RFI_Q-A_Responses.docx
DOCX document 27 KB Posted
- Solicitation number
- FA461025Q0009
About this file
This is a Questions & Answers document for RFQ FA461025Q0009 regarding window cleaning and janitorial services at Vandenberg SFB, providing specific details about the scope of work. The document clarifies that carpet cleaning is required for approximately 4,000 SF in Building 1746 and 516 SF across floors 3, 4, and 7 in Building 1748, with steam/shampoo cleaning specified. For window cleaning, there are 87 total windows to be cleaned, including 27 large windows of varying sizes and 2 glass doors. The tower stairwell exterior windows do not require cleaning, and no bathroom cleaning is included in the scope.
The associated solicitation is a 100% Small Business Set-Aside under NAICS 561720 with a $22M size standard, structured as a Firm Fixed Price contract. A site visit is scheduled for February 5, 2024, at 9:30 AM PST at the Vandenberg SFB Airfield, with base access requests due by February 4. Quotes must be submitted via email by February 12, 2025, at 12:00 PM PST to the specified contracting officers. The work encompasses three separate buildings at Vandenberg SFB, with services including window cleaning, dusting, and stairwell cleaning, plus carpet cleaning in two buildings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12949 Bldg 1748 Tower Room Layouts .eall.pdf | ||
| 12949 Bldg 1746 Flight Line Office Layoutss.eall.pdf | ||
| Atch_01_SOW_AF_Windows_22-Mar-2025.docx | DOCX document | |
| Solicitation - FA461025Q0009.pdf | ||
| Atch_03_Technical Experience Questionnaire_20250203.docx | DOCX document | |
| Atch_02_WD_20250203.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
30 OSS Airfield Window Cleaning & Janitorial Services - FA461025Q0009 Questions & Answers
1. What is the total square footage of the carpet area needing cleaned?
a. Building 1746: Approx 4,000 SF
b. Building 1748 floor 3, 4 & 7: Approx 516 SF.
See attached CAD drawings for each Building/rooms
2. Do all of the exterior of the windows of the tower stairwell need cleaning as well?
a. No.
3. What is the total number of windows that need to be cleaned from the airfield building?
a. 87 total windows; 27 of them are large of varying size including 2 glass doors.
4. Is information regarding the specific size of the windows available?
a. No.
5. Do any bathrooms need cleaning? If so, how many?
a. No.
6. What type of cleaning do the carpets need?
a. Steam/shampoo cleaning.
File details come from the government source that posted it. Updated .