Corrections_-_Response_to_Questions.docx

DOCX document 12 KB Posted

Attached to
Claiborne Bombing and Gunnery Range Federal contract opportunity
Solicitation number
FA4608-13-R-0001
Issued by
Department of the Air Force Global Strike Command

About this file

Corrections - Response to Questions

View the file

Other files for this federal contract opportunity

Other files attached to Claiborne Bombing and Gunnery Range, newest first.
File Type Posted
Amendment_0003.pdf PDF
Section_B_-_pages_3-5_Replacement_Pages.pdf PDF
Section_B_-_pages_3-5_Replacement_Pages.pdf PDF
Amendment_0002.pdf PDF
Response_to_Questions(2).docx DOCX document
Responses_to_Questions.docx DOCX document
Amendment_1.pdf PDF
Atch_7_DD_Form_254_Amendment_1.pdf PDF
FA4608-13-R-0001_Claiborne_Range.pdf PDF
Atch_1_PWS.pdf PDF
Atch_6_ET3_Job_Description.docx DOCX document
Atch_5_Past_Performance_Questionnaire.doc DOC document
Atch_4_INSURANCE_CERTIFICATE.doc DOC document
Atch_3_Wage_Determination.docx DOCX document
Appendices.docx DOCX document
Atch_2_Environmental_Requirements__(June_2013_Revision).doc DOC document
Atch_7_DD_Form_254.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Corrections – Response to Questions

12. Reference PWS Para 4.3.11. What support is the contractor supposed to provide to the Forest Service while they conduct controlled burns? Answer: The contractors ensure the range facilities and equipment are not damaged in case the controlled burns get out of control for some reason. The contractor will use all available resources to protect range facilities during controlled burns. This is primarily confined to the impact area – not the expanded boundaries. The contractor shall also provide assistance in the way of guidance and safe escorts to any USFS personnel that enter the impact area. The contractor shall maintain the helo pad and wind sock in good working order as a base of operations for the USFS helicopter used during controlled burns.

14. Will the government incur the cost of the disposal of non-toxic waste? Answer:

No. PWS Para 4.3.10.3.2 states that the contractor is responsible for the disposal of ALL waste material. That includes non-toxic waste.

19. Will EOD clear/safe range roads and bomb circles prior to grading operations?

Answer: No. As per Appendix E, grading operations are required bi-monthly, but are actually determined by rain and road usage so may be necessary more often during a heavy rainy season. However, grading operations directly on the bomb circle will only be schedule to coincide with the EOD clearance.