RFI # Specification Section/Drawing Number Question Response Date Ret'd Code
1 02072 Part 1, 1.1.B.3 This section references specification section 03002, Concrete however, this section is not included in the specifications. Please clarify.
Paragraph 1.1.B.3 is hereby removed from the specification 02072.
2 02221 page 3 section 3.2.C.8 This section asks to include dewatering in the lineal foot price of the conduit/ductbank installation. The bid sheets do not contain a pricing item ofr this. Please clarify.
There is very little open trench in this project, as most of the underground conduit is installed by the directional boring method. The transitions between borings would have some open trench for which dewatering could be necessary. Please include the cost of dewatering in Contract Line Item Number 0001 for the Fiber Optic installation.
Solicitation Section B pricing Item 0001 refers to horizontal boring for the fiber optic installation.
Speicfication Sections 02221 & 16150 refer to trenching/excavation for untilities. There is no specification for horizontal boring. Please clarify.
A specification for Horizontal Boring has been added.
See new specification section 02507 Utility Directional Drilling
Design of Energy Monitoring and Control System Drawings Page 29 of 214 (Typical)
Please define ATFP.
Anti-Terrorism Force Protection (ATFP) is any increased security measure that would protect against a Terror attack.
Design of Energy Monitoring and Control System Drawings Page 29 of 214 (Typical)
Please clarify "Install New Niagara JACE Building Controller Front End." Is the intent of this statement a new JACE per call out or a connection to the Web Supervisor?
The statement "Install New Niagara JACE Building Controller Front End" will require that a new JACE be installed.
6 Design of Energy Monitoring and Control System Drawings Page 182 of 214
Is Building 1154 connected to 1466 as inidicated on this drawing?
The reference to Building 1154 on drawing page 182 should be Building 1466.
7 Design of Energy Monitoring and Control System Drawings Page 181 of 214 Is Building 1441 connected to this building as indicated? The reference to Building 1441 on drawing page 181 should be Building 1466.
8 Design of Energy Monitoring and Control System Drawings Page 188 of 214 Can this building use JACE I/O or is Delta I/O requested?
Building 1845 requires a new JACE and a new Building Controller. The building devices shall be controlled thru the Building Controller I/O. The communication over the network shall be managed by the JACE I/O.
9 13402-3 2.2 EMCS Software Tridium provides options for up to 5 years of Software Maintenance Agreements. Is this acceptable?
The requirement has been reduced from 10 years to 5 years of Software Updates in Specification 13402, 2.2 A.1.
10 13402-3 2.2 EMCS Software Niagara N4.4 is currently stable and has received approval at other DOD installations. N4.6 is expected this summer but does not have approval. Is N4.4 acceptable?
In order to maintain compabiblity with existing control systems on base, the new JACE's will require that they be downgraded to version 3.8.
11 13402-3 2.2 EMCS Software
Niagara requires the Web Supervisor to be at the revision of the highest JACEs installed in the field. Will the server/Web Supervisor be upgraded prior to this work commencing?
The contractor shall modify the Web Supervisor as necessary to allow new systems to be added to the Central Controller.
12 13402-3 2.1 EMCS Hardware Spec calls out PCMCIA, is USB acceptable alternative? Both PCMCIA and USB are acceptable. Specification 13402 has been revised to allow both.
13 General Do any of the building have restricted work hours associated with them. If so, which buildings and what are the hours of work?
Buildings do not have restricted hours, however multiple buildings require scheduled access and escorted entry.
All dormitory facilities are by escorted entry only, as well as building 1845.
14 General
Have the buildings involved in this project been examined and tested for asbestos, lead paint or any other harmful items that may affect the installation scope of work? If so, please provide a list of buildings and planned remediation (responsibility).
Generally, areas have already been tested and cleared of asbestos and lead based paint. If suspect materials are encountered during construction the Government will add to the contract for testing and abatement.
15 13402-3 2.1 EMCS Hardware Is there a basis of design for the actual JACE equipment?
Nothing is noted. A specification for the JACE has been added.
In regards to Section 15903, Part 1, 1.8 Approved Manufacturers, A. Systems shall be limited to Delta, Honeywell, or Tridium. Is there a process I can submit or can I request to have Distech Controls added to this section?
Distech Controls are acceptable and have been added to Spec 15903
17 6. Does the current EMCS system have an ATO? The current EMCS system does not have Authority to Operate (ATO). The application is being processed.
18 7. Who will be responsible for ensuring this work will meet current ATO requirements?
The Government will ensure this work meets ATO requirements. The contractor will provide information as needed to respond to ATO requirements.
19 8. Who will modify the existing ATO for the additional equipment and configurations under this contract?
The Government will request ATO approval for the newly installed systems.
20 9. Will RF (DISA APL approved wireless) be an acceptable alternate to fiber in challenged locations?
Radio Frequency wireless systems have been determined to be a security risk and are not allowed.
21 Question: Is the cable daisy chained? Answer: It does extend building to building 22 Question: Do we have HSQ in other buildings? Answe: Yes
Question: Who is responsible to Patch the network back?
Answer: The contractor is responsible to maintain the existing HSQ network at each building so that it continues to operate at nearby buildings.
Question: Is is corrrect that we cannot pull the pannels off?
Answer: The panels that have existing network cabling cannot be removed. The modem in the panel must remain operational and the existing fibers that are to/from the building must remain operational.
Question: Can we establish a graphic standard?
Answer: The new graphics installed as a part of this contract shall be compatible with the existing control graphics.
Question: Is the base standard not to insulate valves?
Answer: If equipment is insulated before you replace it it must be reinsulated. If it was not insulated before it was replaced it does not need insulation.
27 Question How far after the bid date do we expect to send notice to proceed? Answer: It may take as long as the bids are good for
28 Question: Is it true that the contractor provides the switches and the base configures them?
Answer: The contractor will provide the media converter and the base would do the set up on the media converter.
29 Clarify the fiber optic route for Bldg 735 on Drawing page 6 of 214.
On Drawing 6 of 214, Note 12 near building 735 is referencing Line 12 of the table on page 7 of 12. The table calls for new conduit with underground directional boring method and fiber optic cable installed to the ground box in the yard. Note 11 on Drawing 6 of 214 calls for the fiber optic to continue in existing conduit to Building 740. Bldg 740 has existing network, which is to be connected to Bldg 735 as a part of the scope of this contract.
Question: what is to be done with Pneumatically Controlled Valves?
Answer: The control mechanism for all pheumatically controlled valves is to be replaced with a digitally controlled electric actuator. It is acceptable to retrofit the existing valve with a new control mechanism, or replace the entire valve with a new digitial controlled mechanism on it.
Question: Is there a base wide control to shut down all air handlers?
Answer: Yes there is a one touch button that shuts off intake air.
32 Site Visit/Attachment 8 In reference to the due date extension request: will the dates listed in attachment 8 also be adjusted?
Yes, the Past Performace Questionnaire (attachment 8) will be due when the propsals are due.
Page 45 of 56; Section 4.1 General - Along with the information required in this paragraph, the offeror shall submit a consent letter (attachment 9) executed by each subcontractor, teaming partner, and/or joint venture partner, authorizing release of adverse past performance information to the offeror so the offeror can respond to such information. For each identified effort for a commercial customer, the offeror shall also submit a client authorization letter, authorizing release to the Government of requested information on the offeror's performance.
Do contractors need to have Attachment 9 completed by all subs, teaming partners, etc…or just from the ones that meet what is stated in the paragraph just above that statement that refers to: "Each offeror shall submit a past performance volume with its proposal, containing past performance information in accordance with the format contained in Attachment 8. This information is required on the offeror and all subcontractors, teaming partners, and/or joint venture partners who are proposed to perform 25% percent or more of the proposed effort based on the total proposed price or perform aspects of the effort the offeror considers critical to overall successful performance."
Attachment 9 will need to be completed by all subcontractors or teaming partners
34 Section 01000 General Requirements,3.24 Project Fence
Section 3.24 requires a 6' high chain link fence "around project site" As this project contains multiple buildings at multiple locations does the government want fencing around each building? Around excavated areas only?
Please clarify.
Fencing is required only at areas that are open excavated and at the material storage site.
Section 01000 General
Requirements,3.17 Quality Control B.3.
& 3.e
B.3 requires a full time QC Manager with no other assigned functions. 3.e describes the safety program under the QCs responsibilities. This implies the QC Manager may also be the Safety Officer. Please clarify if the QCM may also be the SSHO.
The QC manager may also be the Safety Officer.
Attachment 1, Specifications Section 3.8
Submittal Schedule, Items 13402-001 through 13402-006
These items are to submitted with the proposal. Which volume do they go in and is there a page limit for each of these?
Specification 13402, page 17, table 3.8 Submittal Schedule has been revised to have the deliverables due after award.
37 Drawings
Can a conrol valve schedule be issued designating which valves are penumatic (full replacement) versus electric valve actuators are remaining and which need only actuator replacement?
The contractor shall determine the requirement to convert the existing pneumatic control equipment to direct digital control.
38 Site discussion Will the base be responsible for the Cybersecurity or will this be part of the contract proposal work? If the latter please provide a scope of work & specifications for Cybersecurity.
The Government will request ATO approval for the newly installed systems. The Government will ensure this work meets ATO requirements. The contractor will provide information as needed to respond to ATO requirements.
39 Cybersuricty What standard is to be used for Cybersecurity? IEC62443?
The cybersecurity requirements are spelled out in Specification 13402.
40 Media Converter Please confirm Media Converter part number. We believe there may be a missing "E" at the start of the part number.
The reference to the Media Converter is hereby revised to Startech MCMGBSCSM10 or equal.
41 Hot Water Meter Installation What is the verification specification for the hot taps on this meter?
The contractor is required to hire qualified welder(s) for high temperature water pipe welding (400 deg F). The contractor shall ensure that welds are failsafe.
42 Equipment Inuslation Please provide the insulation specification for valve, meters, hot tap insulation where these items are replaced or added.
Provide fiberglass insulation and cover/wrap that will provide a touch temperature of less than 120 deg F on pipe and equipment that is 350 deg F.
43 Equipment Insulation Where valves, etc. are not currently insulated, is there a requirement for adding insulation as part of ths project?
Existing valves that are not insulated will remain un-insulated, and likewise if the existing valve is insulated it will remain insulated.
44 Equipment Insulation It was observed on the walk through that some of the equipment, valves, etc. had removable insulation installed.
Is this acceptable for use of these devices for this project?
Removable insulation for valves and equipment is acceptable.
45 Are all existing BACnet controller points list available and current for integration?
The existing BACnet controller points lists are available on the existing server. The contractor will have access to these points for integration with the new BACnet controllers.
Does the base currently have a graphics standard for their BMS systems? If not, will all graphics associated with this project be standardized?
The new graphics installed as a part of this contract shall match the existing control graphics.
Air Flow Monitoring: the specifications state that at each fan inlet and exit of the inlet fan air flow shall be monitored.
We haven’t seen this on the drawings points list or sequence of operations, please confirm this is not used.
No new air flow monitoring is to be installed as a part of this contract. If air-flow monitoring is already present at a site the contractor shall maintain the air-flow monitoring in the new control system.
Will the base be able to provide all Login and Administrative access to any JACE’s being re-used or upgraded as part of this project?
The base will provide access to existing equipment as needed.
Can we please obtain a list of all the existing JACE’s and their software versions that reside on the base?
This information will have to be acquired by the contractor. The Government will assist in obtaining this information after the contract is awarded.
50 Will cyber security insurance be required as part of this projeCyber security insurance will not be required as a part of this project.
The specifications say that “each controller shall have a minimum of 8 inputs”, as many zone level-controlled units such as one exhaust fan or a unit heater will use far less than 8 inputs and would still have expandability, can a controller with less inputs and outputs be used?
8 inputs is the minimum required for future expandability.
52 It is assumed that splicing will not be allowed in the event wiring is to be reused, please confirm? Splicing of wire is not allowed.
Based on the age and condition of the wiring identified in the buildings is it recommended that all wiring be replaced as part of this project, Would the base like all wiring removed and replaced as part of this project?
Point to point wiring may be reused to the maximum extent possible.
54 It is assumed that all new wiring can utilize existing raceways, please confirm? Existing raceways may be reused.
The specifications say, “actuators shall provide position feedback to the controller”. Does this mean an extra set of wires or can this be calculated? And is this for major central-plant and zone level controllers (unit heater or exhaust fan)
Actuators require a hardwired feedback to determine their actual position.
56 It is assumed that, as a base standard, all wiring is required to be in conduit, please confirm? All wiring is to be in conduit.
Given that the EMCS will already be in place during construction, is a support radius of 100 miles acceptable
A support radius of 200 miles is acceptable.
The drawings reference a lot of new and existing utility meters, can you provide a list of meters that are to be reused and a list to be replaced for Electrical, Natural Gas, Water, Domestic Water, and BTU.
All meters are to be new to provide a readable pulse to the new building controller. Existing Meters may not provide a pulse output that can be digitally read.
The drawings call for a display for the electric meters, is the desire for the information to be displayed on the front end of the BMS?
The system shall display electric consumption at the Central Control system.
Submittals are to show the integrated existing control system. Are we able to get a digital usable copy of the existing submittals?
The existing control system data will be provided to the Contractor. The data is not digitally available.
In review we haven’t seen that any dampers will be replaced, can you confirm?
Dampers are not being replaced as a part of the scope of this contract. Actuators are to be replaced where necessary to provide control capability with the new system.
If, after all pre-bid questions have been answered, there is a discrepancy on the drawings between the points list and sequence of operation schematic, which one should we base our bid off of?
Default to the sequence of operations.
One of the biggest discrepancies on the drawings between the points list and sequence of operations schematic is the number of valves. We have primarily seen this on the larger equipment (AHUs, Central Plants) rather than terminal units. Can you clarify what valves are existing and if they are modulating or 2 position control?
Generally, valves are existing and only need be converted to digital control. The contractor shall verify if a specific valve is modulating or 2 position control.
64 Is the intent of the project to replace all existing valves and actuators or are we to reused the existing?
Reuse exsiting valves/actuators to the extent that they are compatible with the new controls system.
Is it correct to assume that all room temperature sensors are to be provided with a display and override capabilities except for those in common areas (hallways, cafeterias, etc) where it would be more feasible to use a flat stainless steel wall plate temperature sensor?
Acceptable as proposed.
On the drawings for many of the buildings there is a note on the points list that says, “Provide for each of 4.” Can you clarify what this note means? It is unclear whether that means there are four total units or if there are 4 points that should be combined onto one controller.
The note refers to the number of total units (for example 4 pumps)
67 For pneumatic demo, is the intent to cap it in place or remove it in its entirety? Remove pneumatic controls in their entirety.
68 Who is responsible for the pneumatic demo? The contractor is repsonsible to remove the pneumatic control systems.
The points lists on the drawings have DP sensors across all of the pumps, is the intent for these to provide pump status in lieu of a current sensing relay?
The Differential Pressure (DP) sensors will provide pump status. Current sensing relays are an acceptable alternative to DP's.
For buildings with Fin Tube Radiators, is there a valve for each of the radiators or are there cases where multiple radiators are controlled off of one valve? For reference buildings B735 and B220.
Generally, there is 1 valve per thermostat. There may be multiple fin tubes controlled by a single valve.
1. Will new electric actuators be allowed to replace old pneumatic actuators? In phase one this was not allowed, and new valves were required.
It is acceptable to replace the existing pneumatic actuators with electric digital actuators and leave the existing valve in place.
72 2. Will x-ray inspection be required on welds on HTHW lines to install BTU meters?
Third party testing of welds are not required. The contractor shall use licensed qualified welders for this project.
w
3. Will Testing, Adjusting, and Balancing be required, and if so, will it be required before and after required before and after
Testing, Adjusting and Balancing will be required at the completion of each building control system replacement.
74 4. Would you desire to have the new Jaces use N4 version or the existing Jace AX version?
New JACES shall have version 3.8 to be compatible with existing JACES and the central control system.
5. If an upgrade is desirable and N4 software is used on the new buildings the Web Supervisor would need to be upgraded to N4 as well. The existing system uses PxImport tags at the Jace level to import graphics to the Web Supervisor. Should an upgrade of the existing system also be included in the pricing?
The upgrade will not be performed under the scope of this contract.
6. The existing Jace 700’s would have to be individually tested to confirm that they are upgradable to N4 or they should be replaced if the test fails. Is replacement within the budget of this project since no mention of the existing system was in the scope of the project? Provide new JACES with the existing version 3.8.
77 7. Which CLIN item should be used for an N4 upgrade to the existing system if this is desired? No upgrade under this contract.
8. 2.30 OUTPUT DEVICES, VALVES AND DAMPERS.
States that all dampers and valves feedback signals are to be wired back to the control panel terminal strip. Do they need to be wired to an input of a controller?
Feedback signals for all devices shall be wired to an input of a controller.
9. The ATFP system code requirements are not listed in the References 1.1. Is the current ATFP method of implementation acceptable?
The current ATFP method of implementation shall be acceptable.
80 10. What is the temperature and pressure that the new valves on the HTHW system must be rated for? Minimum 400 deg F and 400 psi rated valves.