REPAIR_MONITORING_WELLS_Questions_set_1.pdf

PDF 47 KB Posted

Attached to
Repair Monitoring Wells
Solicitation number
FA462619RA005
Issued by

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR MONITORING WELLS – Questions Set 1

1) Would horizontal directional drilling be an acceptable installation method for the 1 ¼” discharge pipe? If so, would it be acceptable to slightly modify the route of the pipe to accommodate a single bore without a 90 degree turn?

Yes horizontal directional drilling would be acceptable and changing the discharge line route to accommodate shallower bends can be worked out. Please include installing a tracer wire with the line in the bid if this installation method is proposed.

2) Due to the fact that the site drawings are not to scale, can an estimation of discharge pipe footage be provided?

These estimations are based off the proposed discharge pipe locations shown in the drawings.

F-03 estimated to be 225’ F-04 estimated to be 175’ G-10 estimated to be 225’ J-03 estimated to be 230’ J-05 estimated to be 225’

File details come from the government source that posted it.