This is a material submittal schedule spreadsheet for the refurbishment of the Ultimate Warrior Statue at Building 5483. The form outlines required contractor submissions including conservation credentials, insurance coverage documentation, paint specifications, and structural repair material details. Each item requires specific types of submittals such as certifications of compliance, shop drawings, samples, or manufacturer recommendations.
The associated solicitation (FA448424Q0046) from the Department of the Air Force Air Mobility Command outlines a 120-day performance period for moving, refurbishing, and replacing the statue at Joint Base McGuire-Dix-Lakehurst, NJ. This is a small business set-aside under NAICS 238990 ($19M size standard). A site visit is scheduled for February 18, 2025, at 10:00 EST at Building 5418, with required visitor information due by February 13, 2025. Questions are due by February 21, 2025, at 12:00 PM EST. The contract will be awarded using lowest price technically acceptable evaluation criteria.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | Bldg 5483, Ultimate Warrior Statue | Refurbish Ultimate Warrior Statue | SOLICITATION/CONTRACT NUMBER | |
| TO BE COMPLETED BY THE PROJECT ENGINEER (Fill in the numbers of each submittal required) | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||
| LINE NUMBER | ITEM OR DESCRIPTION |
OF ITEM, CONTRACT
REFERENCE, TYPE OF
SUBMITTAL CERTIFICATIONS OF COMPLIANCE SHOP DRAWINGS SAMPLES COLOR SELECTION MANUFACTURES RECOMMENDATIONS MANUFACTURES WARRANTY CATALOG DATA OPERATING INSTRUCTIONS SPECIFICATIONS STYLE/DESIGN REQUIRED
SUB-
MISSION
DATE DATE
RECEIVED
IN
CONTRACTING DATE TO
CIVIL
ENGINEERS RETURN
SUSPENSE
DATE FOLLOW-UP DATE
CONTRACTOR
| NOTIFIED | CONTRACTOR | ||||||
| RESUBMITTAL | FINAL | ||||||
| APPROVAL | REMARKS | ||||||
| APPROVED | DISAPPROVED | ||||||
| 1 | Conservation Credentials | x | |||||
| 2 | Insurance Coverage | x | |||||
| 3 | Paint | x | x | ||||
| 4 | Structural Repair Material | x | x | ||||
| 5 | |||||||
| 6 | |||||||
| 7 | |||||||
| 8 | |||||||
| 9 | |||||||
| 10 | |||||||
| 11 | |||||||
| 12 | |||||||
| 13 | |||||||
| 14 | |||||||
| 15 | |||||||
| 16 | |||||||
| 17 | |||||||
| 18 | |||||||
| 19 | |||||||
| 20 | |||||||
| 21 | |||||||
| 22 | |||||||
| 23 | |||||||
| 24 | |||||||
| 25 |