This document contains technical specifications and drawings for a Superior Boiler Seminole 6-X-750 150 PSI boiler vessel. The drawings provide detailed dimensions and connection points for the boiler, and specify materials and insulation used. Technical specifications include vessel capacities, heating surfaces, weight, ratings and other technical details.
The related federal contract opportunity is a solicitation to remove jacketing and insulation from Boiler 3 at an Air Force facility, clean the vessel surface, perform non-destructive testing to verify structural integrity, and if satisfactory, replace insulation and jacketing and return the boiler to operational service after combustion, safety and operational inspections. The contractor must provide a proposal split into two conditional options according to the work scope in the Performance Work Statement. The solicitation was issued by the Department of the Air Force Air Combat Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BOILER SERVICE QUESTIONS AND ANSWERS.docx | DOCX document | |
| PWS B304 Boiler 3 vessel integrity NEW.docx | DOCX document | |
| Site Visit MFR.pdf | ||
| NCIC Screening and Pass Request.pdf | ||
| FA460024Q0009 Combo Solicitation.pdf | ||
| PWS Boiler 3 Vessel Integrity.docx | DOCX document | |
| 52.212-2.docx | DOCX document | |
| SCA Wage Determination.pdf | ||
| 52.212-1.docx | DOCX document | |
| FA460024Q0009 Combo Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
50 1
46 1
1. ALL CONTROLS MOUNTED AS PER SPECIFICATION SHEET.
2. SPECIFICATION SHEET TAKES PRIORITY OVER R & D SHEET.
3. BOILER DESIGN CODE ASME SECTION I .
22 GAUGE STEEL JACKET.
4. BOILER INSULATED WITH 2" OF INSULATION WITH
5. ALL DIMENSIONS ARE ±1/2" UNLESS OTHERWISE NOTED.
H
92 73 67
113 1
WATER CAPACITY:
STEAM RELEASE AREA
STEAMING VOLUME
TURNAROUND VOLUME
FURNACE VOLUME
FURNACE HEATING SURFACE
HEATING SURFACE (ASME)
RATED INPUT
STEAM (FROM & AT 212°F)
GROSS OUTPUT
DESIGN PRESSURE
HORSEPOWER
SHIPPING WEIGHT:
(NWL)
(FULL)
HEAT RELEASE: (FURNACE ONLY)
H.( ) HANDHOLE 3" x 4"
SIGHTPORT
J.( ) CLEANOUT
K.( ) FEEDWATER
L.( ) AUXILIARY
M.( ) LOW FIRE HOLD
N.( ) STACK TEMP
R.( ) S.( )
1P.( ) Q.( )
1/2" NPT
1 1/4" PIPE
1/2" NPT
1 1/4" NPT
2" NPT
17" ID
A.( ) STEAM OUTLET
B.( ) LWCO
C.( ) SAFETY VALVE
D.( ) SAFETY VALVE
E.( ) BOILER BLOWDOWN
F.( ) SURFACE BLOWDOWN
G.( ) MANWAY1
BOILER CONNECTIONS
4" 300# FLANGE
1 1/4" NPT
1" NPT
12" x 16"
1" NPT
2" NPT
J P K
11,293 LBS
12,928 LBS
85.74 SqFt
24.09 CuFt
26.28 CuFt
49.93 SqFt
46.64 CuFt
1,554 GAL
1,358 GAL
RATINGS & CAPACITIES
150 PSIG STEAM
5175 LBS/HR
5021 MBH
6277 MBH
759 SqFt
134,576 BTU/CuFt
M B
51 1
DATELTR
TOP OF STACK
N 37 1
WARRICK PROBE
ALWCO
20 20 19 1610
H
215 ±1
16 1
48 1
35 1
134 1
NOTES
?1/48
6-5-750-S150
SEMINOLE
SCALE
HUTCHINSON, KANSAS
BOILER WORKS, INC.
DRAWING No
BOILER MODEL
CHECKED BY
DRAWN BY
REVISION
H B
THIS DRAWING IS THE PROPERTY
OF SUPERIOR BOILER WORKS &
SHALL NOT BE REPRODUCED IN
PART OR IN WHOLE, & NONE OF
ITS INFORMATION SHALL BE
REVEALED WITHOUT PERMISSION
OR TO THE DETRIMENT OF THE
OWNER. IT MUST BE RETURNED
UPON REQUEST.
X
X
DATE
DATE
BY REPRESENTATIVE:
PROJECT:
X
X
K E HH
181 1
C
TUBE CLEARANCE
TOP OF STEAM NOZZLE
5 9
NWL
TOT
B B FA L DOOR SWING
C G 36 1
80 ±1
BOILER JUNCTION BOX
92 ±1/2
MM157S
LWCO
PIPING