25QA913 Amend 0004.pdf

PDF 603 KB Posted

Attached to
Bldg 2036 Asbestos Abatement
Solicitation number
FA462025QA913
Issued by

About this file

This is Amendment 0004 to solicitation FA462025QA913 issued by the 92nd Contracting Squadron at Fairchild AFB for asbestos abatement services in Building 2036. The amendment, effective January 2, 2025, addresses a contractor question regarding boiler line operations during the abatement process, clarifying that the boiler lines will not be shut off during the work.

The amendment requires contractor acknowledgment and signature in blocks 15a, 15b, and 15c to be returned with their proposal. The amendment does not extend the proposal submission deadline. The contracting officer for this action is Kathleen L. Rauch, and the work is being procured by the Department of the Air Force Air Mobility Command.

View the file

Other files

File Type Posted
25QA913 Amend 0003.pdf PDF
25QA913 Amend 0002.pdf PDF
25QA913 Amend 0001.pdf PDF
25QA913 Attach 2 - WD 2015-5537 Rev 23.pdf PDF
25QA913 COMBO.pdf PDF
25QA913 Attach 1 - SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXCEPTION OF SF 30, APPROVED BY NARS 5/79

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

FA462025QA913

PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

2 January 2025

4. REQUISITION/PURCHASE REQ. NO.

5. PROJECT NO. (If applicable)

6. ISSUED BY

CODE

FA4620 7. ADMINISTERED BY (If other than Item 6)

CODE

92nd Contracting Sq./PKA 110 W Ent St., Suite 200 SAME AS BLOCK 6 Fairchild AFB, WA 99011 Attn: kathleen.rauch@us.af.mil

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) () 9A. AMENDMENT OF SOLICITATION NO.

X

FA462025QA913

All Offerors 9B. DATED (SEE ITEM 11)

12 December 2024

10A. MODIFICATION OF CONTRACT/ORDER

NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[X] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [X] is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning _1_ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor [] is not, [X] is required to sign this document and return _1_ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SEE SUMMARY OF CHANGES

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10 A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

KATHLEEN L. RAUCH, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

NSN 7540-01-152-8070 30-105-03 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

FA462025QA913

Amendment 0004 Page 2

SUMMARY OF CHANGES

The purpose of this Amendment is to answer contractor question:

Q1. Will the boiler lines be able to be shut off during the abatement process, or will they have to remain on?

A1. The boiler lines will not be shut off during the abatement process.

All other items remain unchanged.

Fill out blocks 15a, 15b, and 15c and provide a copy with your proposal.

END SUMMARY OF CHANGES

File details come from the government source that posted it. Updated .