This is a Statement of Work for construction services to modernize the kitchen in Building 753 at Fort Bragg, North Carolina. The project number is P2-00101-26, prepared by the 43d AMOG Business Office with a document status date of 09JUL2026. The contractor must complete all physical work within 30 calendar days and furnish all architecture and engineering services, labor, material, equipment, incidentals, supervision, and transportation. Work must comply with UFC 1-200-01, UFC 1-200-02, and applicable Federal, Department of Army, State of North Carolina, and Fort Bragg construction safety and environmental protection standards, including ASHRAE, ASTM, DOD, and EPA regulations.
The scope includes comprehensive kitchen renovation consisting of demolition and construction tasks: removal of existing cabinetry and countertops; replacement of ceiling tiles with beveled tiles; wall repair and painting in uniform color; epoxy floor preparation and refinish with polyaspartic topcoat; installation of cove base, wall-mounted and base cabinets, non-porous countertops, and major appliances including a refrigerator (minimum 21 cubic feet, French door style), electric range with air fryer and convection functions, over-the-range microwave with ventilation, and dishwasher (quieter than 42 dB). Electrical work includes 120V outlet installation, LED panel replacement for fluorescent lights, and outlet/switch replacement per National Electric Code. Plumbing work requires sink and faucet replacement, instant water heater installation, water filter, garbage disposal installation, refrigerator waterline, and dishwasher installation. Mechanical work includes ductwork installation for range ventilation to exterior. Contractor must provide occupancy during construction, implement a Quality Control System, and submit specific materials for approval including furniture proposals, SVTC compatibility documentation, electrical changes, cabling routes, and equipment certifications for classified areas. Monthly anticipated adverse weather delays are included in the Performance Period. Deliverables include as-built drawings, work schedule, status reports, and meeting minutes. Contractor must provide one year warranty on all materials and workmanship. Work hours are 0730-1600, Monday through Friday, with prior approval required for weekend or holiday work.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Project Location: Building 753, 3541Surveyor St. Ft. Bragg, North Carolina
Contract Type: Construction
Project Description: Modernization of kitchen in Building 753
Project Number: P2-00101-26
Document Status: 09JUL2026
Prepared By: 43d AMOG, Business Office
P2-00101-26 Modernization of kitchen in 753
STATEMENT OF WORK
9JUL 2026
NOTE: ONLY CHECKED BOXES APPLY
Request for Construction Services: P2-00101-26 Modernization of Kitchen in B753
1. Description of Work: The contractor will furnish all Architecture and Engineering services, labor, material, equipment, incidentals, supervision, and transportation for work necessary to complete the modernization of the kitchen in building 753. All physical work shall be completed in 30 calendar days. All work shall be performed in accordance with the contract specifications, manufacturer’s recommendations, and UFC 1-200-01 and UFC 1-200-02.
Work performed under this task order shall comply with the latest edition of all required publications, Federal, Department of the Army, State of North Carolina, and Fort Bragg construction safety and environmental protection laws, regulations, rules, and codes (i.e.
American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE), ASTM International (ASTM), U.S. Department of Defense (DOD), U.S. Environmental Protection Agency (EPA), etc.) and the Fort Bragg Installation Design Guide (IDG), dated at the time of the task order award. When a required publication is not specifically referenced in the contract, the contractor shall utilize one that has national applications. Where conflicts arise between publications, the most stringent requirements shall apply.
2. AT/OPSEC Requirements: See AT OPSEC Cover sheet
Access, General Protection, and Security Policy and Procedures.
Contractor and all associated subcontractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or individual facility change, the Government may require changes in contractor security matters or processes.
iWATCH Training.
The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Anti-terrorism Officer). This local developed training will be used to inform employees of the types of behavior to watch and instruct employees to report suspicious activity to the Contract Officer Representative. This training shall be completed within 5 calendar days of the contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 15 calendar days after contract award. This information is available at the following website: https://www.youtube.com/watch?v=vlzYhQp7fPw https://www.youtube.com/watch?v=vlzYhQp7fPw
For Eligibility Verification for Employment
E-Verify is an Internet-based system that compares information from an employee's Form I- 9, Employment Eligibility Verification, to data from U.S. Department of Homeland Security and Social Security Administration records to confirm employment eligibility. The U.S.
Department of Homeland Security is working to stop unauthorized employment. By using E- Verify to determine the employment eligibility of their employees, companies become part of the solution in addressing this problem. All U.S. employers must complete and retain a Form I-9 for everyone they hire for employment in the United States. This includes citizens and noncitizens. On the form, the employer must examine the employment eligibility and identity document(s) an employee presents to determine whether the document(s) reasonably appears to be genuine and relates to the individual and record the document information on Form I-9.
The list of acceptable documents can be found on the last page of the form. E-Verify is mandatory for employers with federal contracts or subcontracts that contain the Federal Acquisition Regulation E-Verify clause.
3. Monthly Anticipated Adverse Weather Delay: Workdays Based on 5-Day Work Week.
These days are included in the POP.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10 9 6 4 4 6 8 7 4 4 5 9
4. Interface with Government Personnel: Access to and from the site shall be coordinated through 43 OSS. Contractor will coordinate work schedule with designated 43d AMOG COR/inspector.
5. Contractor Requirements:
A. Occupancy During Construction
B. Quality Control System (QCS) Required
G. Submittals are required in the following materials.
All Other Materials For Information Only (FIO) Approval The following submittals required for GA Approval:
• Command and Control furniture proposals based on layout and equipment requirements
• Existing and New SVTC life cycle, compatibility with existing equipment
• Raised floor repair
• Electrical changes
• SIPR/NIPR fiber and ethernet cabling routes and compatibility
• Microphone and Camera / system approval for classified areas
• LMR Base Station approval for classified areas
7. Scope of Work: This job includes all labor, materials and equipment required for full performance of the work; both explicit work and implied work required to follow the manufactures specification for proper operation of the products. Product colors and material types shall be approved by the COR before installation. Color options and material shall be submitted on USACE ENG Form 4025. The scope of work of this contract includes, but it not limited to the following specific items of work:
a. Construction/Demolition:
A. Contractor shall remove all cabinetry and countertops in the kitchen.
B. Contractor shall replace all ceiling tiles in the kitchen with beveled ceiling tiles C. Contractor shall repair all damage to walls in the kitchen to a uniform defect free surface before painting.
D. Contractor shall paint door frame color to match the cove base in the room. Painting shall be complete to the entry way of the next room E. Contractor shall prime and apply two coats of paint to a uniform color and texture to all walls in the kitchen.
F. Contractor shall Prepare and refinish Epoxy floor.
i. Contractor shall repair all floor defects to one continuous surface in the kitchen.
ii. Contractor shall prepare the floor for epoxy coating IAW manufactures instructions.
iii. Contractor shall apply one uniform base coat of epoxy and one clear topcoat of polyaspartic coating in the kitchen area.
iv. Contractor shall repair all defects to level before applying base coat of epoxy.
v. The contractor shall ensure topcoat does not have visible bubbles, skips, defects, shallow or high spots. The contractor shall ensure topcoat is free of all defects and be completely smooth.
vi. The contractor shall install the epoxy floor before installing cabinetry.
Base color and topcoat will be approved as a submittal.
G. Contractor shall install cove base in the kitchen. Cove base shall be applied to all wall locations where cabinetry is not present.
H. Contractor shall install wall mounted over the counter cabinets. Cabinets shall have standard clearance to base cabinets and extend to ceiling tiles. Any location there is a gap between the ceiling tile and the cabinets, valence trim will be applied to top of cabinets.
I. Contractor shall install base cabinets in the kitchen. Cabinets shall be uniform in style with a uniform stain. Cabinets shall not contain oriented strand board (OSB), Particle board, or other laminate wood or plastics. Any plywood used must be veneer finished and minimum of ¾ of an inch thick. Cabinets shall have all hardware affixed at completion.
J. Contractor shall install countertops. Countertops will be uniform and solid color throughout material. Material shall be non-porous.
K. Contractor shall install a refrigerator unit in the kitchen. Refrigerator shall be no less than 21 cubic feet for interior size, French door style access, water filtration, water and ice in the door. Fridge shall have a freezer on the bottom.
L. Contractor shall install free standing range with oven in the kitchen. Stove shall be an electric stove; have no less than four positions for pans, be uniform top with no grills, grates and have an oven below. Oven shall be electric. Oven shall have secondary functions of air fryer, convection oven.
M. Contractor shall install microwave in the kitchen. Over the range microwave shall be installed with ventilation to outside wall. Range shall be standard size width ventilation, lights and filters. Touch controls shall include a number pad. Microwave shall have secondary functions of Defrost, Convection, and Air Fry.
N. Contractor shall install dishwasher. Dishwasher shall be quieter than 42 dB when in operation and capacity of 8 place settings. Color shall match installed hardware and other appliances; customer shall approve before purchase.
b. Electrical:
A. Contractor shall install 120 V outlet to support over the range ventilation and microwave oven
B. Contractor shall ensure outlets are spaced down the wall in compliance with the National Electric Code (NEC).
C. Contractor shall replace all fluorescent lights with 2’x4’ LED panel IAW Fort Bragg requirements.
D. Contractor shall replace light switches, outlets and faceplates in the space. Light switches shall be compatible with LED lights. All switches, outlets and faceplates shall be same color approved by customers.
f. Contractor shall install ventilation over the range.
c. Plumbing A. Contractor shall demolish sink. Sink, faucet, and garbage disposal and all hardware shall be removed and disposed of in construction waste.
B. Contractor shall replace sink and faucet C. Contractor shall install instant water heater D. Contractor shall install water filter with hot and cold water at the sink.
E. Contractor shall install garbage disposal. Disposal shall be quiet rated with a minimum of ½ horsepower rating F. Contractor shall install waterline to the refrigerator.
Contractor shall install dishwasher in proximity to sink.
d. Mechanical
A. Install duct work for over range ventilation to nearest wall.
i. Install wall transition and grate over the exterior vent.
B. Install “over the range” ventilation.
i. Vent and ductwork must vent to exterior of building
ii. Vent must have vent control closure on the exterior of the building
e. General
A. The government referenced details indicate the general extent of the work. The references are not intended to indicate or describe all work required for the full performance and completion of the requirements of the job.
B. The contractor will procure all equipment and necessary items to complete the installation of all equipment needed to meet the design they have engineered. The contractor must also perform operational checks on all equipment installed. All cables shall be routed with a structured and orderly manner as well as secured within support hardware i.e. J-hooks and Cable trays. All calculating must be approved by 43 CS SCOI, 43 CS SCOS-S, Ft Bragg NEC and USAF TEMPEST regulations.
C. The contractor shall comply with all base installation standards, manufacturers specifications, as well as all commercial codes and standards. The contractor shall be familiar with appropriate Commercial/Military/Local Installation Standards.
Installation tasks shall be performed in accordance with the appropriate installation standards and practices.
8. ADDITIONAL ENCLOSURES: It is the responsibility of the contractor to ensure they are in receipt of and have reviewed all appendices prior to the award.
A. SOW Appendix A – Record Drawings B. SOW Appendix B – Pictures of kitchen C. SOW Appendix C – AT OPSEC Cover sheet
9. DELIVERABLES: ALL deliverables are subject to Government acceptance and approval. They shall meet professional standards, and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables
DATA ITEM TITLE
AS BUILT
WORK SCHEDULE
STATUS REPORT
MEETING MINUTES
10. CYBERSECURITY: Conform to UFC 4-10-06 Cybersecurity of Facility-Related Control System
11. INSPECTION AND ACCEPTANCE: Upon completion of work a Project Manager from the Communications Squadron and a Ft Bragg VTC Team representative, and the NEC will inspect the area prior to government acceptance.
a. The contractor will provide in-person training on the operation of the installed system and a one-each simple operational guide pamphlet/instructions
12. DUST BARRIERS: Contractor provide adequate dust barrier in construction areas to prevent dust and debris exposure to computer and work areas. Special care is to be taken to prevent dust exposure to server and data storage equipment areas.
13. DISPOSAL OF WASTE: Loose debris on trucks leaving the site shall be loaded in a manner that shall prevent losing or dropping of materials on streets and conform to local ordinances / laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets.
The Contractor shall be responsible for cleaning up any materials that fall from trucks and held liable for any resulting damages. The Contractor is solely responsible for spillage from its vehicles, and such spillage shall be cleaned up immediately. The Contractor shall report all spills to the Fort Bragg Fire Department 910.432.0911 or 911. For the duration of this contract and on a daily basis, the Contractor shall remove from all roads and / or streets asphalt, mud, soil, rocks, trash, and debris that result from its operations. All roads and / or streets affected shall be cleaned before the close of business on the day affected. Contractor is also responsible for restoring the site/grounds back to its original condition. Grass/soil must be restored to its original condition.
• The contractor shall submit all trip tickets from the off-post landfill facility to the
COR/ACOR within three working days to show all debris is being land-filled in accordance with all Federal requirements and in an approved location.
• The Contracting Officer (KO) will determine if materials removed from and not reused in the project are salvageable or unsalvageable. Salvageable materials shall be disposed of as directed by the KO. When material is designated as unsalvageable, the material from that point shall become the property of the Contractor.
• The Fort Bragg Lamont Construction and Demolition (C&D) Landfill is closed and does not accept any C&D Waste or Asbestos Waste. The Municipal Solid Waste (MSW) Transfer Station at the Lamont Landfill Facility is closed and is not accepting MSW at the facility.
• All contractors shall use a State Certified C&D Landfill or Subtitle “D” Landfill outside
Department of Defense land for the disposal of C&D waste, asbestos waste, and MSW.
The contractor shall maintain data of all waste disposed (C&D and MSW) and all materials recycled in execution of a Contract. The Department of the Army (DA) and the North Carolina Department of Environmental Quality (NCDEQ) require monthly and annual reporting of all materials (waste and recyclables) managed by Fort Bragg. The Fort Bragg Environmental Compliance Branch, Solid Waste/Recycling Office is responsible for compiling data into monthly Directorate Reports to be consolidated into reports for DA and NCDEQ. A form from the Solid Waste/Recycling Office or a Contractor form shall be completed by the Contractor with the type of waste or recycled material, the weight of the waste/material (tons or pounds), and the certified facility accepting the waste/material. This information shall be submitted to Fort Bragg Solid Waste/Recycling Office no later than the second Friday of each month. Information can be submitted in person or by fax (910.396.4188). Phone number is 910-396-3372.
• All recyclable materials generated during execution are Government property unless the contract specifies that the Contractor can obtain the materials. State Law and Fort Bragg regulations require covering of loads of waste or recyclables to prevent litter. All waste and recyclable material loads are subject to be inspected of their contents while on Department of Defense land. The Lamont Landfill Facility Recycling Area will accept specific recyclable items as indicated below.
• Concrete, Brick, Block and Asphalt: tested and free of asbestos and lead based paint to be recycled; no larger than 2 feet by 2 feet pieces or equivalent; minimal amount of dirt in load; no rebar protruding out of the concrete.
• Steel and Aluminum: no items requiring demilitarization; no items containing or coated with liquid.
• Cardboard: clean of trash, plastic, Styrofoam, wood, metal, etc.; 40 cubic yard dumpsters available for material; alternate acceptance location at Fort Bragg Recycling Center (Building 3-1240, DPW Compound at Butner Road / Reilly Road intersection).
14. SALVAGE: All materials and equipment to be demolished, except recyclable items and items indicated in as Government salvage shall be vested to the Contractor upon removal from the Department of Defense land. The Government shall not be responsible for the condition, loss, or damage to such materials and equipment after NTP. All unsalvageable material shall be disposed of legally outside the Department of Defense land. Projects which include Government salvage will have such items clearly designated in the scope. Government salvage materials shall be cleaned, sorted, identified, bundled, boxed, etc. and delivered to the collection location identified.
15. AVAILABILITY AND USE OF UTILITY SERVICES: Utility services are available on site (power and water) for the accomplishment of the work required. Any additional utility services will be furnished at an additional cost to the Contractor.
The Government will make no connections or alterations to the existing utility systems for the Contractor. Utilities for offices and/or storage buildings or areas will be billed to the Contractor monthly and will not be furnished free of charge. The Contractor shall be responsible for installing meters or other connections at no cost to the Government. At the conclusion of the contract, the Contractor shall remove all temporary connections, distribution lines, meters and associated paraphernalia unless otherwise notified by the COR. Prior to installing any utility connections at an office/storage site, the plan will be approved by the COR. When utility meters are installed, the Contractor shall notify the COR for the initial meter reading. Failure to obtain this initial reading will result in the Contractor being charged for the entire amount shown on the meter.
16. CONTRACTOR STORAGE AND TRAILERS: The Contractor shall place or paint a sign on all storage trailer(s) and building(s) used in this contract. At a minimum, the sign shall contain the name of the Contractor and a telephone number at which the contractor can be reached. The trailer(s) and building(s) shall be completed with gates and/or doors which can be locked. Only material for this project shall be stored in the trailer(s) or building(s). The Contractor shall remove the storage trailer(s) or building(s) within 30 days after completion of the contract and prior to submitting his final invoice. The area around the storage trailer(s) and building(s) shall be kept clean.
17. SAFETY: Safety will follow the Corps of Engineers Safety Manual EM 385-1-1. Use of appropriate safety equipment is mandatory and not limited to hard hats and steel-toed shoes. The contractor is responsible for daily cleaning up and complete restoration of the area once the contract is complete. Additional safety references to be followed include:
b. 29 CFR 1910, OSHA General Industry Standard
c. 29 CFR 1926, OSHA Interim Construction Standard
d. DA Pamphlet 385-10, The Army Safety Program
e. Fort Bragg Regulation 385-10, Fort Bragg Safety Program
18. CONTRACTOR’S PERSONNEL
• Contractor personnel performing work under this contract shall be U.S. citizens unless the provisions of Army Regulation 25-2, Information Assurance have been fully completed, and approval has been granted by the Government for the non-U.S. citizen to perform the required support.
• Contractor personnel performing work under this contract shall be able to read, write, speak, and understand the English language to effectively carry out all contract requirements. They shall have a command of both the written and spoken English language to communicate in person properly, clearly, and effectively or via electronic devices (telephone or Email) with co-workers, customers, and the general public.
• Contractor personnel must act as guests on the installation, which they are. Employees are expected to be always on the job site. In the event a contractor employee’s conduct is unsatisfactory, the foreman/supervisor is expected to handle the situation accordingly and in a timely manner.
19. HOURS OF WORK: Work shall be accomplished between the hours of 0730- 16:00, Monday through Friday. No work will be done on weekends or on federal holidays without prior approval from the Contracting Officer. Legal holidays falling on Saturday are observed on the proceeding Friday and those falling on Sunday are observed on the following Monday. Work schedule and facility security to be coordinated with the Contracting Officer Representative (COR) or Quality Assurance (QA) personnel for facility access and security maintenance during duration of work.
Contractors shall not work outside of the stated hours of work, without first obtaining approval from the COR or QA personnel.
20. WARRANTY: The contractor shall provide a minimum of one (1) year warranty on all materials and workmanship from the date of the Government’s acceptance of the work.
a. The warranty will cover all newly installed equipment and cabling, technical support for any issues regarding the equipment as well as provide technical support to keep the equipment updated with current firmware and software
21. PHOTOGRAPHY: Photography on Fort Bragg is regulated/restricted. All contractors needing to photograph as part of their work must gain approval from the OPSEC officer assigned to supervise the unit.
END OF STATEMENT OF WORK