banks of bleachers on each side (4 total) and we want to do a 1 for 1 swap.

2. What is the period of performance once awarded?

a. 120 days