This document is a request for quote for portable toilet leasing and servicing at Vandenberg Space Force Base in California. The solicitation seeks quotes for supplying, delivering, servicing, and removing portable toilets and hand wash stations on a short-term and long-term rental basis. Quotes are due by February 8, 2023, with the contract to be awarded on a firm fixed price basis. The performance work statement outlines requirements for unit specifications, ordering and scheduling, delivery and placement, servicing, relocation, removal, and quality control. The appendices provide historical unit usage data and maps of the base locations.

View the file

Other files for this federal contract opportunity

Other files attached to Portable Toilet Leasing Vandenberg Space Force Base, newest first.
File Type Posted
Solicitation - FA461023Q00020001.pdf PDF
Portable Toilet QA 20230201.pdf PDF
Attch 7 - Portable Toilet Pre-Invoice BLANK.xlsx XLSX spreadsheet
Attch 5 - Pricing Schedule.xlsx XLSX spreadsheet
Attch 2 - SCA WD 2015-5647 Rev 17.pdf PDF
Attch 4 - Teaming Arrangement Questionnaire.docx DOCX document
Attch 3 - Technical Questionnaire.docx DOCX document
Attch 6 - PWS Appendix D - Environmental Specs.pdf PDF
Solicitation - FA461023Q0002.pdf PDF
Attch 1 - FY23 PWS Portable Toilets.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

PORTABLE TOILET RENTAL

& SERVICE CONTRACT

Vandenberg Space Force Base, California

7 February 2023 i

TABLE OF CONTENTS

1. DESCRIPTION OF SERVICES 1

Specific Tasks 1 Quality Control 4

2. SERVICE SUMMARY 5

3. GOVERNMENT-FURNISHED ITEMS 6

4. GENERAL INFORMATION 6

Rental Charges / Invoicing 6 Domestic Sewage / Waste Disposal 6 Fines Assessed Against the Government 7 Hours of Operation 7 Security Requirements 7 Environmental Management 8 Customer Complaints 8 Environmental Management 8 Required Reports / Submittals 8

5. APPENDICES

A. Historical Data 10 B. Base Maps 11 C. Sample AF IMT 332 Base Civil Engineering (BCE) Work Request & 12 Sample Permanent Unit List (Separate Document) D. Vandenberg Environmental Requirements (Separate Document)

PERFORMANCE WORK STATEMENT

FOR

PORTABLE TOILET RENTAL & SERVICE

1. DESCRIPTION OF SERVICES. The contractor shall provide all management, personnel, tools, supplies, equipment, materials, and labor necessary to deliver and place, maintain, and remove portable toilets at designated locations at Vandenberg Space Force Base (VSFB), California and remote off-base sites, as required. Services shall be performed in accordance with (IAW) this Performance Work Statement (PWS); applicable commercial/industry standards;

American National Standard Institute (ANSI) requirements (ANSI Z4.3, Section 5, Requirements for Portable Toilet Facilities and Portable Toilet Rooms); Occupational Safety and Health Administration (OSHA) and Environmental Protection Agency (EPA) requirements;

manufacturers’ recommendations; Americans with Disabilities Act (28 CFR, Part 35, Subpart A); and all applicable federal, state, and local laws/ordinances. Contractor shall provide portable toilet rental and service to buildings/areas identified by a Work Request.

[Note: One-way mileage from the Lompoc Gate entrance of VSFB to the northern-most location (Building 1967) is 18 miles; from the Main Gate (Santa Maria Gate) entrance it is 9.5 miles to the eastern-most location (North Star Training Area); and one-way mileage from the South Vandenberg SFB Gate on Highway 246 to the southern-most location (Boathouse Dock) is 14 miles.]

a. Specific Tasks.

(1) Unit Requirements. Contractor shall rent (provide) to the Government portable toilets and hand wash stations that, as a minimum, meet industry standards, ANSI Z4.3, Section 5, Requirements for portable toilet facilities and portable toilet rooms and the following requirements:

(a) Units shall be skid-mounted, trailer-mounted, or American Disabilities Act (ADA) disabled-access units and serviced weekly. Units shall be in new or like-new condition. The contractor shall make all necessary repairs to maintain the units in fully operational condition for the duration of the contract. Each unit will be identified with a unit identification number and the contractor’s name and telephone number.

(b) Standard Toilet Units shall be single stool with interior hand wash that has a minimum 3-gallon capacity, paper towel holder, and a soap/anti-bacterial hand gel dispenser and serviced weekly. The door shall be self-closing, tight-fitting, and shall have an inside lock.

(c) ADA Toilet Units shall be single stool with an anti-bacterial hand gel dispenser and serviced weekly. The door shall be self-closing and shall have an inside lock.

(d) Hand wash stations shall be provided and serviced weekly. Hand wash stations will be provided at Buildings 1768, 1963, and 1993 for mission requirements, these units are rented monthly and are specified on the long-term unit listing. There may be hand wash stations ordered on an as-needed basis.

(2) Unit Ordering and Scheduling. To order portable toilet units, the Government Contracting Officer Representative (COR) shall notify the contractor by electronic mail and provide a Work Request (see Appendix C for sample). A telephone call may be placed to the contractor for requirements periodically. The 30th Civil Engineer Squadron (30 CES) Service Contracts Section are the only personnel authorized to place calls against this contract. CES COR-authorized Work Request shall be the basis for contractor invoicing on this contract.

(a) Within 30 minutes of receiving an email, the contractor shall acknowledge receipt of Work Requests.

(b) At the beginning of every month, the COR will order permanent units (i.e., units that are anticipated to be in place at specified locations on a long-term basis) via Work Request (see Appendix C). With the Work Order, the Government will provide a document to identify the location and quantity of all long-term units this document is identified as the ‘Perm List’.

Additions, deletions, or changes to the previous month’s Perm List unit’s document will be annotated on the new month’s Work Request.

(c) The COR will order Temporary Units via a Work Request. The billing cycle will be on a 30-day basis. If the units are needed longer a new Work Request for Continuation of Service will be issued, or rental dates will be documented on the Work Request.

(3) Unit Delivery and Placement.

(a) At contract award, the contractor shall coordinate the delivery and placement of toilets with the outgoing contractor so that no facility will be without portable toilets.

(b) Contractor shall deliver and place units at the location specified on the Work Request or within 3 hours for routine requests (unless otherwise specified by the government, i.e., by close of business on a specific date) and within 2 hours for emergency same day requests.

For orders requesting three (3) or more units, an additional 15 minutes will be permitted for each additional unit due to cleaning, servicing, and loading requirements. On specific Work Requests the COR may require that the contactor notify the COR of the delivery time.

(c) Contractor shall place a service sticker on the inside of the unit door. The delivery date and each service date shall be annotated on the sticker.

(d) At times the government may have short-notice mission requirements that shall require the contractor to respond to the request on the same day or perhaps at the beginning or the end of the business day.

(e) Emergency Response is a delivery and placement within 2 hours for same day requests. When an Emergency Response is requested by the government the contractor will invoice against the CLIN for the Emergency Response as well as the unit type or service ordered.

The government will specify "Emergency Response" on the Work Request and in the e-mail sent by the COR.

(f) Contractor, when requested, shall ensure each unit is anchored in place and able to withstand winds up to 35 knots/40 miles per hour. The contractor shall ensure the unit(s) is anchored in a manner appropriate for the surface on which the unit(s) is placed (i.e., dirt, gravel, and asphalt, concrete). If a unit(s) blows over due to high winds, the contractor shall upright and service the unit(s) at no additional cost to the Government within 2 hours of notification from COR. The suggested anchoring technique is sandbags, or weights, and at some locations the units can be tethered to chain link fences or other items. Reference paragraph 6(b).

(4) Unit Servicing. For scheduling, inspection, and continuity purposes, the contractor shall service each unit, to include hand wash stations, at least every 7 calendar days and shall service each unit the same day each week. There is a Long-term unit located at a remote location at Orcutt Hill, Building 1; this is an On-Call Unit for cleaning/servicing. The government will notify the contractor when the unit requires servicing (at no cost to the government due to it being on the long-term rental listing). A Unit Cleaning Schedule can be developed as North Base, South Base, and the Cantonment Area. The unit shall be serviced using industry standard practices which must include (and are not limited to) the following:

(a) Complete removal of all waste, cleaning of the inside of the waste tank, to include cleaning and sanitation of the toilet seat. Waste shall be dumped at a properly licensed disposal site.

(b) Contractor shall exercise care to prevent spillage of the waste tank contents during the cleaning process. In the event spillage occurs, the contractor shall notify the COR and thoroughly clean up the entire area contaminated by the spillage. Contractor shall advise COR of the estimated time for completion of the clean-up.

(c) Servicing of the units shall comply with Federal, State, and local laws, ordinances, and regulations, industry standard practices and procedures, and the provisions of Appendix D attached.

(d) At contract startup, the contractor shall provide a service schedule within 10 days to the COR indicating the day of the week the units will be serviced. Since the number and locations of units may change on a regular basis, the contractor’s service schedule can be submitted by “areas” versus identifying specific units (for example: all North VSFB units on Mondays, all Main Cantonment units on Tuesdays, all South VSFB units on Wednesdays, or as preferred by the contractor.)

(e) Hand wash stations shall be refilled and serviced weekly to include proper sanitation and maintenance.

(f) Aircraft Lavatory Cart. Aircraft lavatory carts will be removed from the aircraft by the government and placed in a fleet cart which will be located in the vicinity of Base Operations, Building 1746. On an on-call basis, the contractor shall remove waste from the fleet carts, service and maintain the surrounding area in a clean and sanitary manner. Routine response time is within 3 hours of notification; emergency response time is within 2 hours of notification. The Government will determine if emergency response is warranted. Contractor will bill the Service CLIN and the Emergency Response CLIN when required.

(g) Additional Cleans. All servicing and cleaning will be in accordance with the cleaning schedule. However, unexpected services and cleaning may be required due to excessive use or blow-overs. In the event that servicing, and cleaning is required outside of the regular cleaning schedule, the contractor shall have 3 hours from the time of notification to complete any additional service call. Emergency response time is within 2 hours of notification. The Government will determine if emergency response is warranted. Contractor will bill the service CLIN and the Emergency Response CLIN when required. At a minimum, additional cleanings shall include the services described in paragraphs 1a(4), 1a(4)a, 1a(4)(b), and 1a(4)(c) above.

(5) Unit Relocation.

(a) When necessary, the government may relocate portable toilet units that are already in place. Or the contractor will be notified to perform the relocation.

(b) When directed by the COR, the contractor shall relocate a unit within 2 hours from the time of notification, if it's designated as an emergency requirement. Contractor will bill the service CLIN and the Emergency Response CLIN.

(c) If a unit is delivered to the incorrect location by the contractor the contractor shall relocate the unit to the proper location at no cost to the government.

(6) Unit Removal.

(a) Contractor shall not remove any units that are in-place without a written request from the COR. When a unit is no longer required, the COR will notify the contractor to remove the unit(s). Contractor shall remove requested units within 36 hours of COR notification, unless otherwise agreed upon by discussion between the COR and the contractor. When a task is complete and units have been removed, the contractor shall notify the government via phone or e-mail.

(b) When the contractor has anchored the unit(s) IAW paragraph 1a(3)(d), the contractor shall restore the affected surface to the original condition at no additional cost to the Government.

(c) Upon contract end, the contractor shall remove all portable toilet units within 7 calendar days. The incumbent contractor shall coordinate the removal of the toilets with the incoming contractor so that no facility will be without toilets.

(d) After contract expiration, the Government will not be liable for any compensation to the contractor for any units abandoned in-place after contract expiration, even if the units are damaged.

(7) Quality Control. The contractor shall provide a Quality Control Plan to the COR for review and acceptance within 10 days of contract award. The Quality Control Plan shall encompass all aspects of the PWS. The contractor shall perform quality control in accordance with provisions outlined in the Quality Control Plan and shall provide corrective action of all discrepancies upon notification by the COR. Any modifications to the Quality Control Plan shall be submitted to the COR for review.

2. SERVICES SUMMARY. The contractor service requirements are summarized into performance objectives that relate to mission critical items. The performance thresholds briefly describe the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

3. GOVERNMENT-FURNISHED ITEMS. Except for specific Government-furnished services noted below, the contractor shall furnish everything to perform required services outlined in this contract and PWS.

a. Forms. Work Request Form. Also referred to as work orders or work requests. This form will be submitted to the contractor by the Service Contracts Section CORs and is utilized to assign work requirements to the contractor. Contractor shall respond only to work orders that have been submitted by or oral requests by the Service Contracts Section CORs (for billing to this contract). See sample form at Appendix C.

PERFORMANCE OBJECTIVE

PWS REFERENCE

PERFORMANCE THRESHOLD

METHOD OF

SURVEILLANCE

Unit Requirements. All units provided shall be IAW all contract requirements and specifications.

Para 1, 1a(1), and 1a(1)(a) through 1a(1)(b) inclusive

No more than two customer complaints or two COR write-ups, or any combination thereof, per month related to a damaged, defective, or unsightly unit.

Customer Complaint;

Periodic Validation

Unit Ordering and Scheduling. Timely contractor response to COR telephone calls and timely acknowledgment of receipt of COR e-mails.

Para 1, 1a(2), and 1a(2)(a) through 1a(2)(c) inclusive

No more than two late or unreturned phone calls.

OR

No more than two failures to acknowledge receipt of e-mailed work requests per month.

Customer Complaint;

Periodic Validation

Unit Delivery and Placement. All units shall be delivered promptly and placed IAW accepted standards and contract requirements.

Para 1, 1a(3)(a) and 1a(3)(c)

No more than two late delivery complaints per month.

No more than one complaint per month for placement at a wrong location.

Customer Complaint;

Periodic Validation

Securing of Units. All units shall be properly installed and secured so as to prevent blow overs from high winds.

Para 1, 1a(3)(c) No more than one unit blow over per month. Customer Complaint;

Periodic Validation

Unit Servicing. Contractor shall service units IAW contract requirements.

Para 1, 1a(4) and 1a(4)(a) through 1a(4)(g) inclusive

No more than two customer complaints or COR write-ups, or any combination thereof, per month regarding poor service, late service, or no service.

Customer Complaint;

Periodic Validation

Unit Relocation. Contractor relocates units as requested by Government and IAW contract response time and requirements.

Para 1, 1a(5)(a) through 1a(5)(c) inclusive

No more than one customer complaint or one COR write-up, or any combination thereof, per month based on delayed response time for requested unit relocation.

Customer Complaint;

Periodic Validation

Unit Removal. Contractor removes units as requested by the Government and IAW required contract timeframe and requirements.

Para 1, 1a(6), 1a(6)(a) through 1a(6)(d) inclusive

No more than two customer complaints or two COR write-ups, or any combination thereof, per month based on units not being removed within 24-hour response period for routine removals and/or within the 7-day period for contract end.

Customer Complaint;

Periodic Validation

Invoice. Contractor shall invoice on or before the 5th day of the month for the prior months service.

Pre-Invoice documentation shall be submitted to the COR before submission into WAWF.

Para 4.d. Invoice shall be accurate upon submission for COR review.

100% Surveillance

b. Maps. The Vandenberg Space Force Base maps will be provided to the contractor for planning delivery schedules. The maps must be safe-guarded and are Controlled Unclassified Information. Specific placement map may be provided. The location specified in the map must be used.

4. GENERAL INFORMATION.

a. Permanent Unit Rentals: Standard portable toilet with sink, ADA, Trailer Mount Units and Handwash Stations will be rented and invoiced on a Monthly basis. Contractor shall invoice the appropriate Contract Line Item Numbers (CLIN). The Permanent Units facility listing will have a separate work order. All units including the hand wash stations will be cleaned and serviced weekly. For monthly invoicing purposes, the billing cycle is from the first day of the month to the last day of the month.

b. Short Term Rentals. Short term rentals will be rented on a 30-day basis and invoiced on the appropriate CLIN. These temporary units can remain in place for a period of 1 to 30 days.

If the units are required for longer than 30 days, a Continuation of Service work order will be issued and the unit(s) will require a cleaning (at no additional cost to the Government). An e-mail will be sent requesting removal when required. See 1.a.(6) for more information on removals.

c. Notice of Removal. The Government will give the contractor at least 24-hours’ notice via e-mail for a Notice of Removal when a unit is no longer required. The contractor may schedule removal with no further rental charges to the government. No rental charges will be paid for any period beyond the date specified by the Notice for Removal, regardless of whether or not the unit continues to receive usage.

d. Invoicing. Contractor shall provide COR with written Pre-Invoice Documentation in Excel format which itemizes each work request, type of unit, location description, and unit price (with formulas) with a bottom-line total for each CLIN. The Pre-Invoice Document will be submitted to the COR on or before the 5th day of the month for the prior months service.

Document must be submitted in advance and Accepted by the COR before submission into WAWF. COR will provide a sample pre-invoice document at contract start-up.

e. Domestic Sewage/Waste Disposal. Sewage/waste disposal on the VSFB installation is strictly prohibited. A copy of the contractor’s off-base disposal permit shall be provided with the contractor’s proposal. The contractor shall, at their expense, provide off-base disposal of all contract-generated sewage/waste only at licensed and approved disposal facilities designated for this type of waste.

f. Fines Assessed Against the Government. The Government shall retain from amounts otherwise due the contractor an amount equal to any fines assessed against the Government as a result of the contractor’s failure to perform in accordance with the terms of this contract.

g. Hours of Operation. The Government Program Office’s hours are Monday through Friday, 7:00 a.m. to 4:30 p.m. The contractor can reach CORs during office hours or contact the CES 24-hour response office at 805-606-1856 for after-hour’s emergencies. The contractor shall have personnel available by cell phone during program office hours and for after-hours emergency response. The contractor shall acknowledge and return calls within 30 minutes during normal duty hours and within 1 hour for after hour calls. Once the contractor has acknowledged the call to coordinate work effort with the COR, response times as noted in this PWS apply.

h. Federal Holidays Observed. The following federal holidays are observed by Vandenberg SFB: New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

i. Security Requirements. At all times while on the installation, all contractor employees shall comply with all Vandenberg SFB security requirements imposed by the Installation Commander. Contractor needs to be aware that entry requirements are subject to change due to installation and real world situations. In regards to permanent base access entry, all employees are subject to a background check through the FBI.

(1) Main Base Access. The current security access restrictions at the Santa Maria Gate (main base entry point) require all contractor vehicles which are the standard size of a delivery truck, van or larger vehicle, to enter ONLY through the Lompoc Gate. This gate is located at the intersection of Santa Lucia Road and Pine Canyon Road. There is a vehicle check/pull-off area and the Contractor will be required to pull off and submit to a vehicle search by 30 Security Forces personnel prior to gaining entry to the base. NOTE: The Contractor shall plan and allow for delays during peak traffic times at Lompoc Gate. These delays may be a result of current in-place security procedures. VSFB entry requirements are subject to change due to installation and real-world situations. The current hours of operation for Lompoc Gate are 6:00 a.m. to 7 p.m., Monday through Friday (subject to change). 30th Security Forces may be contacted to answer base access questions for the Lompoc Gate at 805-606-3911.

(2) Contractor Security Manager. Upon contract award, the Contractor shall designate in writing to the COR, a Security Manager who shall be the contractor’s point of contact for all security matters. Within five (5) working days of contract award, the Contractor’s security manager shall contact the 30th Civil Engineer Squadron’s (CES) Security Manager for assistance in accomplishing contractor personnel security requirements. The Contractor shall brief all their employees that they shall immediately leave any area upon notification by the CO, COR, Fire Department, constituted authority or Security Forces personnel when operational requirements, real-world activities or emergencies dictate.

(3) Restricted/Controlled Areas. The majority of work performed on this contract will be accomplished at non-secured facilities. However, there are facilities that are controlled areas and require special security procedures. Contractor shall comply with various levels of security and established personnel security for restricted/controlled area entry procedures. The Contractor’s employees will be escorted by the unit personnel for access into any VSFB restricted/controlled areas and shall wear a visitor badge as required. Contractor employees working in restricted/controlled areas shall fluently speak, understand, read and write English.

(4) Contractor Employees. The contractor shall not employ persons for this contract if such employee is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. All contractor employees must be able to read, write, speak, and understand the English language. Contractor employees must present a neat appearance and shall be easily recognized as contractor employees by wearing an identification tag that shall include the company’s name/logo and employee’s name. The contractor shall provide company identification tags at no additional cost to the Government. Upon completion of the contract, or an individual contractor employee’s employment, the contractor shall retrieve all identification media issued by 30th Security Forces Squadron and immediately surrender it to the Government.

(5) Contractor Vehicles. Contractor vehicles shall have the company name/logo prominently displayed on each side panel of the vehicle whenever vehicle is on the VSFB military installation. The contractor shall provide company vehicle identification at no additional cost to the Government.

j. Customer Complaints. The COR or base personnel can generate formal customer complaints regarding services received under this contract based on concerns that may exist with portable toilet placement, pickup, and servicing. Upon receipt of complaints from base personnel, the COR will perform contract review, evaluate, validate process, and forward all validated complaints to the contractor for investigation, corrective action, and preventive actions taken to preclude repeat non-compliance. The contractor shall provide written actions taken to rectify the customer complaint within 48 hours of notification (unless the complaint constitutes emergency or safety hazard, which requires a response within 4 hours).

k. Environmental Management. The contractor and all subcontractors shall comply and with applicable federal, state, county, and local environmental laws and regulations which include, but are not limited, to general and specific permit conditions, Air Force Instructions (AFIs), policies, guidelines, compliance documents, and management plans. The point of contact for environmental regulatory agencies for VSFB is 30 CES/CEI, Installation Management Flight. See Appendix D for all environmental requirements. The contractor shall comply with the latest Vandenberg Environmental Compliance Requirements Document (Appendix D).

l. Required Reports/Submittals. The contractor is required to provide documentation as indicated below:

(1) Contract Pre-Award/Start-Up:

• Business License and Insurance documents

• Environmental Protection Plan, see Appendix D, General Requirements, Section

01 57 20, Environmental Protection, Paragraph 3.11 Control and Management of Hazardous Wastes, paragraph f.

• Sewage/Waste Disposal Permit, see para 4.e.

• Unit Servicing Schedule, see para 1.a.(4)(d)

(2) Post-Award:

• Quality Control Plan, see para 7.

(3) Monthly:

• Pre-invoice document for acceptance; then, Electronic 2-1 WAWF Invoice

Submittal, see para 4.d

5. APPENDICES.

A. Historical Data B. Base Maps (will be issued at post award meeting) C. Sample Work Request & Sample Permanent Unit List D. General Requirements, Section 01 57 20, Environmental Protection

APPENDIX A

HISTORICAL DATA

The following figures represent estimated historical data. This information does not guarantee the contractor a projected workload.

ANNUAL QUANTITIES FY18 FY19 FY20 FY21

Standard Unit 870 920 931 811 Trailer Mount Units 13 16 24 20 ADA Units 117 148 120 91 Additional Clean 4 2 0 0 Barrel (Fleet Cart) Service 2 1 2 1 Relocation 0 0 0 2 Handwash Stations N/A N/A 6 7

APPENDIX B

BASE MAPS

Maps are Controlled Unclassified Information

Hard copies will be provided to awarded contractor at Post-Award.

Maps are for Official U.S. Air Force Use Information Safeguarding is Mandatory.

APPENDIX C

SAMPLE BASE CIVIL ENGINEER WORK REQUEST AF IMT 332

PERFORMANCE WORK STATEMENT
FOR
PORTABLE TOILET RENTAL & SERVICE
PERFORMANCE THRESHOLD
PERFORMANCE OBJECTIVE