Final 09 91 00 Painting.pdf

PDF 220 KB Posted

Attached to
Saber Pre-solicitation notice Federal contract opportunity
Solicitation number
FA4600-10-R-0006
Issued by
Department of the Air Force Air Combat Command

About this file

-

View the file

Other files for this federal contract opportunity

Other files attached to Saber Pre-solicitation notice, newest first.
File Type Posted
SIGN IN SHEET Oct 15 2010.doc DOC document
Seed project Honor guard room.pdf PDF
Amendment6.doc DOC document
Attachment 3 Seed SOO Rpr AHU's O-Club B462 28 Sept 2010.doc DOC document
Amendment5.doc DOC document
Question and Answers 24 Sep 2010.docx DOCX document
Sheet 05.dwf DWF file
Sheet 08.dwf DWF file
Sheet 16.dwf DWF file
Sheet 10.dwf DWF file
Sheet 13.dwf DWF file
amendment4.doc DOC document
Attachment 3 Rpr AHU's O-Club B462 Sept 2010.doc DOC document
Sheet 09.dwf DWF file
Sheet 17.dwf DWF file
Sheet 15.dwf DWF file
Question and Answers.docx DOCX document
amendedsolicitation2.doc DOC document
final 23 05 93 Testing Adjusting and Balancing.pdf PDF
Sheet 10-10.pdf PDF
Performance Period.pdf PDF
final 26 05 33 Raceways.pdf PDF
final 26 05 19 Wires and Cables.pdf PDF
Sheet 2-02.pdf PDF
Sheet 3-Sheet 3.pdf PDF
final 07 92 00 Joint Sealers.pdf PDF
Final 05 50 00 Metal Fabrications.pdf PDF
Sheet 11-11.pdf PDF
final 26 05 53 Electrical Identification.pdf PDF
Final 23 38 13 Kitchen Ventilator Hood Systems.pdf PDF
final 23 07 00 HVAC Insulation.pdf PDF
final 23 00 00 General Provisions.pdf PDF
Final 26 05 26 Grounding.pdf PDF
final 23 01 30 HVAC Air-Distribution Cleaning System.pdf PDF
Sheet 19-Sheet 19.pdf PDF
Final 23 05 00 Basic HVAC Materials and Methods.pdf PDF
Sheet 9-9.pdf PDF
Sheet 5-Sheet 5.pdf PDF
Sheet 12-12.pdf PDF
Section 1B AF66 Master Oct 2008.xls XLS spreadsheet
Sheet 16-16.pdf PDF
Sheet 11-11.pdf PDF
Section 1C Master Copy June 2008.pdf PDF
SITE PLAN.dwg DWG drawing
Ntitle.dwg DWG drawing
Rpr Wing XP.dwg DWG drawing
Site Visit Sign In Sheet.pdf PDF
Preconstruction Conference Attachment 4.doc DOC document
Attachment 1.docx DOCX document
Attachment 5.docx DOCX document
Show all 50

Saber Pre-solicitation notice has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OFFUTT AIR FORCE BASE

(092036) 09 91 00-1 (Repair AHU O-Club, B462)

2010 by FEI

SECTION 09 91 00

PAINTING

PART 1 - GENERAL

1.1 SCOPE

A. Work required under this Section includes all labor, materials, tools and equipment necessary to complete all work relative to furnishing and application of all painting as shown on the drawings or described in the specifications. Work within this Section shall be completely coordinated with work of other trades.

B. Although such work is not specifically shown or specified, furnish and install all supplementary or miscellaneous items, appurtenances, devices and coatings incidental to or necessary for a sound, secure and complete installation.

1.2 EXTENT OF WORK

A. Without imposing restrictions or limitations to the extent of work intended, work to be performed under this section includes, but is not limited to, the following:

1. Exterior Painting - Field painting of all ferrous metal ductwork and supports on roof including new roof top unit.

a. All other areas and items noted on plans or in other sections of the specifications.

2. Interior Painting - Includes surfaces of all new gypsum board ceilings and bulkheads unless noted otherwise. All touch up areas as required where existing ceilings are removed and replaced.

a. All other areas and items noted on plans or in other sections of the specifications.

1.3 CODES, SPECIFICATIONS AND STANDARDS

A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in the text by basic designation only. Any material or operation specified by reference to the published specifications of a manufacturer or other referenced specification or standard shall comply with the requirements of the latest edition. In case of a conflict between a referenced specification or standard and these project specifications the more stringent requirement shall govern.

B. Comply with the applicable provisions of the following codes, specifications and standards to the extent indicated by reference thereto.

1. American Conference of Governmental Industrial Hygienists - ACGIH 0100Doc

“Documentation of the Threshold Limit Values and Biological Exposure Indices”.

2. American Society of Testing and Materials - ASTM C 669 “Glazing Compounds for Back

Bedding and Face Glazing of Metal Sash”.

3. American Society of Testing and Materials - ASTM D 235 “Mineral Spirits (Petroleum Spirits)

(Hydrocarbon Dry Cleaning Solvent)”.

(092036) 09 91 00-2 (Repair AHU O-Club, B462)

4. American Society of Testing and Materials - ASTM D 523 “Standard Test Method for Specular

Gloss”.

5. American Society of Testing and Materials - ASTM D 4214 “Standard Test Method for

Evaluating the Degree of Chalking of Exterior Paint Films”.

6. American Society of Testing and Materials - ASTM D 4263 “Indicating Moisture in Concrete by the Plastic Sheet Method”.

7. American Society of Testing and Materials - ASTM D 4444 “Use and Calibration of Hand-Held

Moisture Meters”.

8. American Society of Testing and Materials - ASTM E 84 “Standard Test Method for Surface

Burning Characteristics of Building Materials”.

9. American Society of Testing and Materials - ASTM E 2129 “Standard Practice for Data

Collection for Sustainability Assessment of Building Products”.

10. American Society of Testing and Materials - ASTM F 1869 “Measuring Moisture Vapor

Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride”.

11. International Building Code - IBC 2006.

12. Master Painters Institute - MPI “Architectural Painting Specification Manual”.

13. Master Painters Institute - MPI “Maintenance Repainting Manual”.

14. Master Painters Institute - MPI 42 “Latex Stucco and Masonry Textured Coating”.

15. NACE International “The National Association of Corrosion Engineers” - National Fire

Protection Association - NFPA 101 “Life Safety Code”.

16. NACE International “The National Association of Corrosion Engineers” - NACE No. 1 / SSPC -

SP5 “White Metal Blast Cleaning”.

17. NACE International “The National Association of Corrosion Engineers” - NACE No. 2 / SSPC -

SP 10 “White Metal Blast Cleaning”.

18. NACE International “The National Association of Corrosion Engineers” - NACE No. 3 / SSPC

SP - 6 “Commercial Blast Cleaning”.

19. NACE International “The National Association of Corrosion Engineers” - NACE No. 5 / SSPC

SP - 12 “Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating”.

20. The Society For Protective Coatings - SSPC PA 1 “Shop, Field, and Maintenance Painting”.

21. The Society For Protective Coatings - SSPC PA Guide 3 “A Guide to Safety in Paint

Application”.

22. The Society For Protective Coatings - SSPC QP 1 “Standard Procedure for Evaluating Painting

Contractors (Field Application to Complex Industrial Structures)”.

23. The Society For Protective Coatings - SSPC SP 1 “Solvent Cleaning”.

(092036) 09 91 00-3 (Repair AHU O-Club, B462)

24. The Society For Protective Coatings - SSPC SP 2 “Hand Tool Cleaning”.

25. The Society For Protective Coatings - SSPC SP 3 “Power Tool Cleaning”.

26. The Society For Protective Coatings - SSPC SP 5 “White Metal Blast Cleaning”.

27. The Society For Protective Coatings - SSPC SP 6 “Commercial Blast Cleaning”.

28. The Society For Protective Coatings - SSPC SP 7 “Brush-Off Blast Cleaning”.

29. The Society For Protective Coatings - SSPC SP 10 “Near-White Blast Cleaning”.

30. The Society For Protective Coatings - SSPC SP 11 “Hand Tool Cleaning”.

31. The Society For Protective Coatings - SSPC SP 12 “Surface Preparation and Cleaning of

Metals by Waterjetting Prior to Recoating”.

32. The Society For Protective Coatings - SSPC VIS 1”Guide and Reference Photographs for

Steel Surfaces Prepared by Dry Abrasive Blast Cleaning”.

33. The Society For Protective Coatings - SSPC VIS 3 “Visual Standard for Power-and Hand-Tool

Cleaned Steel”.

34. The Society For Protective Coatings - SSPC VIS 4 “Guide and Reference Photographs for

Steel Surfaces Prepared by Waterjetting”.

35. U.S. Army Corps of Engineers - USACE EM 385-1-1 “Safety -- Safety and Health

Requirements”.

36. U.S. Department of Labor Occupational Safety & Health Administration - OSHA 29 CFR

1910.1000 “Toxic and Hazardous Substances, Air Contaminants”.

37. U.S. General Services Administration - GSA FED - STD - 313 (Rev D; Am 1) “Material Safety

Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to

Government Activities”.

38. U.S. Green Building Council - USGBC LEED Reference Guide “Leadership in Energy and

Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC)”.

1.4 DEFINITIONS AND ABBREVIATIONS

A. Coating: A film or thin layer applied to a base material called a substrate. A coating may be a metal, alloy, paint, or solid / liquid suspensions on various substrates (metals, plastics, wood, paper, leather, cloth, etc.). They may be applied by electrolysis, vapor deposition, vacuum, or mechanical means such as brushing, spraying, calendering, and roller coating. A coating may be applied for aesthetic or protective purposes or both. The term "coating" as used herein includes fillers, primers, sealers, emulsions, oils, alkyds, latex, enamels, stains, varnishes, sealers, epoxies, thinners and other applied coatings, whether used as primer, intermediate, or finish coat. The terms paint and coating are used interchangeably.

B. DFT or dft: Dry film thickness, the film thickness of the fully cured, dry paint or coating.

(092036) 09 91 00-4 (Repair AHU O-Club, B462)

C. DSD: Degree of Surface Degradation, the Master Painters Institute MPI system of defining degree of surface degradation. Five (5) levels are generically defined under the Assessment sections in the MPI

Maintenance Repainting Manual.

D. EPP: Environmentally Preferred Products, a standard for determining environmental preferability in support of Executive Order 13101.

E. EXT: MPI short term designation for an exterior coating system.

F. INT: MPI short term designation for an interior coating system.

G. micron / microns: The metric measurement for 0.001 mm or one / one - thousandth of a millimeter.

H. mil / mils: The English measurement for 0.001 in or one / one - thousandth of an inch, equal to 25.4 microns or 0.0254 millimeter.

I. mm: The metric measurement for millimeter, 0.001 meter or one / one - thousandth of a meter.

J. MPI Gloss Levels: MPI system of defining gloss. Seven (7) gloss levels (G1 to G7) are generically defined under the Evaluation sections of the MPI Manuals. Traditionally, Flat refers to G1 / G2, Eggshell refers to G3, Semigloss refers to G5, and Gloss refers to G6. Gloss levels are defined by MPI as follows:

GLOSS LEVELS

Gloss is tested in accordance with ASTM D 523

GLOSS LEVEL DESCRIPTION

UNITS @ 60

DEGREES

UNITS @ 85

DEGREES

G1 Matte or Flat 0 to 5 10 maximum

Gl Velvet 0 to 10 10 to 35

G3 Eggshell 10 to 25 10 to 35

G4 Satin 20 to 35 35 minimum

G5 Semi - Gloss 35 to 70

G6 Gloss 70 to 80

G7 High Gloss

K. MPI System Number: The MPI coating system number in each Division found in either the MPI

Architectural Painting Specification Manual or the Maintenance Repainting Manual and defined as an exterior (EXT / REX) or interior system (INT / RIN). The Division number follows the CSI Master

Format.

L. Paint: Terms "paint" and "painting" refer to all applied coatings. See Coating definition.

M. REX: MPI short term designation for an exterior coating system used in re - painting projects or over existing coating systems.

N. RIN: MPI short term designation for an interior coating system used in re - painting projects or over existing coating systems.

(092036) 09 91 00-5 (Repair AHU O-Club, B462)

1.5 COORDINATION OF PAINTING REQUIREMENTS

A. The painting subcontractor shall examine other Sections of the Specifications and shall thoroughly familiarize themselves with all their provisions regarding their painting requirements. Except as otherwise specified, surfaces left unfinished by the requirements of other Sections shall be painted or finished as a requirement of this contract.

B. Painting and finishing work called for under other Sections of the Specifications is included under those

Sections.

C. Prime Coat Coordination: Provide finish coats which are compatible with prime paints used. Review other sections of these specifications in which prime paints are to be provided to ensure compatibility of total coating system for various substrates. Upon request from other trades, furnish information on characteristics of finish materials proposed for use, to ensure compatible prime coats are used. Provide barrier coats over incompatible primers or remove and reprime as required at no additional cost to

Owner. Notify Architect in writing of any anticipated problems using specified coating systems with substrates primed by others.

1.6 REGULATORY REQUIREMENTS

A. Environmental Protection: In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution Control District and regional jurisdiction. Notify Owner’s Representative of any paint specified herein which fails to conform.

B. Lead Content: Do not use coatings having a lead content over 0.06 percent by weight of non - volatile content.

C. Chromate Content: Do not use coatings containing zinc - chromate or strontium - chromate.

D. Asbestos Content: Materials shall not contain asbestos.

E. Mercury Content: Materials shall not contain mercury or mercury compounds.

F. Silica: Abrasive blast media shall not contain free crystilline silica.

G. Human Carcinogens: Materials shall not contain ACGIH 0100Doc confirmed human carcinogens (A1) or suspected human carcinogens (A2).

1.7 SUBMITTALS

A. No later than 4 weeks following the Notice to Proceed, the Contractor shall verify in writing that he intends to apply the products listed in the paint schedules.

B. Product Data: Provide primers and undercoat paint produced by the same (Single - Source) manufacturer as the finish coats. This submittal shall include the name of the corresponding specified item, the full identifying product names and catalog numbers of each of the products substituted therefore, together with the following detail information attested to by a Chemist or Officer of the manufacturer:

1. Spreading rate.

2. Dry mil thickness.

3. Non - volatile percent by weight.

(092036) 09 91 00-6 (Repair AHU O-Club, B462)

4. Dust free time.

5. Recoat time.

6. Chemistry of product.

7. Indicate VOC content.

C. Shop Drawings for Piping Identification: Submit color and stencil codes to be used.

D. Submit a specification manual containing the full line of manufacturer’s products.

E. Certificates: Submit Applicator's Qualifications.

F. Certifications by the manufacturer that products supplied comply with local regulations controlling use of volatile organic compounds (VOCs).

G. Provide test reports for materials used indicating fire hazard classification as determined by ASTM E

84. Materials shall meet requirements established in NFPA Number 101, Life Safety Code &

International Building Code. Generally, all paint used must maintain a Class "A" fire rating on non-combustible substrates.

H. Manufacturer's Instructions: Submit Application instructions for each product specified.

I. Mixing: Detailed mixing instructions, minimum and maximum application temperature and humidity, potlife, and curing and drying times between coats for each product specified.

J. Manufacturer's Material Safety Data Sheets: Submit manufacturer's Material Safety Data Sheets for coatings, solvents, and other potentially hazardous materials, as defined in Federal Standard 313.

K. Submit three (3) color sample cards for each color selected. Prepare sample cards with number of coats as specified for substrate where color is used. Step all samples to show coats.

1.8 APPLICATOR'S QUALIFICATIONS

A. Contractor Qualification: Submit the name, address, telephone number, FAX number, and e - mail address of the contractor that will be performing all surface preparation and coating application. Submit evidence that key personnel have successfully performed surface preparation and application of coatings on a minimum of three similar projects within the past three years. List information by individual and include the following:

1. Name of individual and proposed position for this work. Provide information about each previous assignment including: Position or Responsibility held.

2. Name of Owner’s project contact in organization who can be contacted as a reference, their mailing address, telephone number, fax number, and e - mail address

3. Location, size and description of structure, dates work was carried out and description of work carried out on structure.

1.9 PRODUCT, DELIVERY, STORAGE AND HANDLING

A. Deliver materials in original unopened containers.

(092036) 09 91 00-7 (Repair AHU O-Club, B462)

B. Label each container with following information:

1. Name or title of material.

2. Manufacturer's stock number and date of manufacture.

3. Manufacturer's name.

4. Contents by volume, for major pigment and vehicle constituents.

5. Thinning instructions.

6. Application instructions.

7. Color name and number. Corresponding to Color Schedule found elsewhere in Division 09.

C. Protect from freezing or damage.

D. Store all materials in a single place designated by the General Contractor. Keep storage neat and clean. Make good all damage thereto or to surroundings. Remove rags and waste from building daily.

Take precautions to avoid danger of fire. Post "No Smoking" signs in storage areas.

E. Maintain storage for paint materials in conformity with fire codes and authorities having jurisdiction.

Protect floor from any spilled materials.

F. Paints and thinners shall be stored in accordance with the manufacturer's written directions, and as a minimum, stored off the ground, under cover, with sufficient ventilation to prevent the buildup of flammable vapors, and at temperatures between 40 to 95 degrees F. Do not store paint, polyurethane, varnish, or wood stain products with materials that have a high capacity to adsorb VOC emissions. Do not store paint in occupied spaces.

1.10 SAFETY AND HEALTH

A. Apply coating materials using safety methods and equipment in accordance with the following: Work shall comply with applicable Federal, State, and local laws and regulations, and with the Accident

Prevention Plan, including the Activity Hazard Analysis as specified in and in Appendix A of EM 385 - 1

- 1. The Activity Hazard Analysis shall include analyses of the potential impact of painting operations on painting personnel and on others involved in and adjacent to the work zone.

B. Safety methods used during coating application shall comply with the requirements of SSPC PA Guide

3.

C. Toxic Materials To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

1. The applicable manufacturer's Material Safety Data Sheets (MSDS) or local regulation.

2. OSHA 29 CFR 1910.1000.

3. ACGIH 0100Doc, threshold limit values.

1.11 ENVIRONMENTAL / PROJECT CONDITIONS

(092036) 09 91 00-8 (Repair AHU O-Club, B462)

A. Comply, at minimum, with manufacturer recommendations for space ventilation during and after installation. Isolate area of application from rest of building when applying high - emission paints or coatings.

B. Coatings - Do not apply coating when air or substrate conditions are:

1. Less than 5 degrees F above dew point;

2. Below 50 degrees F or above 95 degrees F unless specifically pre - approved in writing by the

Owner’s Representative and the product manufacturer. Under no circumstances shall application conditions exceed manufacturer recommendations.

3. Damp, or during cold, rainy or frosty weather. Avoid painting surfaces exposed to hot sun.

C. Protection During Cleaning: Personnel engaged in solvent - cleaning of galvanized metal and aluminum, or cleaning concrete, masonry, or portland cement plaster with 5 to 10 percent solution of hydrochloric acid, shall wear the appropriate personal protective equipment to prevent skin and eye contact and fumes inhalation. Ventilate all work areas properly.

D. Personnel Protection During Coating Applications: Personnel painting with high - build glaze coating systems shall wear the appropriate personal protective equipment to prevent skin or eye contact or inhalation. Ensure employees use and maintain solvent - resistant, personal protective equipment for the whole body. Emergency eye wash and water supplies shall be available near the work area for emergency flushing of the eyes and body. Coating applications shall be performed only in areas with good ventilation. Smoking will not be permitted in the area where coating is being applied. Wall and room temperature at the time of coating application and curing shall be in accordance with the manufacturer's instructions.

E. Protection During Application of Polyurethane Paints: Mix and apply polyurethane paints only in specifically designated areas with local exhaust ventilation and other environmental control measures as recommended on the basis of an on-site industrial hygiene survey. Supply and use air respirators in closed areas where adequate ventilation cannot be obtained.

F. Post - Application: Vacate space for as long as possible after application. Wait a minimum of 48 hours before occupying freshly painted rooms. Maintain one of the following ventilation conditions during the curing period, or for 72 hours after application:

1. Supply 100 percent outside air 24 hours a day.

2. Supply airflow at a rate of 6 air changes per hour, when outside temperatures are between 55 degrees F and 85 degrees F and humidity is between 30 percent and 60 percent.

3. Supply airflow at a rate of 1.5 air changes per hour, when outside air conditions are not within the range stipulated above.

G. Avoid painting near temporary heaters which might discolor paint.

H. Painting Contractor shall apply all materials under adequate illumination. Contractor shall assure adequate illumination exists in all areas where painting operations are in progress.

I. The painting Contractor is responsible for inspecting the work of others prior to the application of any paint or finishing material. If any surface to be finished cannot be put in proper condition for finishing by customary cleaning, sanding and puttying operations, the painting Contractor will immediately notify the

(092036) 09 91 00-9 (Repair AHU O-Club, B462)

General Contractor and the Owner’s Representative, in writing, and shall not proceed with this work until conditions have been corrected and are acceptable.

J. Commencing of work in a specific area constitutes acceptance of surfaces, and responsibility for satisfactory work.

K. Painting Contractor shall provide wet paint signs as required.

L. Paint exposed surfaces whether or not colors are designated in "schedules," except where a surface or material is specifically indicated not to be painted or is to remain natural. Where an item or surface is not specifically mentioned, paint the same as similar adjacent materials or surfaces. If color or finish is not designated, the Architect will select from standard colors or finishes available.

M. Owner’s Representative and Architect approval is required PRIOR to application of each coat.

N. The minimum numbers of paint coats are specified in the Paint Schedule found elsewhere in this section. The application of additional coats to provide a total color and sheen uniformity on all surfaces shall be provided at no additional cost to the Owner. The painting Contractor shall not be entitled to payment in excess of the amount agreed upon in their contract for any extra work over and above that specified unless authorized in writing by a Change Order.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Paint systems specified herein shall be manufacturers top - of - the - line products and shall be subject to compliance with specifications. Paint products specified in Paint Schedule are products of Diamond

Vogel. Comparable products of the following manufacturers are approved for use:

1. Benjamin Moore.

2. Kwal Paints.

3. Pittsburg Paints.

4. Pratt & Lambert.

5. Sherwin Williams.

B. Paint of other manufacturers will not be approved.

2.2 PAINT MATERIALS

A. Solvents (for cleaning and product reducing) shall be pure and of highest quality, and shall be approved by the Architect. They shall bear identifying labels on the containers, with the manufacturer's instructions printed thereon.

B. Paint shall arrive on the job ready - mixed, except for tinting of undercoats.

C. All thinning and tinting material shall be as recommended by the manufacturer for the particular material thinned or tinted.

2.3 APPLICATION EQUIPMENT

(092036) 09 91 00-10 (Repair AHU O-Club, B462)

A. Application equipment is not required to be new, but shall be adequate and commensurate for the work and workmanship required herein.

2.4 ACCESSORY MATERIALS

A. Provide all required ladders, scaffolding, drop cloths, maskings, scrapers, tools, sandpaper, duster, cleaning solvents and waste, as required to perform the work and achieve the results herein specified.

PART 3 - EXECUTION

3.1 PROTECTION OF AREAS AND SPACES NOT TO BE PAINTED

A. Prior to surface preparation and coating applications, remove, mask, or otherwise protect, hardware, hardware accessories, machined surfaces, radiator covers, plates, lighting fixtures, public and private property, and other such items not to be coated that are in contact with surfaces to be coated.

Following completion of painting, workmen skilled in the trades involved shall reinstall removed items.

Restore surfaces contaminated by coating materials, to original condition and repair damaged items.

3.2 SURFACE PREPARATION GENERAL

A. Remove dirt, splinters, loose particles, grease, oil, [disintegrated coatings,] and other foreign matter and substances deleterious to coating performance as specified for each substrate before application of paint or surface treatments. Oil and grease shall be removed prior to mechanical cleaning. Cleaning shall be programmed so that dust and other contaminants will not fall on wet, newly painted surfaces.

Exposed ferrous metals such as nail heads on or in contact with surfaces to be painted with water -thinned paints, shall be spot - primed with a suitable corrosion - inhibitive primer capable of preventing flash rusting and compatible with the coating specified for the adjacent areas.

1. Assure that surfaces are clean and dry.

2. Assure that surfaces are free of foreign material which will affect adhesion or appearance.

3. Remove mildew and neutralize surface.

4. Correct efflorescence before painting.

3.3 FERROUS METAL SURFACES

A. All ferrous metal shall, at a minimum, be cleaned in accordance with The Society for Protective

Coatings (formerly Steel Structures Painting Council), Surface Preparation Level 1 - Solvent Cleaning

(SSPC SP 1) preparation procedures and methods.

B. Ferrous metal shall be cleaned to the minimum requirements of the The Society for Protective Coatings

(formerly Steel Structures Painting Council), Surface Preparation levels and the NACE International

“The National Association of Corrosion Engineers” Surface Preparation levels as listed in the following table:

MINIMUM SURFACE PREPARATION BASED ON TYPE OF COATING AND ENVIRONMENT

COATING TYPE INTERIOR ENVIRONMENTS EXTERIOR ENVIRONMENTS

Drying Oil SSPC SP 2 SSPC SP 3

Alkyd SSPC SP 6 / NACE 3

SSPC SP3 For Localized Areas

SSPC SP 11

Asphaltic SSPC SP 3 SSPC SP 11

Latex SSPC SP 6 / NACE 3 SSPC SP 11

(092036) 09 91 00-11 (Repair AHU O-Club, B462)

Vinyl Lacquer SSPC SP 10 / NACE 2

Chlorinated Rubber SSPC SP 10 / NACE2

Epoxy SSPC SP 6 / NACE 3 SSPC SP10 / NACE 2

Polyurethane SSPC SP 10 / NACE 2

Organic Zinc SSPC SP 6 / NACE 3 SSPC SP 10 / NACE 2

Inorganic Zinc SSPC SP 10 / NACE 2 SSPC SP 5 / NACE 1

Where conflicts exist between manufacturer’s written requirements and those listed in this table, the higher level of cleaning method shall be followed.

C. The following water jetting levels may be substituted where an abrasive blasting method is not allowed due to environmental conditions, the project location or worker safety restrictions.

SURFACE PREPARATION SUBSTITUTION LIST

STANDARD SPECIFIED EQUIVALENT WATER JETTING

STANDARD

SSPC SP 5 SSPC SP 12 WJ 1 / NACE 5

SSPC SP 10 SSPC SP 12 WJ 2 / NACE 5

SSPC SP 6 SSPC SP 12 WJ 3 / NACE 5

SSPC SP 7 SSPC SP 12 WJ 4 / NACE 5

3.4 GALVANIZED METAL SURFACES

A. New Galvanized surfaces should be weathered a minimum of 6 months prior to painting. New or

Existing Galvanized Surfaces With Only Dirt and Zinc Oxidation Products shall be cleaned with solvent, or non - alkaline detergent solution in accordance with The Society for Protective Coatings

(formerly Steel Structures Painting Council), Surface Preparation Level 1 (SSPC SP 1).

B. Galvanized with Slight Coating Deterioration or with Little or No Rusting: Water jetting to The Society for Protective Coatings (formerly Steel Structures Painting Council), Surface Preparation Level 12

(SSPC SP 12 WJ 3) to remove loose coating from surfaces with less than 20 percent coating deterioration and no blistering, peeling, or cracking. Use inhibitor as recommended by the coating manufacturer to prevent rusting.

C. Galvanized With Severe Deteriorated Coating or Severe Rusting: Water jet to The Society for

Protective Coatings (formerly Steel Structures Painting Council), Surface Preparation Level 12

(SSPC SP 12 WJ 3) degree of cleanliness. Spot abrasive blast rusted areas as described for steel in

Steel Structures Painting Council, Surface Preparation Level 6 (SSPC SP 6), and waterjet to The

Society for Protective Coatings (formerly Steel Structures Painting Council), Surface Preparation

Level 12 (SSPC SP 12 WJ 3) to remove existing coating.

3.5 NON - FERROUS METALLIC SURFACES

A. Aluminum and aluminum - alloy, lead, copper, and other nonferrous metal surfaces. Surface

Cleaning: Solvent clean in accordance with The Society for Protective Coatings (formerly Steel

Structures Painting Council), Surface Preparation Level 1 (SSPC SP 1) and wash with mild non -alkaline detergent to remove dirt and water soluble contaminants.

3.6 GYPSUM BOARD

A. Fill all minor irregularities left by drywall finishers and sand to a smooth level surface. Exercise care to avoid raising nap of paper. Must be clean and dry. All nail heads must be set and spackled.

(092036) 09 91 00-12 (Repair AHU O-Club, B462)

Spackled nail heads and tape joints must be sanded smooth and all dust removed prior to the application of paint. Joints must be taped and covered with joint compound.

B. Surface Cleaning: Plaster and stucco shall be clean and free from loose matter; gypsum board shall be dry. Remove loose dirt and dust by brushing with a soft brush, rubbing with a dry cloth, or vacuum

- cleaning prior to application of the first coat material. A damp cloth or sponge may be used if paint will be water-based.

C. Repair of Minor Defects: Prior to painting, repair joints, cracks, holes, surface irregularities, and other minor defects with patching plaster or spackling compound and sand smooth.

D. Allowable Moisture Content: Do not apply epoxies to damp surfaces as determined by ASTM D

4263. New plaster to be coated shall have a maximum moisture content of 8 percent, when measured in accordance with ASTM D 4444, Method A, unless otherwise authorized. In addition to moisture content requirements, allow new plaster to age a minimum of 30 days before preparation for painting.

3.7 WORKMANSHIP

A. Employ only skilled mechanics. Application to interior wall and ceiling surfaces may be by brush or roller. Spray application will be permitted only upon approval from Architect. Application to hollow metal doors and frames shall be by spray.

B. Keep equipment in proper condition to provide a job commensurate with intent of specification.

C. Mix, and apply materials as recommended by manufacturer.

D. Tint priming and undercoats to approximate shade of final coat, except for vivid colors. These, if suggested by manufacturer, shall be applied over a pure white base coat of like material.

E. Maintain a rough schedule showing when painter expects to complete respective coats of paint for various areas. Keep schedule current as job progress dictates.

F. Do not apply succeeding coats until the Architect and Owner’s Representative has been notified and has had an opportunity to observe previous coat.

G. Protect painted surfaces and all adjacent work and materials by suitable covering during progress of work.

H. Evenly spread and smoothly flow on all materials for full, smooth, cover.

I. Provide complete coverage and hide. All paint systems are to "cover" to provide total color and sheen uniformity. When color or undercoats show through, apply additional coats until paint film is of uniform finish and color, at no additional cost to Owner.

J. Assure that all coats are thoroughly dry before applying succeeding coats.

K. Unless otherwise indicated, do not paint items which have a complete factory finish. A factory prime coat does not qualify as a complete factory finish.

L. Do not paint moving parts of valves, operating units, mechanical and electrical parts, such as valve and damper operators, sending devices, and motor and fan shafts.

(092036) 09 91 00-13 (Repair AHU O-Club, B462)

M. Do not paint over code labels, such as UL, FM, or equipment identification, or rating plates, etc.

unless there is a removable film over the label prior to painting.

N. Where spray painting is permitted or required, spray finish 100 SF as a sample. For metal doors and frames, one door and frame shall receive spray finish as a sample. Approved sample will constitute standard for subsequent work.

O. Paint interior of ductwork behind grilles flat black. Paint access panels, registers, etc., unless pre-finished, the same color as adjacent walls or ceiling. Where adjacent surfaces do not require paint, use such color as directed by Architect.

P. Touch up suction or hot spots in drywall and / or concrete before applying succeeding coats.

Q. Follow manufacturers label instructions exactly.

R. Schedule and coordinate work with other trades.

3.8 CLEANUP

A. Protect adjacent work, whether to be painted or not, against damage by painting and finishing work.

Leave all such work undamaged. Clean, repair or replace, and repaint, damaged work as directed by Architect.

B. Remove temporary protective wrappings, provided by others for protection of their work, after completion of painting operations. Upon completion of work, clean all window glass and other paint spattered surfaces. Remove spattered paint by proper methods of washing and scraping. Use care not to damage finished surfaces.

C. Remove any surplus materials, scaffolding and debris, leave areas broom clean.

3.9 WASTE MANAGEMENT

A. Do not use kerosene or any such organic solvents to clean up water based paints. Properly dispose of paints or solvents in designated containers. Close and seal partially used containers of paint to maintain quality as necessary for reuse. Store in protected, well - ventilated, fire - safe area at moderate temperature. Place materials defined as hazardous or toxic waste in designated containers.

3.10 COLOR SCHEDULE

A. Apply paint in colors, textures, and patterns of wall coating systems as selected by the Owner’s

Representative. Colors of finish coats shall match existing adjacent surfaces or as selected by the

Owner’s Representative. Manufacturers' names and color identification are used for the purpose of color identification only. Named products are acceptable for use only if they conform to specified requirements. Products of other manufacturers are acceptable if the colors approximate colors indicated and the product conforms to specified requirements. Tint each coat progressively darker to enable confirmation of the number of coats.

3.11 PAINT SCHEDULE

A. The schedule shown hereinafter is not intended as a listing of surfaces to be painted; it indicates only the type and minimum number of coats of paint to be applied to those surfaces which are to be painted. All surfaces painted shall have total color and sheen uniformity.

(092036) 09 91 00-14 (Repair AHU O-Club, B462)

B. General: Provide the following paint systems for the various substrates indicated.

3.12 PAINT SCHEDULE: EXTERIOR

A. Ferrous Metal: Primer is not required on shop primed items. (All Exterior Metals including -

Miscellaneous Steel designated to be painted)

1. Aliphatic Polyurethane: Minimum 2 finish coats over a primer with total dry film thickness not less than 11 mils excluding primer.

a. Primer: Synthetic Rust Inhibiting Lead and Chromate Free Primer with a minimum solids by weight of 67 percent and solids by volume of 42 percent with a total dry film thickness to develop a dry mil thickness of not less than 2 mils. (AZ - Cote - All)

b. First Coat: Self priming 2 component high build epoxy with a minimum solids by weight of 87.2 percent and solids by volume of 81 percent to develop a dry mil thickness of not less than 5 mils. (Mult - E - Poxy 180)

c. Finish Coat: Two component, aliphatic polyurethane with a minimum solids by weight of 75 percent and solids by volume of 62 percent to develop a dry mil thickness of not less than 6 mils. (Pinnacle 330HS)

B. Aluminum and Zinc - Coated Steel Metal: (All Exterior Aluminum and Zinc - Coated Steel Metal etc.

designated to be painted)

1. Aliphatic Polyurethane: Minimum 2 finish coats with total dry film thickness not less than 11 mils and to provide total color and sheen uniformity.

a. First Coat: Self priming 2 component high build epoxy with a minimum solids by weight of 87.2 percent and solids by volume of 81 percent to develop a dry mil thickness of not less than 5 mils. (Mult - E - Poxy 180)

b. Finish Coat: Two component, aliphatic polyurethane with a minimum solids by weight of 75 percent and solids by volume of 62 percent to develop a dry mil thickness of not less than 6 mils. (Pinnacle 330HS)

3.13 SCHEDULE: INTERIOR

A. Gypsum Drywall Systems: (Glaze Paint)

1. Epoxy Mastic: Self priming 2 component high build epoxy with a minimum solids by weight of 87.2 percent and solids by volume of 81 percent. Minimum 2 finish coats over a primer with total dry film thickness to develop a dry mil thickness of not less than 10 mils excluding primer and to provide total color and sheen uniformity.

a. Primer: Vinyl Acrylic Latex low odor latex primer / sealer with a minimum solids by weight of 43 percent and solids by volume of 26 percent with a total dry film thickness to develop a dry mil thickness of not less than 1.5 mils. (DU - 1507 Interior

PVA)

b. First Coat: Epoxy Mastic (Mult - E - Poxy 180).

c. Finish Coat: Epoxy Mastic (Mult - E - Poxy 180).

(092036) 09 91 00-15 (Repair AHU O-Club, B462)

B. Existing Painted Gypsum Drywall Wall Systems:

1. Interior Latex Eggshell: Interior Latex with a durable eggshell finish, with a minimum solids by weight of 45 percent and solids by volume of 35 percent. Minimum 2 finish coats existing painted surface with total dry film thickness not less than 4 mils excluding primer and to provide total color and sheen uniformity.

a. First Coat: Interior Latex Eggshell (DE - Pro Plus).

b. Finish Coat: Interior Latex Eggshell (DE - Pro Plus).

END OF SECTION