Question_ _Answer_1.pdf
PDF 12 KB Posted
- Attached to
- Barksdale AFB Grounds Maintenance Federal contract opportunity
- Solicitation number
- FA4608-13-R-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTCH-2-BID_SCHEDULE_11_Feb_13.pdf | ||
| Amendment_02-11_Feb_13.pdf | ||
| Grounds_Base_Map_Revised.jpg | JPG image | |
| Questions_from_Site_Visit_and_Solicitation-_7_FEB_2013.pdf | ||
| Site_Visit_Attendees.pdf | ||
| ATTCH-2-BID_SCHEDULE-Updated_6_Feb_13.pdf | ||
| Amendment_1_-_6_Feb_13.pdf | ||
| Site_Visit_Route_31-Jan-13.pdf | ||
| FA4608-13-R-0002_Grounds_Solicitation-Released-15-Jan-13.pdf | ||
| Appendix_E_--_BAFB-Tree_Management_Plan-Final2.pdf | ||
| ATTCH-4-2013_Grds_Maint_Performance_Questionnaire.pdf | ||
| ATTCH-1-30_OCT_2012-Grounds_Maintenance_PWS_2013.pdf | ||
| ATTCH-2-BID_SCHEDULE.pdf | ||
| ATTCH-3-WageD_23_July_12.pdf | ||
| 13-R-0002-GROUNDS-14-Jan-13_Solicitation.pdf | ||
| ATTCH-5-Environmental_(Oct_12_Revision).pdf | ||
| Appendix_G-NEW.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4608-13-R-0002- BAFB Grounds Maintenance Solicitation
Questions & Answers
Q. Section L does not state a total number of copies for each of the three separately bound parts (Price, Technical and Past Performance). Will one copy of each suffice?
A. Per the addendum to 52.212-1(c), paragraph B(1)(a) the company needs to submit an original and two copies of the SF 1449 price proposal, as well as, an electronic copy of attachment 2 in excel format.
Since there is not a minimum number of copies stated for part II and III of the proposal, one copy will suffice.
Q. Does the 10 page limit on the technical volume include the cover page and table of contents?
A.Yes, the technical volume is limited to 10 pages starting with a cover page if a company chooses to have one.
Q. Is there a page limit for the technical proposal?
A.The page limit for the technical proposal is stated on the evaluation criteria clause FAR 52.212-2 (10 pages maximum)
Q. The solicitation for grounds maintenance at Barksdale AFB was out last year and subsequently awarded. Can you confirm that this is the same solicitation and why the government is soliciting bids less than 9 months later?
A. The solicitation that was out last year has been cancelled there was no award made; this new solicitation is for the same requirement please refer to the new solicitation for updated information and evaluation criteria.
Q. If the above question is confirmed yes, can you provide the awarded annual price?
A. The annual price on the previous contract for grounds maintenance is 1.2 Million.
Q. CLIN 0017 AA Prune Trees states Unit of Issue as MONTH on SF1449 and Attachment 2-Bid Schedule, is this the correct Unit of Issue?
A. An Amendment to the SF1449 will be issued to reflect the change of Unit of Issue on CLIN 0017 AA Prune Trees from MONTH to EACH .