DEPARTMENT OF THE AIR FORCE
319TH CONTRACTING SQUADRON (ACC)
GRAND FORKS AIR FORCE BASE, NORTH DAKOTA
8 July 2021
MEMORANDUM FOR RECORD
FROM: 319 Contracting Squadron, Grand Forks AFB, North Dakota
SUBJECT: FA465921R0009, GFAFB A-E Project: Add Restroom/Canopy/Overwatch at Commercial Gate, Questions and Answers
Q1: Are paper copies of the drawings needed for the Draft RFP as well as the Final RFP?
Statement of Work for Type “B” Services, “5. Submittals” states for Draft RFP only 1 CD/DVD is required." Work Standards for A-E Title I Services, “1.3 Electronic submission … A paper copy of the drawings shall accompany the electronic submissions.”
A1: Paper copies are not required for draft submittal.
Q2: Is the A/E/C CAD Standard Release 6.0 the current manual?
A2: As of 7 Jul 20, the current A/E/C CAD Standard Release is 6.1.
Q3: The Type "B" SOW speaks of Design-Build (D-B), "Bridging Documents." I want to verify that we would not be on the hook for the actual construction of the design.
A3: Correct. The scope of this effort does not include construction.
MAUREEN HARRIS, GS-13, DAF
Contracting Officer
| 2021-07-08T06:39:13-0500 | |
| HARRIS.MAUREEN.1407273628 |