Attachment 2 - PWS_Camp Warlord Fire Notification System Replacement updated 24 September 2024.pdf
PDF 169 KB Posted
- Attached to
- Camp Warlord Fire Alarm
- Solicitation number
- FA446024Q0288
About this file
This document is a Performance Work Statement (PWS) for the furnishing, removal, and installation of a fire notification system at 13 facilities at Camp Warlord on Little Rock Air Force Base, Arkansas. The contractor shall provide all personnel, transportation, tools, equipment, materials, and services required to complete the work within 180 days of contract award. The work must comply with all National Fire Protection Association guidelines, federal, state, and local regulations, codes, and license requirements. The PWS details the specific requirements for the new fire alarm control unit, initiating devices, notification appliances, wiring, and testing. It also outlines the contractor's responsibilities for disposal of waste, safety and regulatory requirements, and warranty. The related federal contract opportunity is for the Camp Warlord Fire Alarm solicitation, which requires interested contractors to submit quotes via email by 4:00 PM CDT on Thursday, September 26, 2024.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
24 September 2024
PERFORMANCE WORK STATEMENT (PWS)
FURNISH, REMOVE AND INSTALL FIRE NOTIFICATION SYSTEM
CAMP WARLORD FACILITIES
1. DISCRIPTION OF SERVICES
1.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, materials and services required to furnish, remove and replace fire notification system in 13 facilities of Camp Warlord on Little Rock AFB, AR 72099. The contractor shall accomplish all services below to meet the requirements of this Performance Work Statement (PWS). Work shall be in compliance with all National Fire Protection Association guidelines, Federal, State and local regulations, codes and license requirements. Work shall be accomplished within 180 days of contract award date.
1.2. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the contractor’s responsibility to notify the Contracting Officer (CO) immediately. These services shall not be used to perform work of a policy/decision making or management nature, (e.g., inherently governmental functions). All decisions relative to programs supported by the contractor shall be the sole responsibility of the Government.
2. SAFETY AND REGULATORY REQUIREMENTS
2.1. Camp Warlord is a training camp. It comprises of 13 facilities, 1401, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414. Building 1401 will hold main fire alarm equipment (panels, etc.) and must communicate to all devices in 13 facilities. Contractor shall coordinate with government representative for access. Work shall be accomplished during the hours of 7am to 4pm, Monday-Friday excluding Federal Holidays. Escort will be provided by the facility user.
2.2. Pre-Install Requirements: Before services are commenced, the contractor shall inspect the work site and ascertain all information for the diligent performance of the service(s). The contractor shall notify the ordering agency of any conditions that prevent the suitable completion of these services to include operations that could endanger Government personnel or property and require appropriate abatement action. If the contractor discovers problems associated with the work after starting, he or she shall immediately notify the Contracting Officer (CO) for their approval if the work is to continue. Coordinate with the Government designated representative to have utilities/fire alarms etc…turned on or off during the competition of the task.
2.3. Disposal of waste: All waste disposals are the responsibility of the contractor to include any fees or permits. Recycling containers may be provided if needed for the operation.
Coordinate through your government representative or Contracting Officer Representative
(COR).
2.4. All work shall be accomplished in accordance with all UFGS 28 31 70, UFC 3-600-01, UFGS 25 05 11 and UFC 4-010-06. Contractor must use newest regulations regarding the installation and repair of fire notification systems.
3. WORK REQUIREMENTS
3.1. Drawings provided by the contractor. The capabilities of the cabins shall be to communicate with the main cabin (Bldg #1401) that shall then transmit to the local fire department in the event of an emergency. This is not a mass notification system. There is no sprinkler system. This project is a basic addressable fire alarm system repair and replacement. All the sleeping facilities must have a combination smoke carbon monoxide detector and a heat detector as part of the installation.
3.1.1. Contractor shall provide drawings according to UFGS 28 31 70. A QFPE is required. No additional personnel are needed except DFPE for final testing. Please use UFGS 28 31 70 for design requirements for fire alarm system.
3.1.2. Contractor shall show single-line fire alarm riser diagram. Each device on riser should be identified by type. Indicate connection of equipment.
3.1.3. This work includes designing and providing a new, complete, basic addressable fire alarm system as described herein and contract drawings. Include system wiring, raceways, pull boxes, control equipment, initiating devices, notification appliances, and other accessories and miscellaneous items required for a complete operational system even though each item is not specifically mentioned or described. Provide systems complete and ready for operation. Design and installation must comply with UFGS 25 05 11, UFC 4-010-06 and AFGM 2019-320-02.
3.2. Contractor must provide all materials, workmanship, installation, inspection, testing and equipment.
3.2.1. Provide all materials, equipment, and devices that have been tested by a nationally recognized testing laboratory and listed for fire protection service. Panel, BT-X Tranceiever, all wiring, detectors, addressable manual pull stations, addressable interface devices, etc. Select material from one manufacturer – FCI/Monaco, where possible, and not a combination of manufacturers, for any classification of materials. Material and equipment must be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid opening. No mass notification equipment needed. Please refer to UFGS 28 31 70.
3.2.2. Contractors must provide all new wiring. Do not reuse existing wire. IAW UFC 3-600-01 Para 9-18.9.4.1, wiring may be solid copper or stranded as permitted by NFPA 70.
3.2.3. Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or equipment. Major components include, but are not limited to, the following:
3.2.3.1. FACU Nameplates must be etched metal or plastic, permanently attached by screws to control units or adjacent walls.
3.2.4. Keys and locks for equipment, control units and devices must be identical. Master all keys and locks to a single key as required by the Installation Fire Department.
3.2.5. Provide a typeset printed or typewritten instruction card mounted behind a glass cover in a stainless-steel frame. Install the instructions on the interior of the FACU. The card must show those steps to be taken by an operator when a signal is received as well as the functional operation of the system under all conditions, normal, alarm, supervisory, and trouble. The instructions and their mounting location must be approved by the Contracting Officer before being posted.
3.3. Fire alarm (FACU) control unit provided by the contractor.
3.3.1. Contractors must provide a complete fire alarm control unit (FACU) according to the
UFGS 28 31 70.
3.3.2. FACU must have a fully enclosed in a lockable steel cabinet as specified herein.
Operations required for testing or for normal care, maintenance, and use of the system must be performed from the front of the enclosure. If more than a single unit is required at a location to form a complete control unit, the unit cabinets must match exactly. The system must be capable of defining any module as an alarm module and report alarm trouble, loss of polling, or as a supervisory module, and reporting supervisory short, supervisory open or loss of polling such as valve supervisory switches, independent smoke detection systems, relays for output function actuation. Refer to UFGS 28 31 70.
3.3.3. Install control unit components in cabinets large enough to accommodate all components and also to allow ample gutter space for interconnection of control units as well as field wiring.
The cabinet must be a sturdy steel housing, complete with back box, hinged steel door with cylinder lock, and mounting provisions. Refer to UFGS 28 31 70.
3.3.4. Program capability via switches in a locked portion of the FACU to bypass the automatic notification appliance circuits features. Operation of this programmed action must indicate on the FACU display as a supervisory or trouble condition. Refer to UFGS 28 31 70.
3.3.5. Provide control units and control units that are fully field programmable for both input and output of control, initiation, notification, supervisory, and trouble functions. The system program configuration must be menu driven. System changes must be password protected. Any proprietary equipment and proprietary software needed by qualified technicians to implement future changes to the fire alarm system must be provided as part of this contract. Refer to UFGS 28 31 70.
3.3.6. Power and supervise each circuit such that a signal from one device does not prevent the receipt of signals from any other device. Initiating devices must be manually reset by switch from the FACU after the initiating device or devices have been restored to normal.
3.3.7. Contractor shall use UFGS 28 31 70 for all equipment and materials that must be provided.
3.4. Installation
3.4.1. Locate the FACU where indicated on the drawings. The FACU must be located in conditioned space. Conductor terminations must be labeled and a drawing containing conductor, their labels, their circuits, and their interconnection must be permanently mounted in the FACU.
Locate the document storage cabinet adjacent to the FACU unless the Contracting Officer directs otherwise.
3.4.2. When batteries will not fit in the FACU, locate battery cabinets below or adjacent to the FACU. Battery cabinets must be installed at an accessible location when standing at floor level.
Installing batteries above drop ceilings or in inaccessible locations is prohibited. Refer to UFGS 28 31 70.
3.4.3. Locate manual stations as required by NFPA 72 and install. Mount stations according to
UFGS 28 31 70.
3.4.4. Locate smoke and heat detectors. Remove existing detectors. Install combination smoke carbon monoxide detectors and heat detectors in sleeping facilities. Install one smoke detector above new fire alarm panel unit. Combination Smoke/Carbon Monoxide detectors are permitted.
Please also note, due to the combustible construction in the attic, heat detectors are required in that space. There are existing heat detectors in place currently.
3.4.5. Contractor must install visual notification appliances. LED Exit Signs, Strobes, etc. Please refer to UFGS 28 31 70.
3.4.6. Provide ceiling bridges for ceiling-mounted appliances and tiles where needed. Ceiling bridges must be as recommended/required by the manufacturer of the ceiling-mounted notification appliance. Replace damaged ceiling tiles if needed. If no ceiling tiles, patch and paint. Match paint with current paint. Must be a smooth finish.
3.4.7. No blank covers. Patch and paint all holes and removal of devices. Match paint with current paint. Must be a smooth finish unless it’s a popcorn ceiling.
3.4.8. In unfinished areas (including areas above drop ceilings), paint all exposed electrical conduit (serving fire alarm equipment), fire alarm conduit, surface metal raceway, junction boxes and covers red. In finished areas, paint exposed electrical conduit (serving fire alarm equipment), fire alarm conduit, surface metal raceways, junction boxes, and electrical boxes to match adjacent finishes. Refer to UFGS 28 31 70.
3.4.9. Provide wiring that is installed in a neat and workman like manner and installed parallel with or at right angles to the sides and back of any box, enclosure, or cabinet. Protect all fire wall and smoke wall penetrations with a UL approved system. Conductors that are terminated, spliced, or otherwise interrupted in any enclosure, cabinet, mounting, or junction box must be connected to screw-type terminal blocks. Mark each terminal in accordance with the wiring diagrams of the system. The use of wire nuts or similar devices is prohibited. Wiring to conform with NFPA 70. Refer to UFGS 28 31 70.
3.5. Disconnection and removal of existing system.
3.5.1. As new equipment is installed, label it "NOT IN SERVICE" until the new equipment is accepted. Once the new system is completed, tested, and accepted by the Government, it must be placed in service and connected to the supervising station. Remove tags from new equipment and tag the existing equipment "NOT IN SERVICE" until removed from the building. No decommissioned equipment is permitted to be abandoned in place.
3.5.2. Salvage BT-X and return to the LRAFB.
3.5.3. Contractor shall use UFGS 28 31 70 for all disconnection and removal of existing system instructions.
3.6. Pre-Government Testing
3.6.1. Conduct inspections and tests to ensure that devices and circuits are functioning properly.
Tests must meet the requirements of paragraph entitled "Minimum System Tests" as required by NFPA 72. The contractor and an authorized representative from each supplier of equipment must be in attendance at the pre-Government testing to make necessary adjustments. After inspection and testing is complete, provide a signed Verification of Compliant Installation letter by the QFPE that the installation is complete, compliant with the specification and fully operable. The letter must include the names and titles of the witnesses to the pre-Government tests. Provide all completion documentation as required by NFPA 72 including all referenced annex sections and the test reports.
3.6.2. When the verification of compliant installation has been completed, submit a formal request for Government final test to the Contracting Officer's Representative (COR).
Government final testing will not be scheduled until the DFPE has received copies of the request for Government final testing and Verification of Compliant Installation letter with all required reports. Government final testing will not be performed until after the connections to the installation-wide fire reporting system and tested to confirm communications are fully functional. Submit request for test at least 15 calendar days prior to the requested test date.
3.6.3. If equipment worked on was found to be defective or non-compliant with contract requirements, perform corrective actions and repeat the tests. Tests must be conducted and repeated, if necessary, until the system has been demonstrated to comply with all contract requirements.
3.6.4. The tests must be performed in accordance with the approved test procedures in the presence of the DFPE. Furnish instruments and personnel required for the tests.
3.6.5. Contractor shall use UFGS 28 31 70 for all final testing requirements. REFER TO APPENDIX
4. GOVERNMENT FURNISHED EQUIPMENT
4.1. None
5. GENERAL REQUIREMENTS
5.1. Contractor personnel and vehicles must possess appropriate passes. These shall be obtained from Installation Security Forces Pass and ID at the Vehicle Inspection Center.
5.2. The Contractor is subject to all installation fire, safety, security, and traffic regulations.
5.3. The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
5.4. The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. Enforcement of workplace safety laws is the responsibility of the agency specified in the applicable law.
5.5. The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
5.6. Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the designated representative, must be corrected immediately.
5.7. Contractor Employees: While on the installation, the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the organization or by wearing appropriate badges containing the organization's name and the employee's name. Contractor personnel must wear issued base identification cards at all times while on the installation.
5.8. Service contracts shall require contractor employees to identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with government personnel. In addition, contracts shall require contractor personnel to appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
6.0. WARRANTY
6.1. Contractor shall guarantee all material, workmanship and labor from defects for a period of 12 months from the date of acceptance of the work. A warranty letter detailing the work accomplished per facility is required to be furnished to the government representative upon acceptance of the work.
7.0. APPENDIXES
Appendix A: Location Map of the Facilities.
Appendix B: Commander’s Environmental Policy Appendix C: UFGS 28 31 70 Appendix D: UFGS 25 05 11 Appendix E: UFC 4 010 06 Appendix F: UFC 3 600 01 Appendix G: AutoCAD Dwgs for 1401 and Huts