Questions and Answers.docx

DOCX document 16 KB Posted

Attached to
Dyess AFB - Honeywell Vindicator Intrusion Detection System (V3)
Solicitation number
FA466125Q0118
Issued by

About this file

The document is a Questions and Answers file for the Dyess AFB Honeywell Vindicator Intrusion Detection System (V3) solicitation. The Q&A provides detailed facility characteristics for Building 7312, including construction details such as brick perimeter walls, suspended ceilings, and a raised floor in the classroom area. Key technical infrastructure details reveal no existing cable infrastructure, no cable trays, no exterior cameras, and no current intrusion detection system in place.

The solicitation, issued by the 7th Contracting Squadron at Dyess AFB, requires a comprehensive installation of a Honeywell Vindicator Intrusion Detection System (V3), including all labor, personnel, equipment, and post-installation training. Contractors must submit questions by 5 June 2025 at 2:00 p.m. CST, with quotes to be emailed to samuel.gonzales.1@us.af.mil and taylor.norris@us.af.mil. The project is under the Department of the Air Force Global Strike Command, with a facility originally constructed in December 1954 and most recently renovated in 2025.

View the file

Other files

File Type Posted
Questions and Answers.docx DOCX document
RFQ FA466125Q0118 Amendment 1.docx DOCX document
1. FAR Provisions and Clauses.pdf PDF
3. Brand Name J&A_Redacted.pdf PDF
4. Statement of Work.pdf PDF
5. Salient Characteristics.pdf PDF
6. Bldg 7312 Floor Plan.jpg JPG image
RFQ FA466125Q0118.docx DOCX document
2. FAR 52.212-5.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. How old is the facility? Dec 1954, most recently renovated 2025

1. How stable is the power? As stable as any on base. There is no generator power

1. Is there a dropped ceiling in all areas of installation? Not in the hallways, but everywhere else. The classroom area has a raised floor

1. What type of walls are in the perimeter areas? Brick

1. Do we need to drill between the walls, to run our cable infrastructure? All necessary conduit has been installed.

1. Do we need to use conduit? If yes, what do you estimate the total conduit footage will be? See above answer.

1. Are the door frames metal and concrete filled? Metal, not concrete filled.

1. Do you currently have existing IDS Sensors in your doors? Please specify which doors. There is not nor ever has been an IDS on B7312

1. What is the manufacturer of the existing IDS system? See above answer.

1. Will we be able to reuse the existing cable? If so, what type of cable is there currently? There is no existing cable inside B7312.

1. Are Ceilings Suspended? Or Hard Lid? Suspended

1. Are there existing Cable Trays for wiring above ceilings? No

1. Can Existing Wiring be utilized? No

1. Is a “UPS” required? If so, What Time/Power Duration is required? Yes

1. What is the height of Exterior Cameras? (If any) No exterior Cameras

1. Are there pipe chases between floors? There is a raised floor in the classroom area