Attachment 1 Performance Work Statement (PWS)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4659-13-R-0018-0002.pdf | ||
| Request_for_Information_(RFI).pdf | ||
| Amendment_0001.pdf | ||
| Solicitation-Replace_Carpet.pdf | ||
| Material_Submittal_Schedule.pdf | ||
| Solicitation_Cover_Letter.pdf | ||
| Financial_Institution_Reference_Sheet.pdf | ||
| Wage_Determination.pdf | ||
| Waiver_Green_Procurement_Form.pdf | ||
| Specifications-JFSD201333_.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE
WORK STATEMENT
FOR
Replace Carpet Basic Contract
Grand Forks AFB
30 Jul 2013
Table of Contents:
1. DESCRIPTION OF SERVICES. 1
1.1. BASIC SERVICES. 1
1.1.1. VERIFICATION OF DIMENSION. 1
1.1.2. CARPET/COVE BASE REMOVAL. 1
1.1.3. DISPOSAL OF DEBRIS. 1
1.1.4. FLOOR SURFACE REPAIR. 1
1.1.4.1. PATCH FLOORING. 1
1.1.5. SURFACE PREPARATION PRIOR TO INSTALLATION. 2
1.1.6. INSTALLATION OF BROADLOOM CARPET. 2
1.1.6.1. INSTALLATION METHOD. 2
1.1.6.2. SEAMS. 2
1.1.7. MOLDING/TRANSITION STRIPS. 2
1.1.8. INSTALLATION OF CARPET TILE. 2
1.1.9. ADHESIVES. 3
1.1.10. TRANSITION STRIPS. 3
1.1.11. COVE BASE. 3
1.1.12. PRESENCE OF FURNITURE. 3
1.1.13. CODES. 3
2. STANDARD TESTS, QUALITY, AND GUARANTEES. 3
3. CONTRACTOR USE OF PREMISES. 3
3.1. WORK AREA. 3
3.2. STORAGE AREA. 3
3.3. SITE CLEANLINESS. 3
3.4. REFUSE COLLECTION. 3
3.5. SITE SECURITY/HOUSEKEEPING. 4
3.6. SITE UTILITIES. 4
3.7. TOILET FACITILITIES. 4
3.8. ELEVATORS. 4
3.9. SEVERE WEATHER. 4
3.10. VEHICLE CONTROL. 5
3.11. EQUIPMENT CONDITION. 5
4. CONTRACTOR’S TEMPORARY FACILITIES. 5
5. GOVERNMENT FURNISHED SERVICES 5
5.1. INSECT AND RODENT CONTROL. 5
5.2. SECURITY POLICE AND FIRE PROTECTION. 5
5.3. EMERGENCY MEDICAL SERVICES. 5
6. WORK SEQUENCE. 6
6.1. COMMENCEMENT OF WORK. 6
6.2. PROJECT EXECUTION. 6
6.3. FORCED WORK STOPPAGE. 6
6.4. INTERRUPTION OF UTILITY SERVICES. 6
6.5. WORK IN SECURE AREAS. 6
7. ADMINISTRATION REQUIREMENTS. 7
7.1. SUPERVISION. 7
7.2. RECORDS MANAGEMENT REQUIREMENTS BY THE CONTRACTOR. 7
7.3. AVAILABILITY OF CADD DRAWING FILES. 7
8. NOTIFICATIONS TO THE CONSTRUCTION MANAGEMENT
OFFICE (CMO) AND PROJECT COORDINATION. 8
8.1. WORK SCHEDULES. 8
8.2. INTERRUPTION OF ACTIVITIES TO BASE PERSONNEL. 8
8.3. WORK ON MEDICAL FACILITIES. 8
8.4. CONTRACTOR FURNISHED EQUIPMENT DATA. 8
8.5. WARRANTY. 8
8.6. WORK SCHEDULE. 8
9. SUBMITTALS. 8
9.1. MATERIAL SUBMITTALS. 8
9.2. SUBMITTAL PREPARATION. 9
9.3. MANUFACTURER’S INSTRUCTIONS. 9
10. ENVIRONMENT PROTECTION. 9
10.1. HAZARDOUS WASTE. 9
10.2. CONSTRUCTION AND DEMOLTION DEBRIS. 9
10.3. HAZARDOUS MATERIALS. 9
10.3.1. PROCEDURES. 10
10.4. RECYCLE PROGRAM. 10
11. BASE ENTRY PROCEDURES. 10
11.1. MINIMUM SECURITY REQUIREMENTS (ALL AREAS 10
INCLUDING BASE ENTRY). 10
11.1.1. VISITOR PASSES. 10
11.1.2. MATERIAL DELIVERIES. 11
11.1.3. CONTRACTOR VEHCLES. 11
11.2. CONDUCT REQUIREMENTS. 11
11.2.1. OPERATING MOTOR VEHICLES. 11
Appendix A. 12
Appendix B. 13
Appendix C. 14
Appendix D. 16
PERFORMANCE-BASED WORK STATEMENT
FOR
REPLACE CARPET BASIC CONTRACT
1. DESCRIPTION OF SERVICES. The work consists of furnishing all plant, labor and materials to perform all work in strict accordance with these technical provisions and the project drawings. The work site is on Grand Forks Air Force Base, ND including but not limited to dorms, recreation facilities, office areas and daycare facilities.
1.1. BASIC SERVICES. The contractor shall provide carpet replacement services at Grand
Forks Air Force Base. The project shall include, but is not limited to the following:
Carpet removal
Cove base removal
Transition strip removal
Floor patching and surface preparation
Broadloom carpet installation
Carpet tile installation
Cove base installation
Transition strip installation
1.1.1. VERIFICATION OF DIMENSION. Contractor is responsible for measuring the work area(s) to confirm room size prior to cutting required amounts from carpet rolls, even though plans are provided to the contractor showing approximate size and general shape of the room.
All salvageable portions of carpet (in excess of 10 square yards (SY)) shall be rolled, marked and delivered to Material Control in building 418.
1.1.2. CARPET/COVE BASE REMOVAL. Contractor shall remove existing carpet and cove base in work area in a manner to prevent unnecessary damage to work area, to include but not limited to wall paper, trim, and cabinetry. Contractor will not commence any work prior to the arrival of all carpet on base.
1.1.3. DISPOSAL OF DEBRIS. The contractor shall dispose of all scrap materials and debris at an off-base location. Contractor shall furnish refuse containers of the necessary capacity required. Disposal shall be in accordance with existing local, state and federal regulations and shall not be allowed in base refuse containers. The contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations. Debris must be removed at the end of each work day.
1.1.4. FLOOR SURFACE REPAIR. Repair or replacement of existing carpet tile(s) shall include repair of floor surfaces damaged by the removal process or material used to secure the tiles.
1.1.4.1. PATCH FLOORING. Repair of minor holes and spalls in the cement, wood or tile floor shall be made with latex cement compatible with existing surfaces. The contractor’s responsibility for such floor repair preparation shall be limited to the use of no more than one gallon of latex cement per ten square yards of floor area to be covered. Any floor repairs in excess of this amount shall be reimbursed by the government in accordance with the price schedule. The Contracting Officer or representative shall be notified at least one hour prior to the commencement of repairs that will be submitted for reimbursement. Verification of notification from the contracting officer or representative must be attained prior to performing such repairs.
1.1.5. SURFACE PREPARATION PRIOR TO INSTALLATION. All materials must be removed as part of the surface preparation including, but not limited to, tackless strip and old padding. The surface must also be swept clean. All surface prep shall conform to the manufacturer’s installation specifications.
1.1.6. INSTALLATION OF BROADLOOM CARPET. Carpets A and B as labeled on the price schedule will be broadloom carpet. Carpet A will be Shaw Constellation/Phoenix or approved equivalent, as determined through the submittal procedures outlined in paragraphed
9.1. Manufacturing specifications for Carpet A can be found in Appendix A of this document.
Carpet B will be Shaw Interplay/Youngstown or approved equivalent. Manufacturing specifications for Carpet B can be found in Appendix B of this document.
1.1.6.1. INSTALLATION METHOD. Carpet shall be installed by direct glue-down methods in accordance with manufacturer’s installation specifications. Installed carpet shall be smooth, uniform and secure, with minimal seams. Patterns shall be accurately matched. Cutouts, as at door jambs, columns and ducts shall be neatly cut and fitted securely.
1.1.6.2. SEAMS. Seams shall be uniform, unnoticeable, and treated with a seam adhesive. Side seams shall run towards the light where practical and where such layout does not increase the number of seams. Breadths shall be installed parallel, with carpet pile in the same direction.
Seams at doorways shall be located parallel to and centered directly under doors. Seams shall not be made perpendicular to doors at pivot points. Seams at changes in direction of corridors shall follow the wall line parallel to the carpet direction.
1.1.7. MOLDING/TRANSITION STRIPS. Edges of carpet meeting hard surface flooring or different carpeting (pattern, texture, weight, etc.) shall be protected with molding. Installation shall be in accordance with the molding manufacturer’s instructions. Existing molding must be replaced if damaged or unsightly. Replacement of damaged or unsightly molding shall be coordinated with either the project manager or Contracting Flight.
1.1.8. INSTALLATION OF CARPET TILE. The contractor shall install carpet tile (carpet squares) in accordance with manufacturer’s installation specifications. Carpets C will be tiled carpet of an organic pattern meeting the specifications located in Appendix C at the end of this document. Carpets D will be tiled carpet of a geometric pattern meeting the specifications located in Appendix C at the end of this document.
1.1.9. ADHESIVES. Adhesive for installation of carpet shall be waterproof, nonflammable and as recommended by the carpet manufacturer. Seam adhesive shall be waterproof, nonflammable and nonstaining as recommended by carpet manufacturer.
1.1.10. TRANSITION STRIPS. Transition strips shall be replaced to match existing. Most common transitions currently on base are aluminum or vinyl. All transitions strips shall be hammered surface, pinless clamp-down type, designed for the type of carpet being installed.
Finish shall be natural color anodized or pre-finished to match installed flooring. Manufacturer’s specifications for transitions strips can be found in Appendix D.
1.1.11. COVE BASE. In locations where cove base is present and installation of new carpet will require replacement of that cove base, new cove base shall be in accordance with specifications located in Appendix D of this document. Locations of cove base to be replaced will be directed by the government in the documentation for each specific task order under this contract.
1.1.12. PRESENCE OF FURNITURE. The government is responsible to remove all furniture and other items in areas to be surfaced prior to removal/installation date as coordinated through
Contracting and the project manager.
1.1.13. CODES. International Conference of Building Officials has established the basic building code standards for construction, renovation, repair, and maintenance. These standards, commonly referred to as the International Building Code (IBC), together with the Unified
Facilities Criteria UFC 1-200-01 found at http://www.wbdg.org/ccb/DOD/UFC/ufc_1_200_01.pdf shall constitute the minimum acceptable levels of construction, function, and safety for all projects.
2. STANDARD TESTS, QUALITY, AND GUARANTEES. The contractor shall provide a minimum one year warranty on all work performed. A copy of the warranty shall be submitted to the Contracting Officer before final inspection of the facility.
3. CONTRACTOR USE OF PREMISES.
3.1. WORK AREA. All locations for carpet removal and replacement will be vacated by government prior to commencement of work. The contractor will be provided a minimum of 6 dorm rooms per day while working in a dormitory.
3.2. STORAGE AREA. The contractor may have carpet delivered to and stored in B418
Material Control Section (MCS). The contractor shall be responsible for pick-up of carpet at
MCS. Their hours of operation are 0630 to 1700. MCS will not be available outside of normal duty hours. The contractor shall make all cuts during normal hours that will be needed for any approved abnormal hours of work.
3.3. SITE CLEANLINESS. A visually acceptable site at Grand Forks Air Force Base is an important construction standard. A safe and visually acceptable (neat, clean, free of rubbish) construction or work site at Grand Forks AFB is an important construction standard and will enforced. The contractor will maintain trailers and portable storage containers in good condition or must remove them.
3.4. REFUSE COLLECTION. The contractor is responsible for disposing of construction debris and contractor-generated refuse at construction sites safely and properly in accordance with this section.
3.5. SITE SECURITY/HOUSEKEEPING. The contractor is solely responsible for the security of his/her property and general housekeeping of the project area(s). This includes, but is not limited to, vegetation (weed control) and height maintenance to base standards, daily trash and refuse debris collection and containerization, and construction materials stacked, neatly palletized or in enclosed trailers.
3.6. SITE UTILITIES. The government will provide utilities (*water, gas, and electricity) for project work areas when available. The government will NOT modify points of distribution to accommodate contractor project activities. The government will not provide utilities
(gas/electric) solely for construction heating purposes. At remote project work areas where no utilities are available, the contractor shall furnish his/her own utility services. * Contactor shall use an approved backflow prevention devices when connecting to the GFAFB’s water distribution system. Contractor shall also inform CES Utilities (X5200) and Bioenvironmental
Engineering (BEE at X5596) of potential rupture or contamination of GFAFB’s water. The affected system will be quarantine. The contractor shall be responsible for collecting and analyzing bacteriological samples. Sample result shall be reported to BEE. BEE shall review result and approved affected water line be available to the system.
3.7. TOILET FACITILITIES. Contractor personnel may use existing toilet facilities if available on the premises and approved by the facility occupants and the CO or his/her designated representative. At construction sites where toilet facilities are not readily available, the contractor shall provide his/her own chemical sanitary toilets. The contractor shall service the chemical toilets regularly subject to government inspection by the base medical officer. The contractor shall correct all identified sanitary deficiencies within 24 hours of inspection.
3.8 ELEVATORS. When required, the contractor shall arrange for temporary use of existing elevators through the CM and CO subject to approval. Only intermittent use of elevators will be approved. The contractor shall provide and maintain suitable and adequate protective covering for the elevator machinery, hatchway entrance, and the interior of the elevator during the period of temporary use. Also, the contractor shall NOT use loads in excess of the rated capacity of an elevator. On completion of the work, the contractor shall remove any protective coverings together with any resultant dirt and debris, and leave the equipment in a condition equal to or better than found.
3.9. SEVERE WEATHER. The contractor shall develop and be prepared to implement procedures to evacuate and/or protect people and facilities under his/her control in the event of severe weather. These procedures will include provisions for securing or repositioning of equipment. The contractor shall notify the CO of any evacuation procedures. Upon receipt of a severe weather warning, the following sequence of actions will occur.
The CO or his/her representative will instruct the contractor of the severe weather warning.
The contractor shall take immediate action to tie down, remove, protect, or secure his/her materials and equipment providing reasonable assurance that the severe weather will not damage government property. If the contractor fails to secure materials and equipment and it becomes a hazard, Air Force personnel may accomplish the work and potential charges to the contractor may result thereof.
3.10. VEHICLE CONTROL. The contractor shall NOT park or run vehicles on grass areas for shortcuts, and or convenience. Only equipment required in direct performance of work will be permitted to enter grass areas. The contractor shall repair or replace any damage done to lawns or shrubs caused by construction equipment or related project activities. Contractor personnel shall load all loose debris on trucks leaving the site in a manner that will prevent dropping materials on streets, and conform to local ordinances. Fasten suitable cover such as a tarpaulin over the load before entering surrounding streets. The contractor shall promptly clean up any materials that falls from trucks. The use of cell phones is prohibited on Grand Forks AFB while operating a motorized vehicle. Seat belts are required at all time while driving a vehicle. Base speed limits are strictly enforced, and violation(s) may result in suspended base driving privileges.
3.11. EQUIPMENT CONDITION. Equipment and vehicles used on base shall be safe and in good operating condition. The contracting officer (CO), CM, Base Safety, or designated representative, reserves the right to inspect any on-base equipment and reject such equipment if he/she considers it unsafe, in poor operating condition, or inappropriate for the work being performed.
4. CONTRACTOR’S TEMPORARY FACILITIES. All temporary sewer and sanitation facilities shall be self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the Contracting Officer. The doors shall be self-closing. The exterior of the unit will match the base standard (antique linen), unless the facility is behind the construction fence or out of the public view.
5. GOVERNMENT FURNISHED SERVICES
5.1. INSECT AND RODENT CONTROL. When the contractor detects an insect or rodent problem, he/she shall notify the appropriate facility manager or construction representative for entomology services.
5.2. SECURITY POLICE AND FIRE PROTECTION. The government will provide security police and fire protection to the extent necessary to ensure a secure and safe construction site. In return for these services, the contractor shall adhere to the security and fire directives, instructions, and policies of Grand Forks AFB.
5.3. EMERGENCY MEDICAL SERVICES. In the event of a severe emergency, the 319th
Medical Facility, during hours of operation, will respond and transport, if necessary, a contractor employee to one of the local hospitals. The contractor shall reimburse the government for these services.
6. WORK SEQUENCE.
6.1. COMMENCEMENT OF WORK. Work shall begin within the number of days specified on the task order. Each task order will have a period of performance assigned to it.
6.2. PROJECT EXECUTION. The work performed under this contract will be both in occupied and unoccupied facilities/areas. In occupied facilities/areas, the contractor shall accomplish all work in a manner that minimizes inconvenience to the using agencies and their mission. The contractor shall perform all work with continuous daily progress. The government will not accept or permit days of no work or times laps of inactivity by the contractor except for drying or curing of previous work or as directed by the CO. The contractor shall protect all government furniture and equipment within the work area from dust, moisture, debris, and damage. The government will hold the contractor responsible for any damages caused by contractor operations as a result of lack of adequate protection of government property. NOTE:
Once electronic equipment becomes contaminated/damaged with dust it cannot be restored and the contractor shall be held responsible to replace such items at no additional cost to the government. The contractor shall maintain the work site, hallways, and emergency exits free of debris, and safe at all times. The contractor personnel shall strictly adhere to safety standards
(OSHA and AFOSH) and practices at all times during the term of the contract.
6.3. FORCED WORK STOPPAGE. In case of emergency the contractor shall call 911. The
CO, base fire chief, and other base authorized emergency response personnel, or their representative(s), have the authority to order the contractor to terminate work and clear the area of personnel and equipment. The contractor shall comply to such an order with all possible speed. When the previously mentioned authority figures or their representative(s) interrupt the contractor’s operations, the contractor shall immediately notify the contracting officer of the delay.
6.4. INTERRUPTION OF UTILITY SERVICES. The contractor shall not hold the government responsible for interruptions of utility service. The government will be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.
The contractor always has the choice to provide backup power generation, and such in the event of base utility outages.
6.5. WORK IN SECURE AREAS. The contractor shall comply with security regulations imposed by the installation commander and/or the agency responsible for the project location.
Projects in restricted or controlled areas will require escorting by base personnel. Rules of entry will be established and directed to the contractor at the preconstruction meeting for associated projects.
7. ADMINISTRATION REQUIREMENTS.
7.1. SUPERVISION. Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
7.2. RECORDS MANAGEMENT REQUIREMENTS BY THE CONTRACTOR. The
contractor shall make available in a timely manner, any permits, reports, or general performance data required in the PWS. The contractor shall also mark any/all proprietary information in the records submitted to the Air Force/Government for Freedom of Information Act purposes. The contractor shall create, handle and maintain records for the Air Force, regardless of medium, (in a pre-agreed medium that can be used by the Air Force ) in accordance with the requirements established in AFRIMS Records Disposition Schedule (RDS), AFI 33-322, Records
Management program, AFI 33-364, Records Disposition Procedures and Responsibilities, and
AFMAN 33-363, Management of Records. Full text versions of these publications are available for download at http://www.epublishing.af.mil. The contractor’s records person should attend
Records Management Orientation Training conducted by the Base Records Manager. Inquiries as to the specific actions necessary to meet the requirements established in the above referenced publication may be directed to the GFAFB Records Management Office at (701) 747-6143 or
319th CS/SCXK, Bldg 314, GFAFB, ND, 58205-6436.
7.3. AVAILABILITY OF CADD DRAWING FILES. After award and upon request, the electronic “Computer Aided Drafting and Design (CADD)” drawings files will be made available to the contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the contractor and without liability or legal exposure to the Government. The contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney’s fees and defense costs, arising out of or resulting from the use of these electronic files. These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents.
The Government makes no representation regarding the accuracy or completeness of the electronic CADD files and the corresponding construction documents. In the event that a conflict arises between the signed and sealed construction documents prepared by the
Government and the furnished CADD files, the signed and sealed construction documents shall govern. The contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the contractor uses, duplicates and/or modifies these electronic
CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
http://www.epublishing.af.mil/
8. NOTIFICATIONS TO THE CONSTRUCTION MANAGEMENT OFFICE (CMO)
AND PROJECT COORDINATION. The contractor shall notify COR (Contracting Officer
Representative) at least seven days in advance of starting all work. This shall include, but is not limited to, notification when the initial work shall begin; when work shall resume after stoppage exceeding five work days; and when work shall begin following all specified exclusion periods.
8.1. WORK SCHEDULES. The contractor shall coordinate all work schedules with the
Contracting Officer (CO) and with the designated Base Civil Engineer Construction
Representative (CR) prior to the start of work. The contractor shall participate in progress meetings as directed by the CO and/or the CR. Attendance at these meetings may include the contractor’s corporate management representative(s) at the CO’s discretion.
8.2. INTERRUPTION OF ACTIVITIES TO BASE PERSONNEL. If it becomes necessary to interrupt base activities in buildings, the contractor shall request permission, in writing, from the CO five (5) working days in advance.
8.3. WORK ON MEDICAL FACILITIES. The contractor shall coordinate all work in medical facilities through the CO with medical/dental treatment staff liaisons and the
Construction Representative to minimize interruption of care services to their customers.
8.4. CONTRACTOR FURNISHED EQUIPMENT DATA. Approximately ten days prior to project final inspection the contractor shall furnish the following data to the Contracting Officer:
8.5. WARRANTY. Provide a list of all items which are specified to be warranted accompanied by a copy of each specific warranty. For each specific warranted item, the list shall include the name, address, and telephone numbers of the subcontractor who installed the item, the supplier or distributor, and the manufacturer. The completion date of the warranty period shall correspond to the applicable specification requirements for each warranted item.
8.6. WORK SCHEDULE. The standard hours of work on Grand Forks Air Force Base are from 0800 to 1630 hours; Monday through Friday, excluding Federal holidays. If the contractor desires to work during periods other than the base standard work hours, additional Government inspection forces may be required. Therefore, to gain approval to work non-standard hours/days the contractor shall make his/her request in writing to the Contracting Officer three work days
(minimum) in advance of his/her intention to work during periods other than standard work hours/days. The government is not responsible for incurred costs by the contractor when they work irregular or extended work hours. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates may be charged to the contractor.
9. SUBMITTALS.
9.1. MATERIAL SUBMITTALS. Upon award of this contract, the contractor shall submit to the Contracting Officer for approval four hard copies of manufacturer's data, catalog cuts, samples, or other information as required for the items on the Material Submittal Schedule.
Contractor needs to submit samples for the full product line style. Full tiles for modular carpet and minimum 9"x9" samples for broadloom. Government will select 1-3 colors of each to be our standard selection. Sample submittals are not required for individual task orders as long as the product hasn't changed. Additionally, contractor shall provide Material Safety Data Sheets
(MSDS’s). MSDS’s required for cove base adhesive, floor patch, glue and seam sealer. No new materials shall be used unless MSDS has approved by CO.
9.2. SUBMITTAL PREPARATION. In preparing submittals it shall be incumbent upon the contractor to clearly and fully demonstrate that proposed materials, systems, or methods meet or exceed all applicable specific requirements.
9.3. MANUFACTURER’S INSTRUCTIONS. Manufacturer’s instructions pertaining to the use or installation of submitted and approved products, materials, or equipment used or installed in the execution of work under this contract form a part of these specifications as though specifically set forth herein. These instructions apply whether furnished as a normal, usual, or customary practice of the manufacturer or if furnished in response to a requirement stipulated herein.
10. ENVIRONMENT PROTECTION. The contractor shall perform all work in such manner as to prevent the polluting of air, water, or land, and shall follow all applicable federal, state, and local regulations and guidelines. The use of hazardous materials (i.e., lead-based paints, asbestos containing materials and other materials without permission to use) is prohibited. The contractor shall protect against the emission of any hazardous substance(s) that cause or contribute to air pollution and may reasonably be anticipated to endanger health, welfare and the environment.
10.1. HAZARDOUS WASTE. GFAFB is a small quantity generator of hazardous waste. All hazardous waste generated on GFAFB by the contractor must be managed in accordance with small quantity generator standards as specified in 40 CFR 262. The contractor shall comply with all federal, state, and applicable requirements in the GFAFB Hazardous Waste Management Plan
(HWMP). The GFAFB HWMP can be reviewed at the GFAFB Hazardous Waste Office located in Bldg 408 (747-4655).
10.2. CONSTRUCTION AND DEMOLTION DEBRIS. All debris, waste, and excess construction material shall be disposed of off base by the contractor at no cost to the
Government. If any waste material is dumped in areas not permitted by the that state’s regulatory authority, the contractor shall remove the material, dispose of the material in accordance with applicable technical provisions, and restore the area to the condition of the adjacent undisturbed areas. Where directed, contaminated ground shall be excavated, disposed of as approved, and replaced with suitable fill material, all at the expense of the contractor.
10.3. HAZARDOUS MATERIALS. IAW AFI 32-7086 (Hazardous Material Management), contractors using hazardous materials on GFAFB must comply with the authorization procedures outlined below.
10.3.1. PROCEDURES. IAW FAR Clause 52.223-3, each offeror must provide the
Contracting Office with a list of proposed HAZMAT that it plans to use on the installation during the performance of the contract. IAW AFFARS Clause 5352.223-9003, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the HAZMART.
Contractor must submit to the Contracting Office the information and supporting documentation
(including MSDS) necessary to obtain HAZMAT usage authorization. The Contracting Office will transmit the contractor submittal to the HAZMART for processing. If the HAZMAT is a
Class I ODS, the Contracting Officer must also have a copy of the applicable and current SAO approval of the Class I ODS requirements. NOTE: Contractors are not required to coordinate with a government UEC or Unit Safety Representative.
For each contractor-identified HAZMAT that the HMMP team determines does not meet the Air
Force definition of a HAZMAT, the IHMP requirements do not apply. The HMMP team will notify the Contracting Office that the contractor has authorization to bring and use that material on the installation without reporting usage.
If the contractor needs to bring a material on the installation that was not included in the original
HAZMAT listing, the contractor must first notify the Contracting Office and then obtain prior authorization, if the HMMP team determines the material to be a HAZMAT.
All hazardous materials must be approved through the above process prior to bringing any hazardous material on installation.
10.4. RECYCLE PROGRAM. The contractor shall be responsible for complying with the
EPA’s buy recycled program. Information on this program can be found at www.epa.gov/cpg.
Should the contractor be unable to meet EPA recommendations due to design or other considerations they shall notify the CO and request approval of an alternative approach.
11. BASE ENTRY PROCEDURES. Security requirements for Air Force facilities under control of Grand Forks Air Force Base are specific and rigidly enforced. Levels of security include Restricted and Controlled areas. Differing degrees of security are enforced at each area.
Minimum security requirements, common not only to each of these secure areas, are also required for entry onto Grand Forks AFB. Questions of clarification on locations or procedures for controlled/restricted areas contact Security Forces at 701 747-5351. These minimum requirements are outlined below.
11.1. MINIMUM SECURITY REQUIREMENTS (ALL AREAS INCLUDING BASE
ENTRY).
11.1.1. VISITOR PASSES. The Commercial Visitor Control Center will issue a SFMIS AF
Form 74 (Visitor Pass) to the contractor and his/her employees upon completion of screening process for the duration of the contact. The screening process takes time, and the contractor shall visit the Commercial Visitor Control Center prior to expecting base entry to receive required forms and instruction on the application process, to include estimated time of receiving the visitor pass.
http://www.epa.gov/cpg
Although contractors will not be issued vehicles passes vehicles are subject to search while on the installation. Employee privately owned vehicles will not be allowed access to restricted/controlled areas. Company vehicles will be allowed access to restricted/controlled areas.
11.1.2. MATERIAL DELIVERIES. All contractor (including subcontractor) deliveries shall be made through the south gate located off US Highway 2. In order to gain entry onto Grand Forks AFB, the driver must have a valid driver's license rated for the type of vehicle being operated, vehicle registration, proof of insurance, social security number, and the name and contact (telephone) number of someone receiving the delivery. In some cases, an escort may be required to assist drivers in completing the delivery.
Contractors may be required to provide the escort. Drivers are required to exit the installation immediately after completing the delivery.
11.1.3. CONTRACTOR VEHCLES. All contractor vehicles should have markings with the company name for quick identification of ownership and notification if they are involved in an incident.
11.2. CONDUCT REQUIREMENTS. The contractor shall ensure that his/her employees comply with all base traffic regulations and properly conduct themselves while on the base.
11.2.1. OPERATING MOTOR VEHICLES. While operating a motor vehicle on Grand Forks
AFB talking on cell phones is prohibited and seatbelts must be worn at all times.
Appendix A
Carpet A Construction: Pattern loop
Protective treatment: SSP® Shaw Soil Protection or approved equal
Dye method: Solution dyed; yarn dyed
Electrostatic propensity: Less than 3.5 KV - permanent conductive filament
Flammability: ASTM E-648 flooring radiant panel class I
ASTM E-662 NBS smoke chamber less than 450
Warranty: Lifetime commercial limited
Primary backing: Synthetic
Secondary backing: Teklok, Ultraloc MP or approved equal
Gauge: 1/10 minimum
Stitches per inch: 10.0 minimum
Production yarn weight: 26.0 oz / yd2 minimum
Finished pile thickness: 0.12 inches minimum
Average density: 7,800 oz / yd3 minimum
Appendix B
Carpet B
Construction: Textured loop
Protective treatment: SSP® Shaw Soil Protection or approved equal
Dye method: 100% solution dyed
Static control: (AATCC 134) Less than 3.5 kv, built-in permanent conductive fiber
Radiant panel: ASTM E-648 flooring radiant panel class I nbs smoke: ASTM E-662 NBS smoke chamber less than 450
Warranty: Lifetime commercial limited
Secondary backing: Teklok® or approved equal
Gauge: 1/10 minimum
Stitches per inch: 8.0 minimum
Tufted yarn weight: 26.0 oz / yd2 minimum
NSF 140: Gold
Appendix C
Carpets C and D
1. Modular Carpet: Organic Pattern
1.1. Size: 24” x 24”
1.2. Texture: Multilevel pattern loop
1.3. Fiber: Solution died or solution/yarn died, branded nylon type 6,6 or 6.
1.4. Minimum pile weight: 20oz
1.5. Gauge: 1/12 to 1/10
1.6. Minimum density: 6400
1.7. Minimum appearance retention rating: Heavy
1.8. Products with acceptable patterns, colors, and selections include the following:
1.8.1. Shaw: Jekyll II/Kachina II or approved equal
1.8.2. Mohawk/Lees/Bigelow: Funxtion Modular or approved equal
1.8.3. Mannington: A Sense of Place III or approved equal
2. Modular Carpet: Geometric Pattern
2.1. Size: 24” x 24”
2.2. Texture: Multilevel pattern loop
2.3. Fiber: Solution died or solution/yarn died, branded nylon type 6,6 or 6.
2.4. Minimum pile weight: 18oz
2.5. Gauge: 5/64 to 1/10
2.6. Minimum density: 6400
2.7. Minimum appearance retention rating: Heavy
2.8. Products with acceptable patterns, colors, and selections include the following:
2.8.1. Shaw: Color Play/Navajo or approved equal
2.8.2. Mohawk/ Lees/Bigelow: Junxtion Modular or approved equal
2.8.3. Mannington: Scena or approved equal
3. Install modular carpet products in accordance with manufacturer guidelines including floor leveling and preparation.
3.1. Verify installation pattern with contracting officer.
Appendix D
1. Cove Base:
1.1. Vinyl, 0.080” thick, integrated color, (4” or 6”?) high wall base with a straight profile.
1.2. Install wall base in accordance with manufacturer’s guidelines.
2. Transition Strip:
2.1. Vinyl, glue down, ADA compliant transition strips from the same manufacturer of either the carpet or wall base for the following conditions:
2.1.1 Carpet to 1/8” tile
2.1.2 Carpet to carpet
2.1.3 Carpet to floor reducer
2.2. Install transition strips in accordance with manufacturer’s guidelines.