CONTRACT DATA REQUIREMENTS LIST
(2 Data Items)
PREVIOUS EDITION MAY BE USED.
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ________ TM _______ OTHER _________________________
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
7. DD 250 REQ
8. APP CODE
9. DIST STATEMENT
REQUIRED
10. FREQUENCY
11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft Final
Reg Repro
15. TOTAL
16. REMARKS
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT
14. DISTRIBUTION
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Page ____ of ____ Pages
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Signature of preparer of CDRL.
Item H. Date CDRL was prepared.
Item I. Signature of CDRL approval authority.
Item J. Date CDRL was approved.
Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.
DoDD 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;
Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.
DD FORM 1423-2 (BACK), AUG 96
line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B021 title1: RGATES Installation Plan sub1: N/A auth1: DI-MISC-80508 ref1: PWS para 1.3.1, 1.3.4, Fig. 2, 1.3.8 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 9: B - Administrative or Operational (13 Jul 2011) (COR)
Blk 10, 12, and 13: Required 10 working days prior to each version release and with daily status updates during the installations.
RGATES Installation Plan shall at a minimum include the events/installation schedule (with site POC), site preparation procedures, installation procedures (including corrective actions if a problem arises), coordination plan (detailing how functional and site communications will be done and what outages are required), installation checklist, and notification plan (advertising that the installation is happening, who the POCs are, explaining the sequencing as to when, where, and how installs will be performed.)
group1: NSP totalprice1:
data_item2: B022 title2: What's New Document sub2: N/A auth2: DI-MISC-80508 & Appendix 4.3 ref2: PWS para 1.3.1, 1.3.4, Fig. 2, 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 9: B - Administrative or Operational (13 Jul 2011) (COR)
Blk 10, 12, and 13: Required five working days prior to version release. See Appendix 4.3 for example.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:22:25-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:51:08-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 15 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B023 title1: Test Readiness Review Report sub1: N/A auth1: DI-MISC-80761 ref1: PWS para. 1.3.1, 1.3.4, Fig. 2, 1.3.8 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 4: Para. 10-1 Media, first sentence deleted.
Blk 9: B - Administrative or Operational (13 Jul 2011) (COR)
Blk 10, 12, and 13: Due five working days prior to software delivery.
group1: NSP totalprice1:
data_item2: B024 title2: Software Requirements Specification sub2: N/A auth2: DI- IPSC-81433 ref2: PWS para. 1.3.1, 1.3.4, and 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 9: - Critical Technology (13 Jul 2011)
Blk 10, 12, and 13: Due 30 days prior to scheduled release delivery. Due as soon as possible prior to software release, but not to exceed 30 days prior, for unscheduled releases.
Response - Standard group2: NSP totalprice2:
prep_by:
2011-08-03T15:22:50-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:51:23-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 16 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: A001 title1: Technical & Management Work Plan sub1: N/A auth1: DI-MGMT-81117 ref1: PWS para 1.3.1 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1: Y dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: CO (w/ Proposal) draft1_1: 1 reg1_1:
repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 1 totalreg1: 0 totalrepro1: 0 rmks1: Blk 4: Tailor para 10.2.4 to read "– Personnel. The plan shall identify the number of people by function and contractor defined labor categories. Each labor category shall include a brief job description to include education, training, experience, and skill levels required to accomplish the task order. The plan shall show how the combination of resources assigned to each task provides a sufficient knowledge or experience base for function needed to perform the task."
BLK 9: Distribution Code B - Contractor Performance Evaluation
Blk 10,12, and 13: Draft due with proposal. Final due 15 working days after award and 10 working days after each modification.
group1: NSP totalprice1:
data_item2: A002 title2: Contract Performance Report (CPR) sub2: N/A auth2: DI-MGMT-81466A ref2: PWS para 1.3.1 and 1.3.4 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: BLK 9: Distribution Code B - Contractor Performance Evaluation
Blk 10, 12, and 13: Due the 3rd Friday of Contractor's fiscal month.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:03:03-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 11 app_by:
2012-02-29T15:46:48-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 1 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B025 title1: Technical Report – Impact Analysis Worksheets sub1: N/A auth1: See Blk 16 ref1: PWS para 1.3.1 and 1.3.4 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 4, 10, 12, and 13: Due 10 working days following direction from the government to perform.
Review - Standard Response - Standard Blk 9: B - Administrative or Operational Use (13 Jul 2011) (COR) group1: NSP totalprice1:
data_item2: B026 title2: Handheld Terminal Handbook sub2: N/A auth2: See Blk 16 ref2: PWS para 1.3.1, 1.3.2, 1.3.4, 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 4, 10, 12 and 13:
Draft due 30 days prior to version release or AIT hardware install/change. Final due in conjunction with scheduled and unscheduled software release delivery or initial AIT hardware fielding.
Blk 9 B: Administrative or Operational Use (13 Jul 2011) (COR) group2: NSP totalprice2:
prep_by:
2011-08-03T15:24:08-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:51:38-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 17 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat: X system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B027 title1: Document Problem Report sub1: N/A auth1: See Blk 16 ref1: PWS para 1.3.1 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 4, 10, 12, and 13:
Due in conjunction with any administrative changes to documents controlled through CM.
Blk 9: Administrative & Operational Use (13 Jul 2011) (COR) group1: NSP totalprice1:
data_item2: C001 title2: Training Conduct Support Document (TCSD)/Training Lesson (TL) sub2: N/A auth2: DI-SESS-81523B ref2: PWS para 1.3.1 and 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 4: DI-SESS-81523B, with the following deletions: paras 2.2.2.ae. With government approval, the contractor may deviate (add and delete) from the TCSD/TL DID content requirements in order to further tailor the TCSD/TL to the Missions Systems training culture and the contractor’s training strategy. However, the contractor must explain in an executive summary or an addendum to the TCSD/TL its rationale for adding or deleting a specific DID requirement. Nevertheless, the government retains the right to require any part of or all of the Data Item Instructions to be adhered to by the contractor.
Blk 9: B - Administrative or Operational Use (13 Jul 2011) (COR) Blk 10, 12, and 13:
Draft due 30 days prior to version release delivery. Final due 30 days prior to fielding of the release. Each version release and some patches may require a TL. Outline TL due 30 days prior to each planned version release. Final TL due 30 days prior to version fielding.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:25:34-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:51:57-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 18 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat: X system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: A004 title1: Agenda/Minutes sub1: N/A auth1: DI-ADMN-81249A / DI-ADMN-81250A ref1: PWS para 1.3.1 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1: N/A dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 4: Agenda IAW DI-ADMN-81249A Minutes IAW DI-ADMN-81250A
Blk 9: B - Proprietary Information (Determination Date: Based on document content) (COR)
Blk 10, 12, and 13: Agendas due two working days prior to meeting. Minutes due five working days after meeting.
group1: NSP totalprice1:
data_item2: A005 title2: Integrated Master Schedule sub2: N/A auth2: DI-MGMT-81650 / Project Professional ref2: PWS para 1.3.1 and 1.3.4 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: Weekly asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 9: C - Administrative or Operational Use (July 12, 2011)
Blk 12: Initial input due 30 days after contract start.
Blk 13: Subsequent input due weekly.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:03:43-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:47:49-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 2 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat: X system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: A006 title1: Management Plan sub1: N/A auth1: DI-MGMT-80004A ref1: PWS para 1.3.1 and 1.4.14 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 4: Tailor DI-MGMT-80004A by deleting para 3.7
Blk 9: B (Proprietary Information) (12 Jul 2011) (COR)
Blk 10, 12, and 13: Phase-in plan due with proposal. Phase-out plan due six months prior to end of contract.
group1: NSP totalprice1:
data_item2: A007 title2: Equipment Inventory Records (EIR) sub2: N/A auth2: DI- ILSS-81251 ref2: PWS para 1.3.1, 1.3.6, and 1.4.14 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 4: Use AFI 33-112 as a guide. DI-ILSS-81251 is modified by replacing "computer tapes" in Para. 10.2.2 with "standalone computer storage media" Blk 9: B (Administrative or Operational Use) (12 Jul 2011) (COR) Blk 10, 12, and 13: Initial due seven days after contract start.
-EIR must be updated, at a minimum, every 30 days thereafter.
-Final due five days after contract completion.
-The contractor is only required to deliver the EIR for the initial and final inventories, unless otherwise requested by the government. The initial EIR delivery shall consist of the unalterable government verified initial inventory. The final EIR shall consists of the unalterable government verified inventory and a duplicate in Excel that may be altered by the government.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:07:58-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:48:13-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 3 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: A008 title1: Scientific & Technical Reports sub1: N/A auth1: ANSI/NISO-Z39.18 ref1: See Blk 16 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 5: PWS para 1.3.1, 1.3.3, 1.3.4, 1.3.7, and 1.3.8
Blk 9: B - Critical Technology (12 Jul 2011) (COR)
Blk 10, 12, and 13: Delivery schedule will be negotiated at time of government request for the report(s).
group1: NSP totalprice1:
data_item2: B001 title2: Software Test Report(STR)/Software Test Description sub2: N/A auth2: See Blk 16 ref2: See Blk 16 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 4: DI-NDTI-80809B
DI-IPSC-81439
DI-IPSC-81440
Blk 5: PWS para 1.3.1 1.3.2 1.3.4 Fig. 2 1.3.8 Blk 9: C -Test & Evaluation (12 Jul 2011) Blk 10, 12, and 13: Due in conjunction with scheduled software release delivery.
Review - standard Response - standard group2: NSP totalprice2:
prep_by:
2011-08-03T15:09:09-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug2011 app_by:
2012-02-29T15:48:29-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 4 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Off xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B002 title1: Test Procedures/Cases sub1: N/A auth1: DI-NDTI-80603A ref1: See Blk 16 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 5: PWS para 1.3.1 1.3.2 1.3.4 Fig. 2 1.3.8 Blk 9: C - Test & Evaluation (12 Jul 2011)
Blk 10, 12, and 13: Due 10 days after government acceptance of the Software Development Plan.
group1: NSP totalprice1:
data_item2: B003 title2: Software Development Plan sub2: N/A auth2: DI-IPSC-81427A ref2: PWS para 1.3.1, 1.3.4, and 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2:
freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 10, 12, and 13: Due 10 working days after modification.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:09:34-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:48:47-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 5 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Yes xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B004 title1: Interface Requirements Specification (IRS) sub1: N/A auth1: DI-IPSC-81434A ref1: See Blk 16 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 5: PWS para 1.3.1 1.3.4 Fig. 2 1.3.8 Blk 9: B - Critical Technology (12 Jul 2011) (COR)
Blk 10, 12, and 13: IRS is designated within Interface Design Description (B006). Due in conjunction with supportability design baseline.
group1: NSP totalprice1:
data_item2: B005 title2: Integrated Logistics Support Plan (ILSP) sub2: N/A auth2: DI-ILSS-80095 ref2: PWS para 1.3.1 and 1.3.8 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: See Blk 16 freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 9: B - Administrative or Operational Use (12 Jul 2011) (COR)
Blk 10, 12, and 13: Update due 10 working days after a major hardware release.
group2: NSP totalprice2:
prep_by:
2011-08-03T15:10:00-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:49:01-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 6 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government requirements with regard to depth of content, format, otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any line_item: X005 exhibit: A xtdp: Yes xtm: Off othercat:
system: GATES ctr_no: FA4452-12-R-0001 contr: To be filled in at award data_item1: B006 title1: Interface Design Description (IDD) sub1: N/A auth1: DI IPSC-81436A ref1: See Blk 16 req_ofc1: USAF HQ AMC/A6IS dd250_1: N/A appcode1:
dist1: See Blk 16 freq1: See Blk 16 asof1: N/A firstsub1: See Blk 16 subsub1: See Blk 16 addr1_1: COR draft1_1:
reg1_1: 1 repro1_1:
addr1_2: See PWS para 1.4.4 draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0 totalreg1: 1 totalrepro1: 0 rmks1: Blk 5: PWS para 1.3.1 1.3.4 Fig. 2 1.3.8 Blk 9: C - Critical Technology (12 Jul 2012)
Blk 10, 12, and 13: IRS (B004) is designated within IDD. Due in conjunction with scheduled and unscheduled software release delivery.
Review – Dictated by government test schedule Response - Standard group1: NSP totalprice1:
data_item2: B007 title2: Data Base Design Description sub2: N/A auth2: DI-IPSC-81437A ref2: See Blk 16 req_ofc2: USAF HQ AMC/A6IS dd250_2: N/A appcode2:
dist2: C freq2: See Blk 16 asof2: N/A firstsub2: See Blk 16 subsub2: See Blk 16 addr2_1: COR draft2_1:
reg2_1: 1 repro2_1:
addr2_2: See PWS para 1.4.4 draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0 totalreg2: 1 totalrepro2: 0 rmks2: Blk 5: PWS para 1.3.1 1.3.4 Fig. 2 1.3.8 Blk 9: C - Critical Technology (12 Jul 2012)
Blk 10, 12, and 13: Due in conjunction with scheduled and unscheduled software release delivery.
Review – Dictated by government test schedule Response - Standard group2: NSP totalprice2:
prep_by:
2011-08-03T15:10:28-0500
MITCHELL.CEDRIC.1059118370
prep_date: 03 Aug 2011 app_by:
2012-02-29T15:49:17-0600
CURTIS.DERRICK.Q.1070869485
app_date: 29 Feb 12
Page: 7 of_pages: 18 app: Adobe Professional 8.0
Reset:
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the
Item 4; Clarification of submittal dates in Items 12 and 13;
conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the and does not require any substantial change to conform to Government…
This is the start of the file's text. The full file is on GovTribe.
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4452-12-R-0001-0004 | — | |
| Inventory List - GATES.xls | XLS spreadsheet | |
| Questions and Answers | — | |
| FA4452-12-R-0001-0003 | — | |
| FA4452-12-R-0001 Amd 0003.doc | DOC document | |
| Questions and Answers | — | |
| Questions and Answers | — | |
| FA4452-12-R-0001 Amd 0002.doc | DOC document | |
| J - Atchs 6 thru 12 | — | |
| Questions and Answers | — | |
| FA4452-12-R-0001-0002 | — | |
| FA4452-12-R-0001 Amd 0001.doc | DOC document | |
| Questions and Answers.docx | DOCX document | |
| FA4452-12-R-0001-0001 | — | |
| J - Attch 1 - PWS.docx | DOCX document | |
| J - Atch 4 - GFE List.docx | DOCX document | |
| J - Atch 5 - DD254.doc | DOC document | |
| J - Atchs 6 thru 12.docx | DOCX document | |
| J - Atch 3 - QASP.docx | DOCX document | |
| GATES - RFP | — | |
| J - Atch 2 - CDRL Package.pdf | ||
| GATES Bid Library Agenda.doc | DOC document | |
| J - Attch 1 - PWS.docx | DOCX document | |
| GATES Acquisition Library Rules_v1 0.ppt | PPT presentation |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .