This is a Statement of Work (SOW) for traffic signal upgrade services at Travis Air Force Base, dated March 26, 2026.

The contractor shall conduct a comprehensive site survey of ten (10) signalized intersections at Travis AFB and assess the condition of traffic signal controllers, cabinets, signal heads, pedestrian signal infrastructure, detection systems, pull boxes, underground conduit, electrical conductors and cabling, poles, mast arms, electrical power service, and intersection lighting. The survey must be performed by a traffic signal technician holding IMSA traffic signal level 2 or 3 certification. Upon completion, the contractor shall deliver a detailed report with photographs and recommendations for upgrades or replacements, conduct joint review meetings via Microsoft Teams, and ensure the new traffic controller cabinet can communicate with Centracs, Travis AFB's newly installed traffic monitoring system. The specific intersection locations are identified by building numbers and street names (Travis & Ragsdale, Ragsdale & Hickam, Ragsdale & Hanger, Hickam & Broadway, Travis & Broadway, Skymaster & Travis, Travis & First, Windward & Travis, Travis & Burgan, and Parker & Hickam).

The contractor must comply with Federal, State, and Local Code requirements including NSPC, NEC, ASHRAE, OSHA, NFPA, and UFC standards. The contractor is responsible for coordinating with facility occupants through SSgt Colton Fleming (707-424-5275), providing 14 days advance notice of shutdowns, restoring disturbed areas, maintaining a clean work site, obtaining necessary permits (DAF Form 103 renewed every 30 days, DAF Form 592 for welding/cutting operations, confined space permits), managing all hazardous waste disposal, and providing as-built system schematics and maintenance manuals upon completion. The contractor shall warranty all work for one year from government acceptance. Travis AFB security requirements include identity proofing, vetting through NCIC and CLETS checks, and verification that all personnel possess proper credentials to work in the United States.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

Traffic Signal Upgrade, BLDG 1957, 1961, 1965, 1967, 1969, 1971, 1973, 1975, 1977, SOW, 03/26/2026

CUI

1. DESCRIPTION OF SERVICES: Contractor shall perform site survey for ten (10) traffic signals on Travis Air Force Base

1.1.1. 1961: Travis & Ragsdale

1.1.2. 1977: Ragsdale & Hickam

1.1.3. 1975: Ragsdale & Hanger

1.1.4. 1965: Hickam & Broadway

1.1.5. 1979: Travis & Broadway

1.1.6. 1971: Skymaster & Travis

1.1.7. 1957: Travis & First

1.1.8. 1969: Windward & Travis

1.1.9. 1967: Travis & Burgan

1.1.10. 1973: Parker & Hickam

1.2. The contractor shall comply with Federal, State, and Local Code requirements, as well as the NSPC

(National Standard Plumbing Code), NEC (National Electrical Code), ASHRE, Heating Ventilation Air Conditioning standards, and Occupational Safety and Health Administration (OSHA), National Fire Protection Agency (NFPA), and Unified Facilities Criteria (UFC) codes and standards.

1.3. The contractor shall be responsible for coordinating with the building occupants through the facility manager to ensure there will be minimum interruptions to their daily mission. The contractor shall ensure the facility manager is notified of shut down fourteen (14) days in advance. The facility point of contact is SSgt Colton Fleming, and his phone number is 707-424- 5275.

1.4. Work Task [Traffic Signal Upgrade, WT # 18185512]:

1.4.1. Scope

1.4.1.1. Conduct site survey of ten (10) signalized intersections within Travis Air Force Base;

performed by traffic signal technician with IMSA traffic signal level 2 or 3 certification.

1.4.1.2. Assess condition of the following:

1.4.1.2.1. Traffic signal controllers

1.4.1.2.2. Traffic signal cabinet & internal components

1.4.1.2.3. Signal heads

1.4.1.2.4. Pedestrian signal heads, push buttons & ped poles

1.4.1.2.5. Traffic signal detection

1.4.1.2.6. Pull boxes

1.4.1.2.7. Underground conduit

1.4.1.2.8. Electrical conductors

1.4.1.2.9. Traffic signal cabling

1.4.1.2.10. Poles, mast arms and spans

1.4.1.2.11. Electrical power service

1.4.1.2.12. Static signage at intersection

1.4.1.2.13. Lighting at intersection

1.4.1.3. Deliver a report with pictures & list of recommendations for items to be upgraded / replaced.

1.4.1.4. Meetings via teams to jointly review reports.

1.4.1.5. The survey will ensure that the new traffic controller cabinet can communicate with

Centracs, the newly installed traffic monitoring system for Travis AFB.

1.5. It is the responsibility of the contractor to restore any areas/facility components disturbed by their work to their original state. The work area must be kept free and clear of all debris. Access to the facility or driving rights-of-way in the surrounding area will not be closed off or substantially obstructed for long periods of time. The contractor shall dispose of all construction debris off the installation and in accordance with all local, state, and federal requirements as required by section

6. The contractor shall leave work site clean and clear of any work debris, materials, supplies, tools, or equipment associated with this project.

1.6. The contractor shall be responsible for all damage to government property or personal property resulting from actions by contractor employees or equipment during the performance of this contract or while contractor employees are on Travis AFB.

1.7. Upon completion of the work, the contractor shall provide system schematics (as-builts) for what was installed and maintenance guidelines/service manuals for all components installed (if applicable). A minimum of one (1) hard copy shall be provided as well as one (1) digital file containing the information will be provided to 60th CES per the delivery instructions on the award.

1.8. The contractor shall warranty all work for a period of one (1) year from the date of acceptance by the government.

2. HAZARDOUS CONDITIONS. During the course of performing work under this contract, should the contractor find conditions existing that prevent the performance of task specified; the Contracting Officer shall be immediately notified. A confined-space permit must be obtained through the proper authorities before entering any confined space.

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. The Government will provide reasonable utilities and workspace for the contractor to perform the requested duties. There are no covered or secure storage areas available. The contractor will provide all equipment and storage media necessary to perform tasks.

3.1. Toilet Facilities. Use of existing toilet facilities in the immediate work area only will be permitted.

Contractor personnel will ensure facility cleanliness is maintained at all times.

3.2. Security Police and Fire Protection. The government will provide general on-base security police and fire protection service. Security Forces phone extension is (707) 424-2064 for emergencies, and

(707) 424-7222 for routine calls. Travis AFB Fire Department emergency phone is (707) 424-4911.

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA 1.10, 1.11, 1.12 can all be combined into a singly paragraph requiring site clean up

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Combined

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA Security Police. Change to Security Forces. Add numbers in SoW

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Updated

3.3. Telephone. The government shall not provide telephone services. If available, contractor may use government phones in a case of emergencies or during field and site work. No long-distance telephone calls will be authorized.

4. HEALTH AND SAFETY. All holes/pits/trenches/manway openings, etc., that are to be left open because they are being worked in, shall be surrounded with a 48-inch-high mesh fence with highly visible orange plastic coating. The fence shall be securely anchored with tension wires and posts as required to prevent sagging and located a minimum of 3 feet from the opening so as to prevent an individual, should they fall across the fencing, from falling into the opening. Holes shall also be covered, when not being worked in.

4.1. OSHA Requirements. All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 and 29 CFR 1926, project identified national standards, military manuals, instructions, pamphlets, standards, and handbooks, and with the Corps of Engineers (COE) Safety Manual 385-1-1, dated 03 Sep 96.

4.2. Welding, Cutting, and Brazing: Contractor shall obtain required advance approval for any process that includes welding, soldering, brazing, cutting with or use of a torch, or any other operation that involves a flame or equipment that produces a high degree of heat. Approval must be requested 24 hours in advance via DAF Form 592. The CE Representative will assist in filling out and processing the DAF Form 592 when/if required. Operations shall not commence until the Travis Fire Department approves DAF Form 592 and assigns a control number. Contractor shall put a fire watch in place and shall have appropriate fire extinguishers on-site at the location of the work. The contractor shall coordinate work to allow an on-site inspection by Travis Fire Prevention personnel prior to any portion of the work that requires DAF Form 592.

4.3. Work Clearance: A DAF Form 103, Base Civil Engineer Work Clearance Request, shall be completed by the contractor and approved by 60 CES prior to start of work; furthermore, the document must be renewed every 30 days until the completion of the contract. Preparation and approval of the DAF Form 103 can be worked through the assigned 60 CES Representative.

4.4. Confined Space: Contractors shall obtain all necessary approvals and permits for entry into confined space prior to work start.

5. Disposition of Waste, Excess, Scrap, and Salvage Materials. The title to all waste, excess, scrap, and salvage materials generated as a direct result of this contract is vested in the Contractor - unless specifically excepted below. Further (unless listed below in exceptions), these materials shall be disposed of off the Base by the Contractor in accordance with all applicable Federal, State, and Local Regulations.

6. Reporting Requirements. Contractor personnel shall report to the CE Representative, Contracting

Officer, or Security Forces any information or circumstances of which they are aware may pose a threat to

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA This contradicts the first line.

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

I believe this is referring to safety measures for holes being worked in vs not being worked in, since they need to be open if someone is working inside. I tried to add clarification. Please let me know if we need any more corrections

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA The line about small children falling in doesn’t need to be included. “Holes shall be covered, when not being worked in, with three quarter inch plywood or a metal grating”

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Updated

JOHNSON, CHRISTINA A CIV USAF AMC 60 CONS/PKA

This is a DAF Form 592; please search and replace all instances of “AF Form 592” with “DAF Form 592”

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Done

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA CO’s retain COR rights if it is over the threshold. This should say the CE Rep or inspector, or PM. Whoever is the CE person assigned.

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Done

JOHNSON, CHRISTINA A CIV USAF AMC 60 CONS/PKA

Change to, “A DAF Form 103”

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Done the security of DoD personnel, Contractor personnel, resources, and classified or unclassified defense information.

6.1. Security Requirements. Security Requirements. Travis Air Force Base is designated as a closed base. To promote security and safety, all contractors desiring access must adhere to installation entry requirements, including identity proofing and vetting. This includes a National Crime Information Center (NCIC) and California Law Enforcement Telecommunication System (CLETS) check. Identity proofing and vetting is not required for contractors if they have a current favorable government security clearance which can be verified through the Joint Personnel Adjudication System (JPAS). Contractors will be identity proofed and vetted each time a pass is issued. Security Forces may conduct random screenings at any time. If disqualifying base access information is found contractors may be denied base access or have passes currently issued revoked. The primary contractor will ensure all personnel and sub-contractor personnel possess the proper credentials that allow them to work in the United States.

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA Should outline security forces requirements if going to include this. I believe they only allow Real Id and passport

BURNETT, RYAN M CIV USAF AMC 60 CES/CEOE

Removed most of this section per recommendation. Please see new wording

PLATT, STEPHEN T SSgt USAF AMC 60 CONS/PKA Changed the wording a bit in this paragraph

File details come from the government source that posted it. Updated .