Question and Answers.pdf
PDF 65 KB Posted
- Attached to
- Snyder Fiber Optic Cable Federal contract opportunity
- Solicitation number
- FA466120Q0012
About this file
This document includes a question and answer file and a federal contract opportunity solicitation. The question and answer file provides specifics on a site visit scheduled for August 31st at 1:00 PM and mileages from a main site to remote emitter sites. The solicitation requests a contractor to install 24 strand single-mode fiber optic cabling with 50MB bandwidth and 5 phone numbers at each of three remote emitter sites located 13, 7.4, and 22 miles from the main site. The contractor must provide all personnel, equipment, materials, and services to complete the installation, including hand holes, ducting, testing, and termination. The opportunity is for the Department of the Air Force Global Strike Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question and Answers 3.pdf | ||
| Question and Answers 2.pdf | ||
| Snyder ESS Winston Field to Union RES.pdf | ||
| Snyder ESS Winston Airfield to Hermleight RES.pdf | ||
| Snyder ESS Winston Field to Lake Thomas RES.pdf | ||
| RFP Snyder Fiber Optic Updated.pdf | ||
| PWS Snyder Fiber Optic Upgrade Project.pdf | ||
| RFP Snyder Fiber Optic.pdf | ||
| WD 15-5211 (Rev 14) 27 June 2020.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1: Will there be a site visit?
Answer: Site Visit is scheduled for the 31st of August at 1300 hours.
Question 2: There is no documentation, map or table that defines the installation requirements. I don't know if it's 200 feet or 200 miles of fiber so would the Government please consider including any pictures, maps and/or designs with distances available to better understand the project?
Answers: The specific miles to each of the Remote Sites are as follows, and are from the Main Site to each:
Lake Thomas – 13 miles Union – 7.4 Miles Hermleigh – 22 miles
Question 3: Is there a set of plans for the fiber optic install (Handhole and duct system and fiber path)?
No. There aren’t any plans for the install. The hand holes and ducting are to be provided by the contractor, unless they have coordinated with existing Wired Telecommunication carriers to use the existing ducting that is in place now. The contractor that wins the contract would be required to provide the ducting and hand holes, if coordination is not approved by existing services.