Performance Work Statement Summary

This Performance Work Statement (PWS) describes a natural gas distribution system leak detection survey and minor repairs project at Travis Air Force Base in California, dated 14 May 2026. The contractor must survey approximately 197,490 linear feet of natural gas distribution mains, service lines, laterals, valves, valve boxes, meters, risers, and regulators across the base's commercial/industrial areas containing over 460 connected facilities. The contractor shall provide all management, tools, supplies, equipment, transportation, and personnel necessary to complete the work in compliance with Title 49 Code of Federal Regulations Part 192, applicable state regulations, EPA, NFPA, and OSHA requirements. Work must be performed Monday through Friday between 7:00 AM and 4:30 PM, with the contractor required to provide seven days' advance notice before commencing the survey and to coordinate with 60 Civil Engineer Squadron Water Fuel Systems Maintenance (WFSM) for scheduling and restricted area access.

The contractor must conduct joint surveys with government representatives using mobile and handheld detection equipment to locate, classify, and report all leaks, physically marking leak locations with GPS coordinates and yellow flags or measurements from fixed objects. Leaks must be classified by grade (Grade 1: greater than 75% concentration or proximity to buildings; Grade 2: 15-75% concentration; Grade 3: less than 15% concentration) and reported immediately for Grade 1 leaks to WFSM at specified phone numbers. The contractor shall perform repairs to above-ground systems only (valves, pipes, risers, vents, meters, stops, joints) and submit preliminary reports for Grades 2-3 weekly and a comprehensive final report within 30 calendar days containing typed leak inventories with GPS coordinates, classifications, concentration percentages, survey footage totals, and equipment counts. Contractor personnel must be licensed gas operators who speak and understand English, wear appropriate apparel, and maintain properly marked vehicles. The government provides electricity, water, and emergency services (at contractor's expense) but no office space, telephone services, cleaning services, or waste disposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS Natural Gas Distribution System Leak Detection Survey/Minor Repairs Travis AFB, CA

CUI

Performance Work Statement

Natural Gas Distribution System Leak Detection Survey

Travis AFB, California

14 MAY 2026

TABLE OF CONTENTS

1. SCOPE 3

1.2. BASIC SERVICES 3

1.3. HOURS OF OPERATION 3

1.4. SCHEDULES/NOTIFICATIONS 3

1.5. LOCATIONS 3

1.6. COMMERCIAL/INDUSTRIAL AREAS 3

1.7. SURVEY PROCEDURES 3

1.8. REPORTING 4

1.9. CONTRACTOR REQUIREMENTS 4

1.10. CIVIL ENGINEER POC 5

2. QUALITY ASSURANCE 5

3. GOVERNMENT FURNISHED PROPERTY/SERVICES/EQUIPMENT 5

PERFORMANCE WORK STATEMENT

Natural Gas Distribution System Leak Detection Survey, Travis AFB, CA

1. SCOPE: The contractor shall provide all management, tools, supplies, equipment, transportation, and personnel necessary to perform a Natural Gas Leak Detection Survey on approximately 197,490 LF of the natural gas distribution system in the commercial/industrial areas and residential areas of Travis AFB, California. The contractor shall identify, report and record all leak locations and perform work in a manner that will comply with Federal, State and local regulations for leak detection surveys and reporting services. Contractor personnel shall follow the procedures as set forth in Part 192, Title 49, Code of Federal Regulations and applicable state regulations. If identified, the contractor will make repairs to all above ground (only) systems to include valves, pipes, risers, vents, meters, stops, and joints.

1.2. BASIC SERVICES: Provide a leak detection survey for the underground natural gas distribution systems. Work covers all mains, laterals, valves and valve boxes, meters, risers, and regulators using mobile electronic gas leak detection equipment. Hand-held detection equipment will be used only when area is inaccessible by vehicle. The contractor will also be required to make necessary repairs to faulty or leaking above ground components.

1.3. HOURS OF OPERATION: All work on this project shall be accomplished within the hours of 7:00 AM to 4:30 PM Monday through Friday and no work will be accomplished on federal holidays. The contractor may request an extension of operating hours through the Contracting Officer (CO). An extension of operating hours must be requested by the contractor, a minimum of 24 hours in advance and must be authorized, in writing, by the CO. Any special accommodation will depend upon the availability of the 60 Civil Engineer Squadron (CES) Water Fuel Systems Maintenance (WFSM) shop personnel.

1.4. SCHEDULES/NOTIFICATIONS: The contractor shall provide the government seven (7) days advanced notice prior to start of the leak detection survey. The contractor shall plan, prepare, and maintain a consistent schedule of inspection/survey dates. The schedule shall divide the commercial/industrial areas into survey sections/plots that allow for daily completions, and most accurate reporting. Schedule will be provided to 60 CES WFSM prior to beginning survey, to allow coordination to restricted areas. The contractor will promptly notify 60 CES WFSM if the contractor or contractor personnel cannot meet scheduled inspection, survey or repair dates.

1.5. LOCATION: All work on this project will be performed on Travis AFB.

1.6. COMMERCIAL/INDUSTRIAL AREAS: The main base area of Travis AFB consists of approximately 197,490 LF of gas distribution mains and service lines/laterals. The commercial/industrial area contains over 460 facilities connected to the natural gas system.

1.7. SURVEY PROCEDURES: The contractor shall conduct a gas leak detection survey specifically to locate, classify and report all leaks present in the distribution system and related service lines and apparatuses. Contractor surveys will only be conducted jointly with a Government representative. Tests shall be conducted with mobile and/or handheld detection (by walking the gas lines when necessary) and recording devices that are designed and approved for natural gas leakage control surveys. All precautions shall be taken by the contractor to prevent damage to equipment, systems and property. There shall be no smoking, open flame or other ignition sources used by the contractor while conducting the survey; with the exception to any leak detection equipment such as Combustible Gas Indicator (CGI) and Flame Ionization (FI) instruments which may be used by fully trained/certified technicians/operators.

1.7.1. The contractor shall physically mark the location of all leaks at the time the leak is identified and record the GPS coordinates. In grass areas the contractor shall mark the location with yellow gas marking flags or yellow marking whiskers. On hard surfaces, the contractor shall measure and show with measurements from at least three (3) fixed objects the exact location of the leak. The contractor shall provide area dimensions and gas concentration percentage to identify the area of spread for all identified leaks.

1.7.2. The contractor shall classify all leaks detected as to percentage of concentration, spread and potential hazard based on the CGI or other approved detection equipment.

1.7.3. The contractor shall grade detected leaks as follows:

1.7.3.1. Grade 1 Leak: indicates greater than 75% gas concentration at any location. Any leak that is close to (within 25 LF) or under a building shall receive a Grade 1. Any leaks seeping into underground structures, such as manholes or basements, shall receive a Grade 1 indicator.

1.7.3.2. Grade 2 Leak: indicates 15% to 75% gas detection.

1.7.3.3. Grade 3 Leak: indicates a less than 15% gas concentration.

1.7.4. A member of the WFSM shop will be present during the survey.

1.8. REPORTING: Report all Grade 1 leaks upon detection IMMEDIATELY to the 60 CES WFSM shop foreman at 707-424-3025 or 707-424-8875.

1.8.1. Preliminary Reports: The contractor shall submit a preliminary report for Grade 1 leaks immediately upon finding. Preliminary reports for Grade 2 and 3 leaks will be provided to WFSM at the end of each survey week to the 60 CES WFSM Shop.

1.8.2. Final Reports: The contractor shall submit a Final Report of the gas leak detection survey to the Contracting Officer Representative within thirty (30) calendar days after completion of the survey/site tour and shall be contained in a binder. The Final Report shall consist of two (2) hard copies and one (1) on a writeable CD in the latest version of MS Word, Excel or both:

1.8.2.1. Contain a typed list indicating the total linear footage of mains and service lines surveyed and the total number of valves, meters and regulators/risers surveyed.

1.8.2.2. Provide a typed listing of all leaks encountered. Leaks shall be listed in the order of repair priority with the highest given to the gas concentration level and its associated grade. Each leak shall be assigned a number and identifiable with the same number on the report, gas distribution maps and survey sheets. The list shall identify location with GPS coordinates and leak classification/grade and percent concentration.

1.8.2.3. If repairs to above ground systems are identified, the contractor will coordinate with 60 CES WFSM to schedule repairs.

1.9. CONTRACTOR REQUIREMENTS: The contractor’s foreman or representative shall have the capability of speaking and understanding the English language.

1.9.1. Special Qualifications: Contractor personnel shall follow the procedures set forth in Code of Federal Regulations v3, Title 49, Part 192 and all applicable state and/or local regulations pertaining to the required defined work including, but not limited to, Environmental Protection Agency (EPA), National Fire Protection Association (NFPA), and Occupational Safety and Health Administration OSHA).

1.9.2. The contractor and contractor personnel shall be licensed gas operators, wear neat apparel that is appropriate for the work required and all vehicles will be properly marked with company name.

1.9.3. The contractor and their employees, at a minimum, shall comply with the following:

1.9.3.1. Title 49, Code of Federal Regulations v3, Subchapter D, Pipeline Safety

1.9.3.2. AFI 32-1069, Gas Supply and Distribution

1.9.4. The Contractor shall use mobile and handheld detection and recording devices that are designed and approved for natural gas leakage control surveys.

1.10. CIVIL ENGINEER POC: The contractor will contact 60 CES WFSM shop to setup dates and/or coordinate final or any spot check inspections of the contractor’s work.

2. QUALITY ASSURANCE: The government shall inspect and evaluate the contractor’s performance to ensure services are received in accordance in this contract. A WFSM representative shall inspect by watching actual task performance, physically checking an attribute of the completed task, checking a management information report, investigating customer complaints, conferring with facility managers, or otherwise inspecting the task or its results to determine whether performance meets the standards contained in this PWS. The WFSM representative will use the contractor’s work schedule or modified version thereof, to record validation results. Results of the validation then become the official Air Force record of the contractor’s performance. When a performance threshold has not been met or contractor performance has not been accomplished, a WFSM representative will initiate and provide the CO a Contract Discrepancy Report (CDR) for issuance to the contractor. The contractor shall respond to the CDR IAW instructions provided and return it to the CO within 10 calendar days of receipt.

3. GOVERNMENT FURNISHED PROPERTY/SERVICES/EQUIPMENT: The government has provided no property, office or storage space at Travis AFB. The Government will furnish electricity and water as necessary for accomplishing work in accordance with this contract and the contractor shall adhere to all base level utility conservation practices or requirements. The contractor shall be responsible for operating under conditions that prevent waste of utilities. The Government shall provide no telephone services, cleaning services or solid waste collection and/or disposal. If required, the contractor shall acquire refuse and recycling services and the contractor shall adhere to all base level recycling programs.

3.1. The government will provide Security, Medical, Police and Fire services at the contractor’s expense if required for an emergency. In the event of a medical emergency, a base ambulance service for transporting an injured employee to a local hospital is available on a cost reimbursement basis. The on-base emergency phone number is 707-424-4911.