Amendment 0001 SF 30.pdf

PDF 581 KB Posted

Attached to
B154/B155 Repair Fire Suppression & ATS - AMENDED Federal contract opportunity
Solicitation number
FA442724R0004
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is an amendment to a federal solicitation for fire suppression and alarm system repair services at Travis Air Force Base in California. The key details are as follows:

The amendment clarifies that proposals are due to the 60th Contracting Squadron by 4:30 pm on January 4, 2024. It provides contact information for personnel coordinating site visits taking place on December 11, 2023 and confirms that this is a design-build project. The response due date and time, as well as miscellaneous instructions to offerors, have been updated in the solicitation sections. Offerors must submit price and technical proposals separately via email to the points of contact provided by the new deadline.

View the file

Other files for this federal contract opportunity

Other files attached to B154/B155 Repair Fire Suppression & ATS - AMENDED, newest first.
File Type Posted
Amendment 0003 SF 30.pdf PDF
Solicitation - FA442724R00040003.pdf PDF
Solicitation - FA442724R00040002.pdf PDF
Amendment 0002 SF 30.pdf PDF
Work Completed SOW B154-B155.pdf PDF
Solicitation - FA442724R0004 0001.pdf PDF
SOW XDAT18-1083 REPAIR BUILDINGS B154 B155.pdf PDF
Solicitation - FA442724R0004.pdf PDF
Travis Facilities Excellence Guide.pdf PDF
SECTION 01 03 00 PROJECT CLOSEOUT AUG 13.pdf PDF
SECTION 01000 Mar 2019.pdf PDF
Davis Beacon Wage Determination Dated 16NOV23.pdf PDF
Security Clause (1).pdf PDF
SECTION 01 56 00_Environmental Specifications April 2019.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The purpose of this Amendment is to clarify the date and time that proposals are due. Block 14 (Description of Amendment/Modification):

Proposals are due to the 60th Contracting squadron on 04JAN24 at 4:30 pm.

2. All As-Builts will be provided upon request.

3. Please coordinate with 2lt Andrews-Pestana at jacob.andrews-pestana.1@us.af.mil no later than 07DEC23 for all personnel requesting to be on the site visit taking place on 11DEC23 at 0900.

4. To clarify that this project is a design build.

5. No other terms or conditions under this contract have been changed.

6. Please contact jacob.andrews-pestana.1@us.af.mil

Section A - Solicitation/Contract Form

The following changes have been made:

INFORMATION FROM TO

Response Due Time 11:00 AM 04:30 PM Response Due Date 03 Jan 2024 04 Jan 2024

Section L - Instructions, Conditions, & Notices to Offerors or Quoters

Miscellaneous text in this section has been modified to:

PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of proposal, offeror must follow the instructions contained herein. Proposal must be complete, self sufficient, and respond directly to the requirements of this solicitation. The response shall consist of two (2) separate parts, Part I - Price Proposal (SF 1442 front and back)

Part II - Technical Requirements

Part III - Solicitation sections B thru K

B. Specific Instructions:

1. PART I - PRICE PROPOSAL - Submit documents via email as indicated below

a. Print solicitation document. Complete blocks 14-20C of the RFP Section A, SF 1442 (SF 1442, SF 1449, etc.) In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract. This document shall be returned in its entirety (front and back) via email to 2nd Lt Andrews-Pestana, (jacob.andrews-pestana.1@us.af.mil) with a copy to Jennifer Y. Munoz (jennifer.munoz.7@us.af.mil) by 4:30 P.M. on 04 January 2023.

b. If email submission rejects, offeror is required to call the Contracting Officer as soon as rejection is discovered to obtain Contracting Officer direction. Failure to provide the information to support rejection will result in offer being determined a late submission

2. PART II - TECHNICAL REQUIREMENTS

a) Professional Qualifications - Professional qualifications (license and experience) necessary for satisfactory performance of required services.

FA442724R00040001

b) Specialized Experience - Specialized experience and technical competence in the type of work required, including, experience in fire protection system, Pre-action fire sprinkler system, dry pipe sprinkler system, smoke detector system and fire Alarm/control panel system.

c) Past performance evaluations - Recency, relevancy, and scope similarities will be considering factors. Past performance on contracts with government agencies and private industry in terms of cost control, quality of work, and compliance with performance schedule.

d) Area/local Experience - Location in the general geographical area of the project and knowledge of the locality (Travis Air Force Base standard and California regulations) of the project will be considering factors.

e) Project Team Location - Location of contractor and sub-contractor will be considering factor.

f) Provide technical approach and schedule that demonstrates completion of project in accordance with solicited timelines

3. PART III - SOLICITATION FILL-IN SECTIONS B THRU K - Submit documents via email as indicated below.

a) Refer to Sections B through K of solicitation. Complete the necessary fill-ins and certifications in Sections B through K. This document shall be returned in its entirety (front and back) via email to 2ndLt Andrews-Pestana, (Jacob.andrews-pestana.1@us.af.

mil) with a copy to Jennifer Y. Munoz (Jennifer.munoz.7@us.af.mil) by 4:30 P.M. on 04 January 2023.

b) If email submission rejects, offeror is required to call the Contracting Officer as soon as rejection is discovered to obtain Contracting Officer direction. Failure to provide the information to support rejection will result in offer being determined a late submission.

c) Failure to comply with instructions may result in no consideration of your proposal.

C. Documents submitted in response to this RFP must be fully responsive to and consistent with the following:

a) Requirements of the RFP (Contract Line Items (CLINs)& Specifications), and government standards and regulations pertaining to the specifications.

b) Evaluation Factors for Award in Section M of this RFP.

c) All documents must be electronic.

FA442724R00040001

IDCode:
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 06 Dec 2023
ReqNo:
ProjNo: XDAT 18-1083
IssCode: FA4427
AdmCode:
IssuedBy: FA4427 60 CONS LGC

350 HANGAR AVE, ADMINISTRATIVE ONLY NO REQUISITIONS

TRAVIS AFB, CA 94535-2632

UNITED STATES

JACOB ANDREWS-PESTANA, Email: jacob.andrews-pestana.1@us.af.mil Telephone: 424-7760

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA442724R0004
SolDate: 01 Dec 2023
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: WILLIAM J. RIFE
ContDate:
CODate: 06 Dec 2023

File details come from the government source that posted it. Updated .