SOW DOMESTIC WATER REV 2 22 APR 11.docx
DOCX document 1 MB Posted
- Attached to
- Joint Base Domestic Water Piping Federal contract opportunity
- Solicitation number
- FA4484-10-R-0042
About this file
Attachment C-1 Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Domestic Water Piping Questions Answered.docx | DOCX document | |
| Enviornmental Compliance Statement.doc | DOC document | |
| FA4484-10-R-0042.pdf | ||
| Solicitation Cover Letter.pdf | ||
| Past Performance Questionaire Cover Letter.doc | DOC document | |
| Past Performance Questionaire.docx | DOCX document | |
| Wage Determination JB MDL Domestic Water.doc | DOC document | |
| DOMESTIC WATER IDC BS REV 2 22 APR 11.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION
FOR
REPLACING
DOMESTIC WATER PIPING
AT
JOINT BASE MCGUIRE-DIX-LAKEHURST, NEW JERSEY
PROJECT NO. PTFL
April 22, 2011
PTFL 04-1001 01000-14
TABLE OF CONTENTS
SECTION TITLE PAGES
DIVISION 1 - GENERAL REQUIREMENTS
| 01000 | Statement of Work | 01000-1 to 01000-39 | ||
| 01012 | Special Conditions | 01012-1 to 01012-5 | ||
| 01300 | Submittals | 01300-1 to 01300-3 | ||
| 01356 | Storm Water Pollution Prevention Measures | 01356-1 to 01356-5 | ||
| 01400 | Quality Control | 01400-1 to 01400-3 | ||
| 01401 | Domestic Water Testing | 01401-1 to 01401-3 | ||
| 01540 | Affirmative Procurement | 01540-1 to 01540-5 |
DIVISION 2 – SITEWORK
| 02080 | Asbestos Removal | 02080-1 to 02080-13 | |||
| 02222 | Excavating | 02222-1 to 02222-2 | |||
| 02223 | Backfilling | 02223-1 to 02223-3 | |||
| 02225 | Trenching | 02225-1 to 02225-3 | |||
| 02231 | Aggregate Base Course | 02231-1 to 02231-3 | |||
| 02510 | Asphaltic Concrete Paving | 02510-1 to 02510-3 | |||
| 02510a | Fire Hydrants and Associated Hardware | 02510a-1 to 02510a7 | |||
| 02923 | Landscape Grading | 02923-1 to 02923-2 | |||
| 02936 | Seeding | 02936-1 to 02936-4 |
DIVISIONS 3 - CONCRETE
| 03200 | Concrete Reinforcement | 03200-1 to 03200-2 |
| 03300 | Cast-In-Place Concrete | 03300-1 to 03300-5 |
DIVISION 4 – MASONRY (NOT USED)
DIVISION 5 - METALS (NOT USED)
DIVISION 6 - WOOD AND PLASTIC (NOT USED)
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07900 Joint Sealers 07900-1 to 07900-3
DIVISION 8 - DOORS AND WINDOWS (NOT USED)
DIVISION 9 – FINISHES (NOT USED)
DIVISION 10 – SPECIALTIES (NOT USED)
DIVISION 11 - EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14 - CONVEYING SYSTEMS (NOT USED)
DIVISION 15 - MECHANICAL
| 15010 | Mechanical General Requirements | 15010-1 to 15010-6 | |||
| 15030 | Mechanical Demolition | 15030-1 to 15030-1 | |||
| 15040 | Mechanical Project Closeout | 15040-1 to 15040-3 | |||
| 15110 | Valves | 15110-1 to 15110-3 | |||
| 15401 | Pipe Bursting | 15401-1 to 15401-5 |
DIVISION 16 - ELECTRICAL (NOT USED)
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01000
STATEMENT OF WORK
PART I - GENERAL
1.1 DESCRIPTION OF WORK: The contractor shall provide all plant, supervision, management, quality control, labor, tools, equipment, appliances and materials and perform all work necessary to construct, repair, and upgrade by method of Pipe Bursting/Direct Excavation (trenching) sections of the Domestic Water Pipes on Joint Base McGuire-Dix-Lakehurst. All new construction and repairs should include shop drawings, scheduling work, excavation, demolition and installation of piping, valves, fittings, accessories, and pavement, as well as provide temporary bypass support as listed. Pipe Bursting method consists of patented licensed hydraulic puller equipment and pneumatic ram-cutting heads to split and break old pipe while drawing in new welded-fused polyethelyene pipe in-place minimizing excavations and pavement restoration. Soil excavated for pipe bursting pits that are located in a high-visibility areas will be hauled off site by the contractor and stored until the pipe bursting operation is complete. In addition, the contractor will provide the testing, sanitizing, and de-watering of all affected areas. The contractor must also obtain New Jersey Department of Environmental Protection (NJDEP) permits required for performance of this project including, but not limited to Safe Drinking Water Act compliance and permits required under New Jersey Administrative Code (NJAC) 7:10-1.1 et seq. Specifically the contractor shall meet the standards for construction of public community water systems as set forth in NJAC 7:10-11.1 to -11.17. All of this and all other work performed as part of this contract shall be completed in strict accordance with the specifications forming parts thereof, subject to the terms and conditions of the contract.
1.2 LOCATION: The work site is located at various locations on JB MDL and will be site determined as appropriate and according to contract terms.
1.3 PRINCIPAL FEATURES: The work to be performed includes the principal features listed below. This general outline of principal features does not in any way limit the responsibility of the contractor to perform all work and furnish all plant, labor, and material required by the specifications and drawings to perform a complete and permanent job to adequately fulfill the intent of these specifications and to deliver a work product(s) that is fit for its intended purpose. The inspection clause of any resultant contract for this work shall not in any way be interpreted as waiving the Government’s requirement that the work product(s) be fit for its intended purpose. Government inspections do not in any way constitute acceptance of work quality or fitness until the final acceptance inspection is made.
Principle features include: shop drawings, scheduling work, boroscope survey, excavation, demolition, disposal and installation of piping, valves, fittings, and restoration of disrupted grounds and pavement, and provided temporary bypass of domestic water and/or contained potable water as related to the work.
1.4 ENVIRONMENTAL COMPLIANCE: The contractor is required to comply with all applicable State and Federal laws, State and Federal regulations, and Air Force Instructions in effect at the time of performance of this contract. The laws and regulations include, but are not limited to: Environmental and Occupational Safety and Health. The contractor shall be responsible for compliance with construction and operating permits, and is also responsible for penalties, fines, or natural resource damage claims that may be required or assessed by the State of New Jersey, Federal or Local Governments resulting from contractor performance, or failure to perform, during the course of this contract. The Government will inspect for environmental compliance at its discretion, and will notify the Contracting Officer (CO) of any discrepancies found (see paragraph 1.19 for CO authority). In addition, the contractor may be subject to contractual sanctions including, but not limited to withholding, offset, termination, suspension, debarment, and adverse past performance assessment.
A. CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The contractor shall perform work under this contract consistent with the relevant policy and objectives identified in this section and in the JB MDL environmental management system (EMS). The contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified in this section and by the JB MDL EMS (administered by the 87 CES/CEAN). The contractor shall also provide monitoring and measurement information as necessary for the 87 CES/CEAN to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the contractor shall respond and take corrective action immediately. In the case of a nonconformance, the contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator (87 CES/CEAN). In addition, the contractor shall ensure that their employees are aware of the roles and responsibilities identified in this section and how these requirements affect their work performed under this contract.
All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site by the contractor. The CO’s Representative will verify that the contractor has received EMS Awareness Training provided by the 87 CES/CEAN during the pre-construction conference for their project site or location.
B. SOLID WASTE, HAZARDOUS WASTE AND HAZARDOUS MATERIALS: The contractor is responsible for the proper handling, disposal, and costs of solid and hazardous wastes and hazardous materials generated by or utilized during the course of its activities. Proper handling also includes recycling and material recovery. The terms solid and hazardous wastes, and hazardous materials, include, but are not limited to, those defined in the Federal Water Pollution Control Act, the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, the Solid Waste Disposal Act, the Clean Air Act, and the Toxic Substances Control Act, the New Jersey Solid Waste Management Act, the New Jersey Water Pollution Control Act, the New Jersey Air Pollution Control Act and the regulations promulgated pursuant to those Acts. The contractor shall also be responsible for any enforcement action that may be taken by the State of New Jersey, other State or the Federal Government related to handling, transportation and the proper disposal of solid and hazardous waste and hazardous materials. If notification, certifications, documentation, manifests, permits or any other written materials are required by law to be obtained, prepared and/or submitted, the contractor shall prepare same and provide a written copy to the CO, and a copy to the Environmental Flight (87 CES/CEAN) within the timeframes set forth in the law and regulations governing the action. Hazardous waste manifests must be signed by the Environmental Flight Hazardous Waste Coordinator, Building 2403. JB MDL is not responsible for any hazardous materials brought on base by the contractor that may become hazardous waste during the course of performance. Contractor shall remove those materials from the base at their own expense and risk.
1. Source Separation of Solid Waste: Wastes shall be placed in closed metal containers that are emptied before the capacity of each container is exceeded. Solid waste shall be separated and placed in individual containers in a manner that facilitates recycling of the various categories of waste. Contractor is responsible for the handling and the associated costs of disposal for all solid wastes generated. Cardboard and all types of metal shall be source separated and recycled. Recyclable materials shall be delivered to the Recycling Center, building #2321 or an appropriate off-site facility.
2. Hazardous Material Handling: Any hazardous material or chemical to be used or stored by the contractor must be approved, in writing, by the CO prior to the contractor bringing it on the Base. The contractor must utilize an AF Form 3000, Material Approval Submittal, listing each container of hazardous material stored, kept, or utilized, to include Material Safety Data Sheets (MSDS). MSDS sheets must also be displayed on-site for access by contractor employees as well as the Government, per OSHA requirements.
3. Solid Waste Disposal Report: Monthly the contractor shall submit a solid waste disposal report and/or recycling report to the CO with a copy to 87 CES/CEAN. For each waste, the report shall state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste. The contractor shall include copies of the waste handling facilities' weight tickets, receipts, bills of sale, and other sales documentation. In lieu of sales documentation, the contractor may submit a statement indicating the disposal location for the solid waste which is signed by an officer of the contractor firm authorized to legally obligate or bind the firm. The sales documentation or contractor certification shall include the receiver's tax identification number and business, EPA or State registration number, along with the receiver's delivery and business addresses and telephone numbers. For each solid waste retained by the contractor for his own use, the contractor shall submit on the solid waste disposal report the information previously described in this paragraph. Prices paid or received shall not be reported to the CO unless required by other provisions or specifications of this Contract or public law.
C. CLEAN AIR ACT PERMITS: JB MDL is responsible for obtaining and renewing all air permits for all stationary sources on Base that are owned by the Government and for mobile sources such as Government vehicles. Permits are required for boilers 1 MMBtu/Hr and larger, emergency generators larger than 100KW, stationary reciprocating engines larger than 37KW (not including emergency generators), and tanks containing fuel or anything other than air distillates greater than 10,000 gallons. The contractor shall provide written notification to the CO and 87 CES/CEAN office thirty (30) days prior to bringing any equipment of this threshold size on base. It is the contractor’s responsibility to apply for, submit fees and obtain air permits for all contractor-owned and contractor installed air pollution sources. Amendment of JB MDL”s (Dix, McGuire and/or Lakehurst)’s Title V air permit will be required for all sources meeting and exceeding New Jersey Department of Environmental thresholds. The contractor, if maintaining equipments as part of scope, such as the central heat plant, is responsible for compliance with the Government’s air permits and shall maintain all documentation and record keeping required to support those permits in a format acceptable to and approved by the CO. The documentation must be prepared and maintained by the contractor and readily available for on-site inspection by environmental regulators. Air permitting requirements for equipment that is to be installed as part of this contract shall be coordinated with the 87 CES/CEAN Air Program Manager. All permits must be obtained prior to the equipment arriving on base and prior to installation. Permit fees for equipment to be installed shall be paid for by the contractor.
D. LAND USE: Development, including building of docks, piers, bulkheads, bridges, pipelines, cables and filling, dredging or removing of sand or other materials near or on navigable waterways requires a permit. Activities that occur within 300 feet of a wetland may require a permit. Where permits are required, the contractor shall prepared the permit application(s), in coordination with the 87 CES/CEAN Water Program Manager and submit the appropriate fee(s).
E. WATERS AND WATER SUPPLY: It is not permissible to discharge any materials to the navigable waters of the United States without a permit. Accordingly, discharges to or in areas that may reasonably reach or impact wetland areas and all other watercourses, including ditches, is prohibited without a permit. All discharges to storm drains, including but not limited to, soils and sediments contained in water runoff or dewatering operations, are prohibited. An appropriate soil erosion control plan shall be developed and utilized by the contractor for construction projects to ensure that discharges do not occur. Contractor shall comply with JBMDL’s Storm Water Pollution Prevention Plans for each area of the base, copies of which are available in 87 CES/CEAN, in Building 2403 at McGuire, Building 5 at Lakehurst, and Building 5317 at Dix. Projects that disturb one acre or larger during the construction process will require an application to either the Burlington County Soil Conservation District (BCSCD), or Ocean County Soil Conservation District as appropriate for each area, as well as a request for authorization (RFA) for authority to discharge storm water from a small construction activity general permit from the New Jersey Department of Environmental Protection (NJDEP). These submittals shall be prepared by the contractor. The RFA is submitted electronically to the NJDEP. All fees are submitted to the New Jersey Department of Environmental Protection shall be paid by the contractor. Please see Specification Section 01356 Stormwater Pollution Prevention, which is incorporated in its entirety by reference here, and appropriate engineering drawings of this contract for more specific erosion and sediment control requirements.
Projects which disturb more than 5000 square feet must incorporate stormwater discharge controls in accordance with Section 438 of the Energy Independence and Security Act of 2007. The contractor shall follow the design requirements for NJAC 7:8 Stormwater Management to meet the goals of EISA Section 438.
Projects which involve the installation or repair of water mains, wells, or drinking water treatment systems may require permits from the NJDEP. The contractor shall prepare the required permit application in coordination with 87CES/CEAN Water Program Manager. All fees are submitted to the New Jersey Department of Environmental Protection shall be paid by the contractor.
Projects which involve installation of wastewater systems shall be designed to discharge to the JBMDL sanitary sewer system. The discharge of untreated industrial waste is prohibited.
F. LEAD PAINT AND ASBESTOS: If lead paint and/or asbestos materials are to be abated or removed pursuant to this contract, see specification Sections 02081 and/or 02080 respectively for contractor requirements. If this contract does not contain those Sections, and lead paint and/or asbestos is found or suspected during the execution of this contract, the contractor, at their expense, shall have those substances tested by a certified laboratory in accordance with the protocol set forth in New Jersey and Federal law. If the contractor positively identifies these materials at the action level set forth in the law and regulations, he must notify the CO by providing the laboratory results and cease work in those areas that might disturb those items until abatement issues are addressed and resolved. Work may continue as long as the suspected or identified materials are not disturbed.
G. NOTIFICATION OF ENVIRONMENTAL SPILLS: In the event that the contractor spills or releases any unpermitted substance, hazardous substance or hazardous waste into the environment, the contractor shall immediately report the incident to the Fire Department, the CO, and the designated Government representative. The contractor shall be liable for the costs of clean up and remediation of any spills or the release of such substance into the environment.
H. FUEL STORAGE: Gas or diesel fuels shall not be stored on the construction site, or on Base, without prior written approval from the CO. Appropriate containers shall be utilized.
I. ENVIRONMENTAL PROTECTION PLAN: The contractor shall prepare and submit for review and approval an environmental protection plan to the COR that details how the contractor intends to fulfill the requirements of the paragraphs 1.4 A through I, above. The plan shall be submitted at least 30 days prior to the start date of the contract’s first delivery order.
J. DRINKING WATER PROTECTION: The contractor must specifically comply with the following laws and regulations:
1. Federal Safe Drinking Water Act, 421 U.S.C. 300f to 300j-26;
2. National Primary Drinking Water Regulations, 40 C.F.R. 141.1 to 141.175 (Also Parts 142 and 143).
3. New Jersey Safe Drinking Water Act, N.J.S.A. 58:12A-1 to 25;
4. New Jersey Water Supply Management Act Regulations, N.J.S.A. 58:1A-1 to 17;
5. New Jersey Safe Drinking Water Act Regulations, N.J.S.A. 7:14B-1.1 to 4.10 (See N.J.S.A. 7:14B-1.6 “Wellhead protection area”.)
1.5 HEALTH AND SAFETY PLAN: Prior to commencing work, the contractor shall prepare and submit a site/contract specific health and safety plan in accordance with Occupational Safety and Health Act (OSHA) 1910 standards, that are applicable to construction, for review by the CO. The plan will include worker’s safety, confined spaces, OSHA training, handling of hazardous materials (including Material Safety Data Sheets (MSDS)) such as asbestos and fuel discharges, and other site safety considerations. Government approval of plan is required prior to starting work of the contract’s first delivery order.
1.6 AS-BUILT DRAWINGS: N/A
1.7 DATABASE: N/A
1.8 SPECIFICATION DIVISION: These specifications are divided into several trade sections for convenience only and not to establish the units of work required of any trade. The contractor shall be responsible for the allocation and coordination of the work between appropriate trades.
1.9 SUBMITTALS: Items shall be submitted after receipt of Notice to Proceed, within time limits prescribed on the Material Approval Submittals List and in accordance with Section 01300, SUBMITTALS. Materials or equipment shall not be ordered, released for production, shipped or installed until submissions have been approved by the CO. All submittals shall be verified by the contractor as being in full compliance with requirements of these project specifications and/or drawings. Submittals received without the contractor’s certification will be returned, without action, for the contractor’s certification and re-submittal. The CO will not accept partial submittals for approval of materials and/or equipment for review. The CO reserves the right to accept for review partial submittals (in order to expedite construction if necessary) under the condition that the review timeframe is waived. The contractor shall be responsible for submitting for approval, at one time, all items of material and/or equipment that are part of a given system, i.e., for an air conditioning system. Submittals shall be made at the same time for piping, insulation, condensing units, air-handlers, pumps, valves, shop drawings, controls and other components that make-up the required work feature. This requirement shall hold for heating systems, hardware schedules, electrical materials and equipment, roofing systems and all other items required by Material Approval Submittal List. The submittal schedule shall include, among other items, the CPM schedule and the Quality Assurance Plan (both discussed further below).
1.10 PASS AND IDENTIFICATION:
A. The contractor shall obtain the necessary passes and/or identification for entry into JB MDL for himself, all employees and subcontractors prior to commencement of work. Procedures and limitations for entry control are addressed in depth in the Installation Entry Control Procedures at the end of this section. The Government reserves the right to refuse to issue a pass to any and all employees of the contractor for any reason deemed appropriate by the Government and in doing so shall not be entitled to equitable adjustment or relief under the Contract Disputes Act. The Entry Screening Facility may be contacted at (609) 754-3938/3628/2200. The Government will issue passes depending on the type of work to be completed and the length of the contract. The maximum length of these passes is 30 days. The contractor shall be responsible for obtaining additional passes upon the expiration of each pass issued. The Government may inspect at its discretion, all vehicles including those with vehicle passes.
B. Prior to entering JB MDL, commercial/over-sized vehicles shall be inspected at Checkpoint 9 located on Saylors Pond Road at the Dix Area of JB MDL for the Dix and the McGuire Areas. The contractor shall anticipate delays during the inspection process as well as delays due to vehicle queues.
C. Conditions caused by Force Majeure (acts of war, terrorism, nature, etc.) shall be addressed via contract time extension, where warranted, at no cost only. The contractor shall anticipate that in the event of heightened alert, access to JB MDL may be denied for approximately three to five days. The contractor shall also anticipate that during periods of heightened alert, time required to access JB MDL may increase.
1.11 SCHEDULE OF WORK:
A. Work shall normally be accomplished during the standard 8-hour day, 5-day week, 0730hrs to 1615hrs, Monday through Friday excluding Federal holidays. Work outside these hours must be approved by the CO at least one (1) workday prior to proposed work.
B. The contractor shall notify the CO or his representatives two working days prior to moving to the work site to commence work and one working day prior to resumption of work at the site after an interruption of more than two (2) working days.
C. Emergency Repair: Some Delivery Order's may be labeled as Emergency Work; in these cases work shall start within two (2) days of Delivery Order Issuance and be completed within ten (10) days of issuance. In this case if necessary, the contractor shall provide the COTR a work schedule that may include hours outside of those listed in section (A) above. The CO must approve work outside these standard hours at least one (1) workday prior to proposed work.
1.12 INSPECTION: Inspection of work by the Government is for the sole benefit of the Government. The contractor is fully responsible for supplying all necessary quality and technical inspections during the normal progress of work. Review of work in progress by the Government at any time prior to the Final Acceptance Inspection does not constitute interim or final acceptance. At the discretion of the CO, inspection may be directed of work-phased work segments at their completion and prior to initiation of any further work. If phased inspection is directed, the contractor shall notify the CO in writing at least fourteen (14) days prior to expected completion of the phase to be inspected. Such inspection shall not relieve the contractor for variations or unacceptable conditions discovered up to and including the Final Acceptance Inspection. Destructive testing may be required and shall be performed by the contractor at the direction of the CO. Work tested in this fashion shall be compensated only if found to conform to the contract requirements. The contractor shall provide the COTR with a daily report log (Contractor Production Report (CPR)). This log shall be reviewed and agreed/disagreed to by both the contractor and COTR. This log shall identify the number of personnel on site (general contractor and/or sub contractor(s)) and the work accomplished that day. A copy (with signatures) shall be presented to the COTR as part of the documentation of daily progress.
1.13 PRELIMINARY AND FINAL INSPECTIONS: The contractor shall request scheduling of the final and pre-final inspections in writing a minimum of ten (10) work days in advance of project completion. The request for scheduling will be in writing to the CO. Deficiencies shall be corrected within fourteen (14) days of the pre-final inspection.
1.14 COORDINATION OF TRADES: (N/A)
1.15 UTILITIES:
A. The Government shall make all reasonable amounts of domestic water and electricity available to the contractor without charge. The Contractor shall carefully conserve any utilities furnished by the Government. The Contractor, at his/her expense and in a workmanlike manner satisfactory to the Contracting Officer’s Technical Representative (COTR), shall install and maintain all necessary temporary connections and distribution lines, and all meters (if necessary) to measure the amount of each utility used. The Contractor shall furnish to the CO for approval, a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical and water systems. The Contractor shall make arrangements with the COTR, as to the method of determining the amount of water and electricity being used. Telephone service is the responsibility of the Contractor, and shall be coordinated with the COTR and the local communication company. Before final acceptance of the work by the Government, the Contractor shall remove all temporary connections, distribution lines, meters and associated paraphernalia.
B. BASE FIRE HYDRANT USE PERMIT: Prior to the contractor using any fire hydrant on base as source of water, the contractor shall obtain a Permit to Use Fire Hydrant from the Utility Section of the 87th Civil Engineer Squadron. The contractor will be responsible for providing all the equipment necessary to connect to the fire hydrant including, but not limited to the following: fire hydrant wrench, backflow device, hoses and if necessary a valve. The contractor shall adhere to the Fire Hydrant Use Rules and Regulations which are attached to the end of this Section during the use of any fire hydrant. The contractor shall provide the COTR with a copy of the approved Fire Hydrant Use Permit prior to using any fire hydrant on base.
C. INTERRUPTION OF UTILITIES: Contractor shall perform the work under their contract with a minimum of outage time for all utilities. Contractor shall give written notification to the CO at least ten (10) working days in advance of his need for a proposed utility outage. Contractor will provide temporary heat and/or domestic hot water if outage is expected to be longer than eight (8) hours continuous duration. This time period shall include start-up and cool-down periods. The utilities may be interrupted only when approved in writing by the CO. Because of mission requirements, utility interruptions may have to be scheduled at a time other than that requested by the contractor.
D. ROAD CLOSURE: Contractor will provide two (2) weeks written notification to CO prior to roadway closures for utility runs. Contractor shall attempt to maintain traffic flow by working half roadway at a time.
1.16 TOILET FACILITIES: Government toilet facilities will not be available for contractor's or subcontractor's personnel use. Contractor shall provide temporary sanitation facilities: All temporary sewer and sanitation facilities shall be self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the CO. The doors shall be self-closing. The exterior of the unit will match the base standard color, “Dark Brown”. Locate the facility behind the construction fence or out of the public view. COTR shall approve location.
1.17 CONSTRUCTION SIGN: A construction sign shall be erected on the construction site. The location of the sign will be facing the street. The exact location will be coordinated by the COTR. Instructions on how to construct the sign are attached to the end of this Section. Color of sign shall be in accordance with Federal Standard 595; background shall be Federal Color #20040 and lettering shall be #23617.
1.18 FIRE DEPARTMENT EMERGENCY ACCESS: (N/A)
1.19 EMERGENCIES: In case of an emergency, the CO, Security Forces personnel, Base Fire Chief, and Base Operations Officer, or their representatives, shall have the authority to order the contractor to stop work and clear the area of personnel and equipment. The contractor shall comply with such an order with all possible speed. After clearing the work site as instructed, the contractor shall immediately inform the CO of all verbal or written stop work orders. In the case of being halted by Security Forces personnel, the Fire Chief or Base Operations Officer, the contractor shall notify the CO in writing and provide explanation for the stoppage.
1.20 AUTHORITY: Except as noted below, the term “Contracting Officer” as used in this specification includes the authorized representative of the CO acting within the limits of his/her authority. With respect to all paragraphs of the specifications citing “approval by the Contracting Officer” and all paragraphs cited in Material Approval Submittals, of the solicitation, the term “Contracting Officer” means only those individuals properly appointed as a CO within the Contracting Squadron; no other Government personnel has the authority to grant such approval. This includes the Contracting Officer’s Technical Representative (COTR). The COTR has authority to review Material Submittal packages and recommend approval by the CO. At the Final Acceptance Inspection, the COTR will perform the inspection and recommend acceptance or conditional acceptance to the CO.
1.21 PROJECT CLOSE OUT SUBMITTALS:
At the completion of construction and before final payment, the contractor shall submit to the CO the following information, if required, for record and operation purposes. Close out submittals shall be submitted as specified in the various sections of the specifications and as one (1) complete package.
1. As-built drawings as specified in paragraph 1.06
2. Operation and maintenance data/manuals.
3. Guarantees, warranties.
4. Keys and keying schedule.
5. Spare parts and maintenance materials.
6. Special tools/fixtures/devices.
7. Real Property Records (see Capitalization Instructions attached to this section).
1.22 CONTRACTING OFFICER’S TECHNICAL REPRESENTATIVE (COTR):
The Commander, 87th Civil Engineering Squadron or his representative, is designated as the COTR. This designation includes, but is not limited to the following specific functions of this contract:
1. Technical administration and review of work in process.
2. Recommending approval/disapproval of shop drawings, samples and materials.
3. Reviewing and recommending approval/disapproval by the CO all applications for progress payments.
4. Reporting to the CO any work stoppage or discovered non-conforming work items.
5. Recommending destructive testing of work by the contractor to the CO. Testing materials not otherwise specified to be performed by the contractor or others.
6. Conducting Pre-Final and Final Acceptance Inspections to develop a recommendation to the CO for accepting/not-accepting the work.
1.23 DRAWINGS ACCOMPANYING SPECIFICATIONS: Drawings accompanying the specifications are the property of the Government and shall not be used for purposes other than those contemplated by the specifications.
1.24 BASE REGULATIONS: The contractor shall conform to all Base regulations and directives, as identified specifically at the pre-construction conference, that pertain to security, safety, traffic, fire and personnel clearances insofar as they apply to the contractor’s activities or as directed by the Contracting Officer. The contractor shall be responsible for providing and placing barricades, lighting and safety devices during construction activities.
1.25 COORDINATION OF WORK OPERATIONS: The work to be performed under this contract is on an active military base. The contractor shall coordinate work operations with the COTR prior to starting work under this contract. The contractor shall have a superintendent who speaks, reads, writes and understands the English language; has authority to act for the contractor and to be available on the job site throughout each work day. The contractor shall be responsible for his quality control at all times. A specific individual shall be designated as the contractor’s quality control inspector and identified to the COTR at the pre-construction conference.
1.26 CONTRACTOR’S PARKING: The contractor’s employees shall park in the areas assigned by the COTR.
1.27 CONTRACTOR’S EMPLOYEE RESTRICTIONS: The contractor’s employees shall be restricted to areas within this scope of work plus direct routes to and from the site as may be approved in the pre-construction conference with regard to work scheduling and material handling.
1.28 GOVERNMENT FURNISHED PROPERTY (GFP): N/A
1.29 REAL PROPERTY RECORDS: Within fourteen (14) workdays of construction completion, and prior to final payment, the contractor shall complete the attached Capitalization Instructions which include the “Building Checklist” and other associated documents. The Checklist, including the scope of work, real property installed equipment listing, letter of final inspection, list of discrepancies and drawings are to be returned to the CO. Once reviewed and final concurrence from the JB MDL Real Estate Management Office (REMO), located in Building 5318, Dix Area, is received and all deficiencies have been corrected, then the contractor may submit the invoice for final contract payment. Should the Checklist be returned to the contractor for corrections, the contractor shall make the corrections and return the Checklist within fourteen (14) workdays.
1.30 DELAYS DURING CONSTRUCTION: If at any time during construction should a situation be encountered which serves to delay the execution of all work for an indefinite period of time and upon receipt of a written suspension notification from the Contracting Officer, the contractor shall demobilize his work crews as well as those of his subcontractors as soon as possible. In that event, the contracting officer will furnish advance notice for restarting the job and allow a remobilization period (the length of which to be commensurate with the delay period, but no longer than 60 days) prior to required work recommencement. Otherwise, the length of work suspension will be identified in the written suspension notification. The contractor shall not be required to “standby” for an indefinite duration unless specifically directed to do so. (Note: this paragraph does not apply to national emergencies, sovereign acts or Force Majeure, which are covered under other contract provisions.)
1.31 PHYSICAL DATA (N/A)
1.32 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
A. This provision specifies the procedure for determination of time extension for usually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
1 The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month. Determination of usually severe weather conditions will be made by the COTR.
2 The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
B. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON (5) DAY WORK WEEK
| JAN | FEB | MAR | APR | MAY | JUN | JUL | AUG | SEP | OCT | NOV | DEC |
| (9) | (7) | (8) | (8) | (7) | (7) | (6) | (7) | (5) | (7) | (5) | (7) |
C. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CPR log, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2 above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)". (ER 415-1-5) (31 Oct 89).
1.33 QUALITY ASSURANCE PLAN:
A. The contractor shall prepare and submit within 30 days after Notice to Proceed, a Quality Assurance (QA) Plan appropriate for the work intended.
B. The QA Plan shall identify the contractor’s QA Manager, the person responsible for implementing the contractor’s QA Plan. Any contractor person who has been given full authority by the contractor to accept and reject work quality may perform the duties of the QA manager. This includes his/her project manager or superintendent. A full time QA Manager is not necessary to satisfy this requirement, however should the contractor deem it necessary for the satisfactory performance of this work, the cost for a full time QA Manager must be included in the initial bid/price proposal.
C. The QA Plan shall specify types and quantities of inspections, photos (as required to document the quality of all items and especially that of those to be covered or hidden in the construction, such as underground utilities, cabling/piping within walls, etc.), acceptance and rejection criteria, and other items deemed necessary by the contractor to validate an acceptable level of quality materials and workmanship. “Close-in” inspections are to be performed by the contractor’s QA manager, documented with photographs and included in the monthly QA Report. The QA Plan shall include a sample monthly status/result report (Monthly QA Report).
D. The Monthly QA Report shall be submitted with all progress payment applications. No progress payments will be authorized for release to the contractor without this monthly update (among other required documents).
1.34 PROGRESS PAYMENTS & RETAINAGE: (N/A)
1.35 CONSTRUCTION PROGRESS MEETINGS: (N/A)
1.36 REQUESTS FOR INFORMATION, SUBMITTAL AND PROPOSED CHANGE LOGS: (N/A)
1.37 BOND, OVERHEAD (OH) AND PROFIT CALCULATIONS ON MODIFICATIONS: (N/A)
1.38 CHANGE PROPOSAL SUPPORT DOCUMENTATION: (N/A)
1.39 FEDERAL AVIATION ADMINISTRATION NOTIFICATION FORM: (N/A)
RADIOACTIVE MATERIALS: Radioactive materials (RAM) permitted by the Nuclear Regulatory Commission are not permitted on Air Force installations without prior approval from the base Radiation Safety Officer (RSO). The contractor must contact the base RSO at (609) 754-9057 if they have any RAM they wish to bring on base
CONSTRUCTION CHECKLIST INSTRUCTIONS
1. Complete the checklist as thoroughly as possible and deliver to the Government no later than the Pre-Final Acceptance Inspection.
2. Provide the following information with the checklist.
a. REMARKS OR SCOPE OF WORK SHEET (explain the work actually performed, please be precise):
EXAMPLE:
PROJECT NO.: PTFL XX-XXXX
DELIVERY ORDER NO.
TITLE:
FACILITY NO.:
SCOPE OF WORK:
This project provides for the replacement or new construction of ______ linear feet of domestic water pipe underground and replacement of all associated hardware as per Delivery Order Number CLIN items, i.e. fire hydrants, thrust blocks, gate valves, fittings, saddles, excavations, and lateral connections.
The new line will be installed using pipe bursting methods and some excavation or complete excavation for smaller lateral lines.
Bypass piping systems (are/are not) requested for the shutdown of the section to be replaced.
Demolition costs (have/have not) been requested for asbestos.
Piping system to be replaced affects ____#____ buildings.
Provisions for Domestic Water (have been/ have not been) requested.
Repair/Replacement Cost: ___________ New Construction Cost: __________
b. REAL PROPERTY INSTALLED EQUIPMENT (RPIE) LISTING (the itemized RPIE listing must include material type of pipe and valves to be installed, manufacturer, any other pertinent data, price per unit and total cost for each item listed)
c. LETTER OF FINAL INSPECTION (Include date of final inspection and list of attendees)
d. LIST OF DISCREPANCIES
e. SHOP DRAWINGS IF CLIN REQUESTED OF THE PIPELINE WITH LENGTH AND ELEVATION AND LOCATION DIMENSIONS (Attach shop drawings of new pipe showing position of laterals and isolation valves and elevations)
f. COMPLETE “STATEMENT OF CONDITION” (To be completed by the Government)
3. Return completed checklist to the COTR.
LOCAL CONSTRUCTION CHECKLIST (pg 1)
DELIVERY WORK ORDER NO.: ________________ BUILDING AREA GENERAL NO.: __________
CONTRACT NO.: ___________________________ DATE CONSTR COMPLETED: _____________
PROJECT TITLE: ___________________________ BLDG CATEGORY CODE: N/A__________
TOTAL COST: _____________________________ DEMOLITION COSTS: ___________________
TYPE FUNDS (MCP, MC, O&M): _____________ TYPE WORK (REPLACEMENT/REPAIR/NEW): ___
PROJECT NO.: ________________________
1. GENERAL DATA REQUIRED FOR NEW UTILITIES:
a. OUTSIDE DIMENSIONS Length Diameter
(1) Main pipe route ______ ft ______ Inches_______________
(2) Secondary pipe route ______ ft ______ Inches_______________
(3) Secondary pipe route ______ ft ______ Inches_______________
(4) Secondary pipe route ______ ft ______ Inches_______________ Diameter Flanged Threaded Welded
(5) Valve ______inches_____ ______ ______
b. CONSTRUCTION:
(1) Foundations (such as concrete) TYPE _(anchor/pipe support/thrust block)_
c. UTILITIES INVOLVED
(1) Water (size of pipe) ____________________________
(2) Gas (size of pipe) ____________________________
(3) Sewer (size of pipe) ____________________________
(4) Electric (phase, voltage, wire, connected load) _(streetlights/supply runs)______
d. MISCELLANEOUS: (bypass domestic water pump)_____________________________
(pg. 2)
e. RELATED FACILITIES:
CATEGORY UNIT OF TOTAL COST
| CODE NOMENCLATURE MEASURE AMOUNT (MATERIAL & LABOR) 812-223 | PRIM DISTR LINE OH | LF | ________ | $ ________ |
| TRANSFORMS | KVA | ________ | $ ________ | |
| POWER POLES | EA | ________ | $ ________ | |
| 812-224 | SEC DISTR LINE OH | LF | ________ | $ ________ |
| 812-225 | PRIM DISTR LINE UG | LF | ________ | $ ________ |
| 812-226 | SEC DISTR LINE UG | LF | ________ | $ ________ |
| 812-926 | EXTERIOR AREA LIGHTING | EA | ________ | $ ________ |
| 824-464 | GAS MAINS | LF | ________ | $ ________ |
| 831-169 | SEWAGE SEPTIC TANK | KG | ________ | $ ________ |
| 832-266 | SANITARY SEWAGE MAIN | LF | ________ | $ ________ |
| 842-245 | WATER DISTR MAINS | LF | ________ | $ ________ |
| 843-315 | FIRE HYDRANTS | EA | ________ | $ ________ |
| 851-143 | CURBS & GUTTERS | LF | ________ | $ ________ |
| 851-145 | DRIVEWAY | SY | ________ | $ ________ |
| 851-147 | ROAD | SY | ________ | $ ________ |
| LF | ________ | |||
| 852-262 | VEHICLE PARKING, N/ORGN | SY | ________ | $ ________ |
| 852-289 | SIDEWALK | SY | ________ | $ ________ |
| 871-183 | STORM DRAIN DSPL | LF | ________ | $ ________ |
| 872-247 | FENCE, SECURITY | LF | ________ | $ ________ |
| 872-248 | FENCE, INTERIOR | LF | ________ | $ ________ |
| 890-187 | UTILITY VAULT (four or more | |||
| transformers) | SF | _________ | $ _______ | |
| 135-583 | TEL DUCT FACILITY | LF | _________ | $ _______ |
(pg. 3)
2. ALTERATION OR REHABILITATION OF A UTILITY:
| YES | NO | ||
| a. DEMOLITION COSTS. | ___ | ___ |
3. DEMOLITIONS NOT BEING REPLACED – NOT ALL INCLUSIVE: (FILL OUT THIS SECTION IF
REAL PROPERTY IS BEING DISPOSED OF AND NOT BEING REPLACED)
CATEGORY UNIT OF
| CODE | NOMENCLATURE MEASURE AMOUNT REMARKS |
| (Give in the negative) | |
| 852-289 | Sidewalk SY ________ __________________________ |
851-145 Driveway SY ________ ___________________________
812-223 Prim Distr Line OH LF ________ ___________________________
852-261 Veh Pkng, N/Orgn SY ________ ___________________________
(Use additional sheet if you have more than 9 category codes to report)
4.DEMOLITIONS BEING REPLACED – NOT ALL INCLUSIVE: (FILL OUT THIS SECTION IF REAL PROPERTY HAS BEEN DEMOLISHED AND REPLACED)
CATEGORY UNIT OF REPLACED TOTAL COST
CODE NOMENCLATURE MEASURE AMOUNT WITH MATL & LABOR
(positive value) (positive value) 852-289 Sidewalk SY ________ _______ ______________
851-145 Driveway SY ________ _______ _______________
890-121 A/C Plt 5 to 25 TN TN ________ _______ _______________
| (pg. 4) | |
| 5. CERTIFICATION: |
I certify that the above information is accurate and complete to the best of my knowledge and belief.
CONTRACTOR REPRESENTATIVE
COTR
CONCUR: __________________________________________________
CHIEF, CONSTRUCTION MANAGEMENT
6. STATEMENT OF CONDITION:
(FOR GOVERNMENT USE see below for Condition Code Descriptions)
Project has extended the useful life of the facility ______Yes ______No.
Current Condition Code (CC) is ______. Project has upgraded Condition Code to ______.
CHIEF, ENGINEERING FLIGHT
CHECKLIST REVIEWED FOR ACCURACY: _______________________________________REMO
CHIEF
87th SECURITY FORCES SQUADRON (SFS)
APPENDIX TO ALL STATEMENTS OF WORK FOR
JB MDL, NEW JERSEY
INSTALLATION ENTRY CONTROL PROCEDURES FOR ALL CONTRACTORS
The following appendix provides information from Air Force Instruction 31-101 and local supplements on requirements for entering and conducting business while on JB MDL, New Jersey.
1. Contract Award.
1.1. Upon award of a contract, all contractors, including Small Purchase contractors, must initiate a criminal history record information/background check for non-criminal justice purposes on all personnel requiring access to JB MDL to the 87th Security Forces Squadron. This will be completed prior to any access credential for JB MDL being issued to the contractor personnel.
1.2. JB MDL requires all contractors to conduct a criminal history record information/background check WITH fingerprints. This check is done at the contractor's expense and not at government expense.
1.3. This check will require the completed criminal history record/background check results or report be sent by the Investigating Agency to the 87 SFS Entry Screening Facility (ESF).
1.4. All applicants are required to have a criminal history record information/background check for non-criminal justice purposes from BOTH the State of Residence and State of Employment.
| NOTE: | |
| If the applicant lives and works in NJ, then only the NJ check is needed. | |
| If the applicant lives in another state but works in NJ, then a criminal history record information/ background check for non-criminal justice purposes is required from the state the applicant lives in AND the state of NJ. |
1.4.1. General guidance for New Jersey on this process is provided by the NJ State Police and is found in 87 SFS Attachment 1 of this Contractor Security Appendix.
1.4.2. General guidance for Delaware on this process is provided by the DE State Police and is found in 87 SFS Attachment 2 of this Contractor Security Appendix.
1.4.3. General guidance for New York on this process is provided by the NY State Police and is found in 87 SFS Attachment 3 of this Contractor Security Appendix.
1.4.4. General guidance for Pennsylvania on this process is provided by the PA State Police and is found in 87 SFS Attachment 4 of this Contractor Security Appendix.
1.4.5. For guidance from any of the other state or US Territory (i.e. Puerto Rico), contact the state police of that particular state and follow the requirements of para 1.2. and 1.3. above.
1.5. The 87 SFS will not be used to conduct this criminal background check.
1.6. These results must be sent directly from the Investigating Agency to the 87 SFS at the above listed address.