This document is a Site Visit Questions and Answers record that clarifies key operational details for a facility-related project. KTR is designated as responsible for moving furniture rather than government personnel. An escort will be required only on the first day of work, after which contractor personnel may operate independently at the site. Work scope in Building 430 is limited to the doorway threshold, with the closet interior explicitly excluded from the contract requirements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site visit Q’s:
1. Will we move the furniture or will the government?
a. KTR is to move furniture.
2. Will there need to be an escort every day?
a. Only the first day.
3. Will the closet in building 430 need to be done?
a. No stop at the door.