25QA913 Attach 1 - SOW.pdf
PDF 512 KB Posted
- Attached to
- Bldg 2036 Asbestos Abatement
- Solicitation number
- FA462025QA913
About this file
This Statement of Work (SOW) outlines requirements for asbestos abatement services at Building 2036 on Fairchild AFB, WA. The contractor must remove and properly dispose of asbestos containing material (ACM) from 3 mudded fittings in the mechanical room to facilitate valve replacement, with insulation to be removed 3ft on both sides of each valve (27 total linear feet). Encapsulation is not authorized.
The contractor must provide asbestos-certified personnel, develop a detailed work plan including floor plans and documentation, notify the Spokane Regional Air Agency as required, and comply with all federal, state and local regulations including EPA, OSHA, DOT and Air Force Instructions. Work must begin within 30 days of award, with operations permitted Monday-Friday 0700-1630 excluding federal holidays. The mechanical room work area is approximately 20ft high, and the government will remove office furniture and provide utility access. The facility has had no asbestos abatement in the last calendar year.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25QA913 Amend 0004.pdf | ||
| 25QA913 Amend 0003.pdf | ||
| 25QA913 Amend 0002.pdf | ||
| 25QA913 Amend 0001.pdf | ||
| 25QA913 Attach 2 - WD 2015-5537 Rev 23.pdf | ||
| 25QA913 COMBO.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
BLDG 2036 ASBESTOS ABATEMENT
November 2024
FA462025QA913
Attachment 1 - Statement of Work
Statement of Work (SOW) For
Bldg 2036 Asbestos Abatement at Fairchild
AFB, WA
1. DESCRIPTION OF SERVICE: The contractor shall provide all necessary tools, equipment and materials required by law to provide clean-up and removal of asbestos containing material (ACM) in building 2036 on Fairchild AFB, WA.
2. SCOPE OF WORK: The Contractor shall complete all work, which includes furnishing all supervision, labor, material, equipment and services, unless otherwise specified herein, required under this contract. All work shall be performed in accordance with all Federal, State, local laws and regulations, manufacturer’s recommendations and this Statement of Work (SOW).
- Contractor shall provide appropriate asbestos certified personnel to properly abate and dispose of asbestos containing materials from 3 mudded fittings to facilitate valve replacement in the mechanical room of B. 2036.
- Contractor shall properly remove and dispose of all asbestos containing material from the 3 identified fittings to reveal the valves underneath. Encapsulation is not authorized.
- No asbestos abatement has occurred in this facility within the last calendar year.
- Contractor shall develop a detailed work plan. This work plan shall consist of, as a minimum, the scope and location of work performed, floor plan of the worksite noting locations of asbestos abatement, photographs of the worksite, notification records, air monitoring test records, employee training records, and waste shipment records.
- Contractor shall notify the Spokane Regional Air Agency as required.
- Office furniture will all be removed by the government prior to start of work.
- All asbestos removal shall comply with 40 CFR 61 and 763 (U S EPA), 29 CFR 1910.1001
1926.1101, 1910.134 (OSHA), 49 CFR 172-177 (Dept. of Transportation), SRCAA Regulation I Article IX, Washington Administrative Code (WAC) Chapters 296-62 and 296- 65, Department of Labor and Industries regulations, and applicable Air Force Instructions (AFIs).
3. GOVERNMENT FURNISHED PROPERTY AND SERVICES: The government will provide access to utilities as needed.
4. GENERAL INFORMATION
4.1. HOURS OF OPERATION: Hours of operation are 0700-1630 Monday through Friday, excluding Federal Holidays and any other designated down day. Work can be done at other than the normal hours of operation with the approval of the Contracting Officer. The contractor shall coordinate in advance all hours of work and any service interruptions with Civil Engineering points of contact.
4.2. SECURITY REQUIREMENTS: All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations.
5. PERFORMANCE PERIOD: Performance shall begin within 30 days after date of award
6. APPENDICES:
Appendix A: Facility Floor Plan and Location of Work Area Appendix B: Photos
FA462025QA913
All fittings located in Mechanical Rm. Approx. 20ft high
Appendix A: Facility Floor Plan and Location of Work Area
Appendix B: Photos