This document is a Questions and Answers file for a Dyess Air Force Base Intrusion Detection System (IDS) project at Building 7312. The Q&A provides detailed technical specifications for the installation, including facility characteristics such as the building's age (constructed in December 1954, renovated in 2025), wall types (brick perimeter), ceiling configurations (suspended in most areas with a raised floor in classrooms), and specific system requirements. Key technical installation details include mandatory 100% conduit wiring for IDS/ACS, a dedicated AC power circuit, plenum wire acceptance, and installation of two Kaba MAS X-10 cipher locks at primary and secondary entrances.
The related federal contract opportunity, Solicitation Number FA466125Q0118, is issued by the 7th Contracting Squadron at Dyess AFB and seeks a contractor to deliver and install a Honeywell Vindicator Intrusion Detection System (V3). The solicitation requires the contractor to provide all necessary labor, personnel, equipment, and materials for system installation, with post-installation training included. Contractors must submit questions by June 5, 2025, at 2:00 p.m. CST, with quotes to be emailed to specified Air Force contact emails. The project is under the Department of the Air Force Global Strike Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.docx | DOCX document | |
| RFQ FA466125Q0118 Amendment 1.docx | DOCX document | |
| 1. FAR Provisions and Clauses.pdf | ||
| 3. Brand Name J&A_Redacted.pdf | ||
| 4. Statement of Work.pdf | ||
| 5. Salient Characteristics.pdf | ||
| 6. Bldg 7312 Floor Plan.jpg | JPG image | |
| RFQ FA466125Q0118.docx | DOCX document | |
| 2. FAR 52.212-5.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1. How old is the facility? Dec 1954, most recently renovated 2025
1. How stable is the power? As stable as any on base. There is no generator power
1. Is there a dropped ceiling in all areas of installation? Not in the hallways, but everywhere else. The classroom area has a raised floor
1. What type of walls are in the perimeter areas? Brick
1. Do we need to drill between the walls, to run our cable infrastructure? All wiring installed for IDS/ACS is required to be 100% in conduit. Contractors are also required to provide a dedicated AC power circuit for all of our equipment. This will require additional conduit as well
1. Do we need to use conduit? If yes, what do you estimate the total conduit footage will be? See above answer.
1. Are the door frames metal and concrete filled? Metal, not concrete filled.
1. Do you currently have existing IDS Sensors in your doors? Please specify which doors. There is not nor ever has been an IDS on B7312
1. What is the manufacturer of the existing IDS system? See above answer.
1. Will we be able to reuse the existing cable? If so, what type of cable is there currently? There is no existing cable inside B7312.
1. Are Ceilings Suspended? Or Hard Lid? Suspended
1. Are there existing Cable Trays for wiring above ceilings? No
1. Can Existing Wiring be utilized? No
1. Is a “UPS” required? If so, What Time/Power Duration is required? Yes
1. What is the height of Exterior Cameras? (If any) No exterior Cameras
1. Are there pipe chases between floors? There is a raised floor in the classroom area.
1. Is “Plenum Wire” acceptable? Yes.
1. What kind of cipher lock and quantities are required e.g. X-10? After discussion with the Wing Information Security Program Manager, 2 x Kaba MAS X-10 locks are required for the primary and secondary entrance.