REPAIR MONITORING WELLS – Questions Set 1
1) Would horizontal directional drilling be an acceptable installation method for the 1 ¼” discharge pipe? If so, would it be acceptable to slightly modify the route of the pipe to accommodate a single bore without a 90 degree turn?
Yes horizontal directional drilling would be acceptable and changing the discharge line route to accommodate shallower bends can be worked out. Please include installing a tracer wire with the line in the bid if this installation method is proposed.
2) Due to the fact that the site drawings are not to scale, can an estimation of discharge pipe footage be provided?
These estimations are based off the proposed discharge pipe locations shown in the drawings.
F-03 estimated to be 225’ F-04 estimated to be 175’ G-10 estimated to be 225’ J-03 estimated to be 230’ J-05 estimated to be 225’