SOLICITATION NO. FA4497-11-R-0009

CONTRACT NO.

Attachment 5

MANDATORY VERIFICATION SCHEDULE

PROJECT NUMBER: 101038

3 Feb 10

The work listed herein requires mandatory verification by the Government Inspector before any follow-on work is allowed to start. The Contractor must provide evidence of verification by the individual designated as responsible for the Contractor's inspection program, that the work to be verified by the Government complies with these specifications and drawings. The Contractor shall notify the Government Inspector that the work is ready for verification according to the schedule below:

WORK SPECIFICATION OR NOTIFICATION DATE SCHEDULED

INSPECTION

DESCRIPTION DRAWING REFERENCE REQUIRED FOR INSPECTION

COMPLETED

Requirement to Specs 02080 5 work days Shut down utilities

Start of asbestos Abatement Specs 02080 10 work days