LPR Questions and Answers.pdf
PDF 97 KB Posted
- Attached to
- License Plate Reader
- Solicitation number
- FA466124Q0066
About this file
This document is a set of questions and answers related to a federal contract opportunity for installing a License Plate Reader (LPR) CCTV system at Dyess Air Force Base.
The key details are:
- The government is looking for a vendor to install an LPR system at the entry gates of Dyess Air Force Base to continuously record license plates for security purposes.
- This is a small business set-aside under NAICS code 334290, so only small businesses registered in SAM.gov under this code will be considered.
- A site visit will be held on June 27, 2024 at 10:00 am. Interested vendors must RSVP to attend.
- Questions are due by June 17, 2024 at 3:00 pm CST, and an amendment will be issued with answers.
- Offers are due by June 25, 2024 at 10:00 am CST and should be emailed to the contracting officer.
- Award will be based on best value, considering technical acceptability, price, and delivery.
- Funds are not yet available, so no award will be made until funds are appropriated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LPR Questions and Answers
1. Are Scaled Drawings available, if so please post.
No
2. Are Ceilings Suspended? Or Hard Lid?
Suspended
3. Are there existing Cable Trays for wiring above ceilings?
Probably not. I am not sure what those are.
4 .Can Existing Wiring be utilized?
Electrical
5. Is a “UPS” required? If so, What Time/Power Duration is required?
No. The facility is already wired for UPS
6. Are “Or Equal” Equipment substitutions allowed?
Yes
7. Is “Plenum Wire” acceptable?
I do not know what that is.
8. Is “After Hours Access” for said work, available to contractor at no add’l cost to the
Gov’t?
Yes.
9. What is the height of Exterior Cameras? (If any)
Approximate 16’
10. Please provide/post other “Q & A” requests.
N/A
11.Please provide a list of equipment to be installed
See attached
LPR Questions and Answers 12 Are there pipe chases between floors?
The building is a single story.
13. What is the range of the budget for this project, and is it already appropriated?
We do not provide budget information to vendors in supplies/services. The money is appropriated.
14. Because of the high cost of the parts can we bill when parts arrive on site, or in the alternative are progress payments allowed?
When all parts arrive and are accounted for by the WAWF POC and inspect and accepts the parts, you are allowed to bill on those CLINS. Progress payments are not allowed.
15. How many feet of new wire will have to be run?
Unknown. There will be a site visit on 27 June at 1000 am where you would have the opportunity to gauge the length of wire needed.
16. What kind of cipher lock and quantities are required e.g. X-10
No lock required.
File details come from the government source that posted it. Updated .