This is a Statement of Work (SOW) for asbestos mitigation, encapsulation, and HVAC cleaning at Building 1207, Fairchild Air Force Base, Washington, dated May 19, 2026.

The contractor must provide all labor, materials, equipment, and certified personnel to perform professional asbestos mitigation, surface decontamination, and floor encapsulation in two adjacent rooms (approximately 75 and 400 square feet). The work addresses asbestos-containing material (ACM) in floor tile and mastic that was disturbed during carpet removal in early 2026. Key requirements include: (1) site preparation and containment using heavy-duty polyethylene sheeting and HEPA-filtered negative pressure systems; (2) comprehensive surface decontamination of all horizontal and vertical surfaces using HEPA-filtered vacuums and wet-wiping with approved cleaning agents; (3) flooring mitigation involving assessment of all tiles, removal of loose or damaged tiles, application of industry-approved asbestos-specific binding primer/sealant, and installation of self-leveling underlayment compound to encapsulate the ACM; and (4) specialized HVAC system cleaning of ductwork, registers, diffusers, and air handling equipment in compliance with EPA, OSHA, and local asbestos abatement regulations, including replacement of air filters with HEPA-rated filters to meet EPA NESHAP, WAC 296-62, and SRCAA standards. All asbestos-containing waste must be properly packaged, labeled, and disposed of at NESHAP-approved landfills.

Pre-work submittals include valid Washington State Asbestos Abatement Contractor License, AHERA certifications for all on-site workers and supervisors, a completed Notice of Intent filed with Spokane Regional Clean Air Agency (work cannot begin until the 10-day notification period elapses), a site-specific work plan, and manufacturer specification and safety data sheets for all proposed materials. Post-work submittals, due within ten working days of project completion, include a final air clearance report from a third-party AHERA-certified Project Designer demonstrating all areas are below 0.01 f/cc clearance level, waste manifests and landfill receipts, and a project summary with daily logs and photographs. The contractor must also submit all hazardous materials for approval at least fourteen days prior to work commencement, report hazardous material usage annually, maintain secure storage of hazardous materials, and remove all hazardous materials at project end. Access coordination and report submissions are directed to Captain Jacob Perry or Master Sergeant Blackmon.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Asbestos Mitigation, Encapsulation and HVAC Cleaning, B1207

Fairchild AFB, WA 19 May 2026

OVERALL OBJECTIVE

The objective of this contract is to provide all labor, materials, equipment, and all certified personnel necessary to perform professional asbestos mitigation, surface decontamination, and floor encapsulation in two specified rooms. This work will mitigate the asbestos hazard and prepare a safe, stable substrate for the subsequent installation of new hard rubber matting flooring (flooring will be installed under a separate effort).

SECTION I - BACKGROUND INFORMATION

1.1. In early 2026, carpet was removed from two adjacent rooms (approx. 75 sq. ft. and 400 sq.

ft.) within B1207, disturbing the underlying flooring system.

1.2. A previous asbestos survey confirms that the floor tile and associated mastic are Asbestos- Containing Material (ACM).

1.3. This project will serve as the formal decontamination and abatement action for the disturbed

ACM.

SECTION II - REQUIREMENTS

2.1 Site Preparation and Containment

a. Isolate the two affected rooms by establishing critical barriers over all doors, windows, and openings using heavy-duty polyethylene sheeting.

b. Establish negative pressure within the work area using HEPA-filtered air filtration devices ensuring no cross-contamination to adjacent spaces.

c. Isolate the HVAC system in the affected work areas to prevent operation during the mitigation process.

2.2 Surface Decontamination

a. Perform a comprehensive decontamination of all horizontal and vertical surfaces within the two affected rooms.

b. Utilize HEPA-filtered vacuums on all surfaces to capture settled microscopic dust and potential asbestos fibers.

c. Perform a thorough wet-wiping/wet-mopping of all surfaces using approved cleaning agents in the two affected rooms.

2.3 Flooring Mitigation & Encapsulation

a. Perform a physical assessment of all floor tiles in both rooms. Any tiles found to be loose, delaminated, or significantly damaged must be removed prior to encapsulation.

b. Apply an industry-approved, asbestos-specific binding primer/sealant over the entire floor

FA462026QA288 - Asbestos Mitigation Attach 1 - SOW (Amend 0002)

Pg 1 of 4 surface (both remaining tiles and exposed mastic) to lock down any loose fibers and create a bonding layer.

c. Pour and finish a compatible self-leveling underlayment compound over the primed surface to completely encapsulate the ACM and create a smooth surface ready for future rubber matting installation (rubber matting flooring will be installed via separate effort).

2.4 HVAC System Cleaning

a. Perform a specialized asbestos-compliant cleaning and decontamination of the HVAC ductwork, registers, diffusers, and associated air handling equipment serving the two affected rooms for the whole system using approved asbestos abatement methods to ensure no residual asbestos contamination remains.

b. All HVAC cleaning and decontamination activities must be performed in strict compliance with current EPA, OSHA, and local asbestos abatement regulations. Contractor shall determine and employ the appropriate, compliant methods for extraction and containment.

c. Replace air filters with new HEPA-rated air filters. The existing HVAC configuration at B1207 is a standard supply/return system with no HEPA filtration or engineered controls capable of capturing asbestos fibers. Contractor shall provide a full-system duct cleaning that is required to meet EPA NESHAP, WAC 296-62, and SRCAA standards.

2.5 Waste Management

a. All materials generated during this project, including but not limited to removed floor tiles, used PPE, disposable cleaning supplies, and spent HEPA filters, shall be managed as asbestos-containing waste.

b. The Contractor shall be responsible for the proper packaging, labeling, and transport of all asbestos-containing waste. All waste must be double-bagged or sealed in leak-tight containers, display the proper asbestos warning labels, and be manifested for lawful disposal at a NESHAP-approved landfill.

SECTION III – QUALIFICATIONS & SUBMITTALS

3.1 General

a. All submittals shall be provided in a clearly labeled PDF format.

3.2 Pre-Work Submittals

a. Prior to the start of any on-site work, the Contractor shall submit the following to the Government PM for review and approval:

i. Licenses & Certifications: A copy of the company's valid Washington State Asbestos Abatement Contractor License and copies of the AHERA certifications for all workers and supervisors who will be on-site.

ii. SRCAA Notice of Intent (NOI): A copy of the complete and filed "Notice of Intent" submitted to the Spokane Regional Clean Air Agency (SRCAA). Work may not begin until the 10-day notification period has elapsed.

iii. Site-Specific Work Plan: A comprehensive plan detailing containment strategies, negative air calculations, decontamination procedures, and the specific methodology for the HVAC system cleaning.

FA462026QA288 - Asbestos Mitigation

Pg 2 of 4

iv. Material Data: Manufacturer Specification Data Sheets and Safety Data Sheets for all proposed primers, sealants, and self-leveling compounds.

3.3 Post-Work Submittals

a. Within ten (10) working days of project completion, the Contractor shall submit a single, comprehensive Project Closeout Report. This report shall include, at a minimum:

i. Final Air Clearance Report: The full lab report from a third-party, AHERA-certified Project Designer demonstrating that aggressive air sampling has been conducted and that all areas within the containment are below the clearance level of 0.01 f/cc.

ii. Waste Manifests: Copies of all waste manifests and landfill receipts proving lawful disposal of all asbestos-containing waste.

iii. Project Summary: A brief summary of work performed, including daily logs and photographs.

SECTION IV - HAZARDOUS MATERIALS MANAGEMENT PROGRAM (HMMP)

4.1 Hazardous Material Authorization

The Contractor shall be responsible for the proper storage, management, and disposal of any hazardous material brought on Base for contractor use. The Contractor shall use non-hazardous materials whenever possible. All hazardous materials must be approved by the HMMP Team prior to being brought onto the installation. The Contractor shall submit a list of all hazardous materials intended for use during the performance of the contract, along with corresponding manufacturer’s Global Harmonized System compliant Safety Data Sheets (SDS), to the HMMP Team, through the Contracting Officer (CO), at least fourteen (14) days prior to beginning work or bringing hazardous materials onto the installation. The listing shall include product name, chemical type, quantity to be brought onto the installation, and process for which it will be used.

The contractor shall submit this information to the CO using the Contractor Hazardous Material Authorization and Use Form and attach the corresponding SDSs. If during the course of the contract, items not previously identified are to be brought on the base, the Contractor shall submit an updated Contractor Hazardous Material Authorization and Use Form and SDS for approval prior to bringing the HAZMAT onto the base.

4.2 Hazardous Material Usage

Contractor shall report quantity of each hazardous material used on the base by submitting a Contractor Hazardous Material Authorization and Use Form to 92 CES/CEIE via the Contracting Officer. Submit one report for each calendar year of project performance no later than 1 December of that calendar year, or prior to project closeout, whichever occurs earlier.

4.3 Hazardous Material Storage

Hazardous materials shall be stored within a locked secure area not accessible to the base populace after hours. All containers of hazardous material shall be clearly and properly labeled;

closed when not in use; and stored in an upright, secure position.

4.4 Hazardous Material Empty Containers

Hazardous material containers cannot be disposed of in base dumpsters. WAC 173-303-160

FA462026QA288 - Asbestos Mitigation

Pg 3 of 4 defines what is considered an empty container. Any hazardous materials wasted, must be managed as hazardous waste.

4.5 Hazardous Material Removal

The Contractor is responsible for removal of their hazardous materials. No hazardous material shall be left on-site at the end of contract. Touch-up/repair material shall not be provided to the user unless pre-approved by the 92 CES/CEIE Hazardous Material Management Process (HMMP) Team prior to the end of the project.

SECTION V - ADDITIONAL INFORMATION

1. Access to building 1207 shall be coordinated with the Project Managers, Capt Perry or MSgt Blackmon, by email at jacob.perry.10@us.af.mil, casey.blackmon@us.af.mil, or by phone at 509-247-1191 or 509-247-3518.

2. Report submissions shall be delivered to (or via email):

336 TRSS/LG

Captain Jacob Perry 1067 W Survival Loop, Bldg. 1249 Fairchild AFB, WA 99011

FA462026QA288 - Asbestos Mitigation Attach 1 - SOW (Amend 0002)