This Statement of Work (SOW) details a locker installation project for the 2nd Security Forces Squadron (2 SFS) at Barksdale Air Force Base (BAFB). The project requires removing 290 existing lockers (24"W x 24"D x 36"H) and installing 600 new lockers (15"W x 18"D x 36"H) in the Guardmount Room of Building 6000, driven by a manpower increase and need for additional equipment storage for base defenders. The work must be completed within 60 days, with installation performed during normal business hours (0800-1600), excluding weekends and federal holidays, and must maintain adequate movement space for personnel.

Key requirements include contractor coordination with 2 SFS, passing a background check, and potential base access processing. The project is part of a small business set-aside solicitation (NAICS 337215) under contract FA460825QC033, with a site visit scheduled for 25 March 2025 and quotes due by 09 April 2025. Security protocols mandate that non-American citizens initiate entry processing at least 30 days in advance, and contractors must contact 2 SFS Police Services for further coordination and entry details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement Of Work, Dated 11 March 2025 Locker Installation

1200 Chappie James Dr., Barksdale AFB( BAFB), LA 71110, Building 6000, Guardmount Room

SCOPE / DESCRIPTION OF SERVICES: The work covered by these requirements consists of furnishing all plans, materials, labor, equipment, and performing all operations to remove/install new lockers in the 2 SFS Guardmount Room.

DELIVERY AND INSTALLATION: Sixty (60) Days AOR.

BACKGROUND: The 2 SFS is undergoing a manpower increase due to a new mission arriving at BAFB. 2 SFS Defenders are required to have a significant amount of duty gear/equipment to perform base defense. Each Defender needs a locker to store their duty gear/equipment.

LOCATION: 1200 Chappie James Dr., Bldg 6000 Guardmount Room, located at BAFB, LA

HOURS OF OPERATIONS. Normal hours of operation for this contract are between the hours of 0800 and 1600. The contractor shall perform the services required under this contract during this time excluding Saturdays, Sundays, and Federal Holidays.

REQUIRMENTS (OVERVIEW): The work covered under this Statement of Work shall consist of furnishing all material, labor, and equipment in performing all operations necessary to remove/install lockers. The lockers must be installed on top of the existing floor, without structural modifications or hinderance to arming operations within the layout of the room. There must be adequate space between locker rows for Defenders to move freely and for lockers to be opened adjacent.

• Remove existing lockers - 290 @ 24”W x 24”D x 36”H (*see page 2 for current layout)

• Install 600 lockers @ 15”W x 18”D x 36”H (Note: This layout may be adjusted by the contractor with

2 SFS coordination and input)

FA460825QC033

Attachment 3

SECURITY REQUIREMENTS: Coordination for entry to BAFB must be completed between 2 SFS and contractor. Contractor must pass a background check prior to being issued a visitor pass. If contractor is not an American citizen, this process needs to be initiated NLT 30 days in advance. The contractor should contact 2 SFS Police Services at (318) 456-1384 or (318) 456-4407, for further information and coordination.

*Current guardmount room and locker layout

FA460825QC033

Attachment 3

****End of Statement of Work****