SECTION 31 23 00.00 20 Page 1
SECTION TABLE OF
CONTENTS DIVISION 31 -
EARTHWORK SECTION 31 23
00.00 20 EXCAVATION AND
FILL
02/11
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Capillary Water Barrier
1.2.2 Degree of Compaction
1.2.3 Hard Materials
1.2.4 Rock
1.2.5 Pile Supported Structure
1.3 SUBMITTALS
1.4 DELIVERY, STORAGE, AND HANDLING
1.5 CRITERIA FOR BIDDING
1.6 REQUIREMENTS FOR OFF SITE SOIL
1.7 QUALITY ASSURANCE
1.7.1 Shoring and Sheeting Plan
1.7.2 Dewatering Work Plan
1.7.3 Utilities
PART 2 PRODUCTS
2.1 SOIL MATERIALS
2.1.1 Satisfactory Materials
2.1.2 Unsatisfactory Materials
2.1.3 Cohesionless and Cohesive Materials
2.1.4 Expansive Soils
2.1.5 Nonfrost Susceptible (NFS) Material
2.1.6 Common Fill
2.1.7 Backfill and Fill Material
2.1.8 Select Material
2.1.9 Topsoil
2.2 POROUS FILL FOR CAPILLARY WATER BARRIER
2.3 UTILITY BEDDING MATERIAL
2.3.1 Sand
2.3.2 Gravel
2.4 SEWAGE ABSORPTION TRENCHES OR PITS
2.4.1 Porous Fill
2.4.2 Cover
2.5 BORROW
2.6 BACKFILL FOR UNDERDRAINAGE SYSTEMS
2.7 FILTER FABRIC
2.8 MATERIAL FOR PIPE CASING
2.8.1 Casing Pipe
2.8.2 Wood Supports
2.9 MATERIAL FOR RIP-RAP
2.9.1 Bedding Material
2.9.2 Grout
SECTION 31 23 00.00 20 Page 2
2.9.3 Rock
2.10 BURIED WARNING AND IDENTIFICATION TAPE
2.10.1 Warning Tape for Metallic Piping
2.10.2 Detectable Warning Tape for Non-Metallic Piping
2.11 DETECTION WIRE FOR NON-METALLIC PIPING
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Shoring and Sheeting
3.1.2 Drainage and Dewatering
3.1.2.1 Drainage
3.1.2.2 Dewatering
3.1.3 Underground Utilities
3.1.4 Machinery and Equipment
3.2 SURFACE PREPARATION
3.2.1 Clearing and Grubbing
3.2.2 Stripping
3.2.3 Unsuitable Material
3.3 EXCAVATION
3.3.1 Structures With Spread Footings
3.3.2 Pile Cap Excavation and Backfilling
3.3.3 Pipe Trenches
3.3.4 Hard Material and Rock Excavation
3.3.5 Excavated Materials
3.3.6 Final Grade of Surfaces to Support Concrete
3.4 SUBGRADE PREPARATION
3.4.1 Proof Rolling
3.5 SUBGRADE FILTER FABRIC
3.6 FILLING AND BACKFILLING
3.6.1 Common Fill Placement
3.6.2 Backfill and Fill Material Placement
3.6.3 Select Material Placement
3.6.4 Backfill and Fill Material Placement Over Pipes and at Walls
3.6.5 Porous Fill Placement
3.6.6 Trench Backfilling
3.7 BORROW
3.8 BURIED WARNING AND IDENTIFICATION TAPE
3.9 BURIED DETECTION WIRE
3.10 COMPACTION
3.10.1 General Site
3.10.2 Structures, Spread Footings, and Concrete Slabs
3.10.3 Adjacent Area
3.10.4 Paved Areas
3.10.5 Airfield Pavements
3.11 PIPELINE CASING UNDER PAVEMENT
3.11.1 Earthwork for Pipeline Casings
3.11.2 Steel Cased Pipelines
3.11.2.1 Hole for Pipeline Casing
3.11.2.2 Cleaning
3.11.2.3 Piped Utilities
3.11.2.4 End Seals
3.12 SPECIAL EARTHWORK REQUIREMENTS FOR SUBSURFACE DRAINS
3.12.1 Granular Backfill Without Filter Fabric
3.12.1.1 Perforated or Slotted Wall Pipe
3.12.1.2 Open-Joint Pipe
3.12.2 Granular Backfill Using Filter Fabric
3.12.2.1 Perforated or Slotted Wall Pipes
3.12.2.2 Open-Joint Pipe
3.12.2.3 Blind or French Drains
3.13 EARTHWORK REQUIREMENTS FOR SEWAGE ABSORPTION PITS
SECTION 31 23 00.00 20 Page 3
3.14 RIP-RAP CONSTRUCTION
3.14.1 Preparation
3.14.2 Bedding Placement
3.14.3 Stone Placement
3.14.4 Grouting
3.15 FINISH OPERATIONS
3.15.1 Grading
3.15.2 Topsoil and Seed
3.15.3 Protection of Surfaces
3.16 DISPOSITION OF SURPLUS MATERIAL
3.17 FIELD QUALITY CONTROL
3.17.1 Sampling
3.17.2 Testing
3.17.2.1 Fill and Backfill Material Testing
3.17.2.2 Select Material Testing
3.17.2.3 Porous Fill Testing
3.17.2.4 Density Tests
3.17.2.5 Moisture Content Tests
-- End of Section Table of Contents --
SECTION 31 23 00.00 20 Page 4
SECTION 31 23 00.00 20
EXCAVATION AND FILL
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2010) Installation of Ductile-Iron Water
Mains and Their Appurtenances
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016)
Structural Welding Code - Steel
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA C2 (2003) Lumber, Timber, Bridge Ties and Mine Ties - Preservative Treatment by Pressure Processes
AWPA P5 (2015) Standard for Waterborne
Preservatives
ASTM INTERNATIONAL (ASTM)
ASTM A139/A139M (2016) Standard Specification for
Electric-Fusion (ARC)-Welded Steel Pipe (NPS 4 and over)
ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe Piles
ASTM C136/C136M (2014) Standard Test Method for Sieve
Analysis of Fine and Coarse Aggregates
ASTM C33/C33M (2016) Standard Specification for Concrete
Aggregates
ASTM D1140 (2014) Amount of Material in Soils Finer than the No. 200 Sieve
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for
Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for
Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3)
ASTM D1883 (2016) Standard Test Method for California
Bearing Ratio (CBR) of
SECTION 31 23 00.00 20 Page 5
Laboratory-Compacted Soils
ASTM D2216 (2010) Laboratory Determination of Water
(Moisture) Content of Soil and Rock by Mass
ASTM D2321 (2014; E 2014) Standard Practice for
Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
ASTM D2487 (2011) Soils for Engineering Purposes
(Unified Soil Classification System)
ASTM D3786/D3786M (2013) Hydraulic Bursting Strength of
Textile Fabrics-Diaphragm Bursting Strength Tester Method
ASTM D422 (1963; R 2007; E 2014; E 2014)
Particle-Size Analysis of Soils
ASTM D4318 (2010; E 2014) Liquid Limit, Plastic
Limit, and Plasticity Index of Soils
ASTM D4355/D4355M (2014) Deterioration of Geotextiles from
Exposure to Light, Moisture and Heat in a Xenon-Arc Type Apparatus
ASTM D4491/D4491M (2015) Standard Test Methods for Water
Permeability of Geotextiles by Permittivity
ASTM D4533/D4533M (2015) Standard Test Method for Trapezoid
Tearing Strength of Geotextiles
ASTM D4632/D4632M (2015a) Grab Breaking Load and Elongation of Geotextiles
ASTM D4751 (2016) Standard Test Method for
Determining Apparent Opening Size of a Geotextile
ASTM D4759 (2011) Determining the Specification
Conformance of Geosynthetics
ASTM D4833/D4833M (2007; E 2013; R 2013) Index Puncture
Resistance of Geotextiles, Geomembranes, and Related Products
ASTM D5084 (2016a) Standard Test Methods for
Measurement of Hydraulic Conductivity of Saturated Porous Materials Using a Flexible Wall Permeameter
ASTM D6938 (2015) Standard Test Method for In-Place
SECTION 31 23 00.00 20 Page 6
Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
ASTM D698 (2012; E 2014; E 2015) Laboratory
Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft.)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
CID A-A-203 (Rev C; Notice 3) Paper, Kraft, Untreated
1.2 DEFINITIONS
1.2.1 Capillary Water Barrier
A layer of clean, poorly graded crushed rock, stone, or natural sand or gravel having a high porosity which is placed beneath a building slab with or without a vapor barrier to cut off the capillary flow of pore water to the area immediately below a slab.
1.2.2 Degree of Compaction
Degree of compaction is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D698/ASTM D1557, for general soil types, abbreviated as percent laboratory maximum density.
1.2.3 Hard Materials
Weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" but which usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.2.4 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.2.5 Pile Supported Structure
As used herein, a structure where both the foundation and floor slab are pile supported.
SECTION 31 23 00.00 20 Page 7
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Shoring and Sheeting Plan
Dewatering work plan
Blasting work plan
Submit 15 days prior to starting work.
SD-06 Test Reports
Borrow Site Testing; G
Fill and backfill test
Select material test
Porous fill test for capillary water barrier
Density tests
Moisture Content Tests
Copies of all laboratory and field test reports within 24 hours of the completion of the test.
1.4 DELIVERY, STORAGE, AND HANDLING
Perform in a manner to prevent contamination or segregation of materials.
1.5 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.
d. Ground water elevation is 4 feet below existing surface elevation.
e. Material character is indicated by the boring logs.
1.6 REQUIREMENTS FOR OFF SITE SOIL
SECTION 31 23 00.00 20 Page 8
Soils brought in from off site for use as backfill shall be tested for petroleum hydrocarbons, BTEX, PCBs and HW characteristics (including toxicity, ignitability, corrosivity, and reactivity). Backfill shall not contain concentrations of these analytes above the appropriate State and/or EPA criteria, and shall pass the tests for HW characteristics. Determine petroleum hydrocarbon concentrations by using appropriate State protocols.
Determine BTEX concentrations by using EPA SW-846.3-3 Method 5035/8260B.
Perform complete TCLP in accordance with EPA SW-846.3-3 Method 1311.
Perform HW characteristic tests for ignitability, corrosivity, and reactivity in accordance with accepted standard methods. Perform PCB testing in accordance with accepted standard methods for sampling and analysis of bulk solid samples. Provide borrow site testing for petroleum hydrocarbons and BTEX from a grab sample of material from the area most likely to be contaminated at the borrow site (as indicated by visual or olfactory evidence), with at least one test from each borrow site. For each borrow site, provide borrow site testing for HW characteristics from a composite sample of material, collected in accordance with standard soil sampling techniques. Do not bring material onsite until tests results have been received and approved by the Contracting Officer.
1.7 QUALITY ASSURANCE
1.7.1 Shoring and Sheeting Plan
Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations.
Drawings shall include material sizes and types, arrangement of members, and the sequence and method of installation and removal. Calculations shall include data and references used.
The Contractor is required to hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer shall be responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions. The Geotechnical Engineer shall update the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and shall submit an updated plan if necessary. A written report shall be submitted, at least monthly, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Geotechnical Engineer shall be available to meet with the Contracting Officer at any time throughout the contract duration.
1.7.2 Dewatering Work Plan
Submit procedures for accomplishing dewatering work.
1.7.3 Utilities
Movement of construction machinery and equipment over pipes and utilities during construction shall be at the Contractor's risk. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. Excavation made with power-driven equipment is not permitted within two feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted
SECTION 31 23 00.00 20 Page 9 by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
PART 2 PRODUCTS
2.1 SOIL MATERIALS
2.1.1 Satisfactory Materials
Any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and frozen, deleterious, or objectionable materials. Unless specified otherwise, the maximum particle diameter shall be one-half the lift thickness at the intended location.
2.1.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials. Unsatisfactory materials also include man-made fills, trash, refuse, or backfills from previous construction. Unsatisfactory material also includes material classified as satisfactory which contains root and other organic matter, frozen material, and stones larger than 3/4 inches.
The Contracting Officer shall be notified of any contaminated materials.
2.1.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM, GP-GM, GW-GM, SW-SM, SP-SM, and SM shall be identified as cohesionless only when the fines are nonplastic (plasticity index equals zero). Materials classified as GM and SM will be identified as cohesive only when the fines have a plasticity index greater than zero.
2.1.4 Expansive Soils
Soils that have a plasticity index equal to or greater than 12 when tested in accordance with ASTM D4318.
2.1.5 Nonfrost Susceptible (NFS) Material
A uniformly graded washed sand with a maximum particle size of 1 inch and less than 5 percent passing the No. 200 size sieve, and with not more than 3 percent by weight finer than US No. 70 sieve size.
2.1.6 Common Fill
Approved, unclassified soil material with the characteristics required to compact to the soil density specified for the intended location.
2.1.7 Backfill and Fill Material
ASTM D2487, classification GW, GP, GM, GC, SW, SP, SM, SC with a maximum ASTM D4318 liquid limit of 35, maximum ASTM D4318 plasticity index of 12, and a maximum of 25 percent by weight passing ASTM D1140, No. 200 sieve.
2.1.8 Select Material
Provide materials classified as GW, GP, SW, SP, by ASTM D2487 where indicated. The liquid limit of such material shall not
SECTION 31 23 00.00 20 Page 10 exceed 35 percent when tested in accordance with ASTM D4318. The plasticity index shall not be greater than 12 when tested in accordance with ASTM D4318, and not more than 35 percent by weight shall be finer than No. 200 sieve when tested in accordance with ASTM D1140. Coefficient of permeability shall be a minimum of 0.002 feet per minute when tested in accordance with ASTM D5084.
Bearing Ratio: At 0.1 inch penetration, the bearing ratio shall be 95 percent at 95 percent ASTM D1557 maximum density as determined in accordance with ASTM D1883 for a laboratory soaking period of not less than 4 days. The combined material shall conform to the following sieve analysis:
Sieve Size Percent Passing by
Weight
2 1/2 inches 100
No. 4 40 - 85
No. 10 20 - 80
No. 40 10 - 60
No. 200 5 - 25
2.1.9 Topsoil
Provide as specified in Section 32 92 19 SEEDING.
Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth.Amend topsoil pH range to obtain a pH of 5.5 to 7.
2.2 POROUS FILL FOR CAPILLARY WATER BARRIER
ASTM C33/C33M fine aggregate grading with a maximum of 3 percent by weight passing ASTM D1140, No. 200 sieve, and conforming to the general soil material requirements specified in paragraph entitled "Satisfactory Materials."
2.3 UTILITY BEDDING MATERIAL
Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Backfill to top of pipe shall be compacted to 95 percent of ASTM D698 maximum density. Plastic piping shall have bedding to spring line of pipe. Provide ASTM D2321 materials as follows:
a. Class I: Angular, 0.25 to 1.5 inches, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells.
SECTION 31 23 00.00 20 Page 11
b. Class II: Coarse sands and gravels with maximum particle size of
1.5 inches, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487.
2.3.1 Sand
Clean, coarse-grained sand classified as by ASTM D2487 for bedding and backfill.
2.3.2 Gravel
Clean, coarsely graded natural gravel, crushed stone or a combination thereof in accordance with ASTM D2487 for bedding and backfill as indicated. Maximum particle size shall not exceed 3.
2.4 SEWAGE ABSORPTION TRENCHES OR PITS
2.4.1 Porous Fill
Backfill material consisting of clean crushed rock or gravel having a gradation such that 100 percent passes the 2 inch sieve and zero percent passes the 1/2 inch sieve, conforming to the requirements of gradation No. 4 for coarse aggregate in ASTM C33/C33M.
2.4.2 Cover
Filter fabric, Kraft paper conforming to CID A-A-203, Grade B, No. 2, 50 pound weight or a layer of straw at least 2 inches thick as indicated.
2.5 BORROW
Obtain borrow materials required in excess of those furnished from excavations from sources outside of Government property.
2.6 BACKFILL FOR UNDERDRAINAGE SYSTEMS
Clean sand, crushed rock, or gravel meeting the following requirements:
a. Perforated or Slotted-Wall Pipe: Backfill meeting requirements of
Type I material as specified in Table 1.
b. Open Joint Pipe: Type II backfill consisting of Type II materials as specified in Table 1.
c. Blind or French Drains: Backfill consisting of Type II material as specified in Table 1.
d. Any Type Drain Used With Filter Fabric: Clean gravel or crushed stone or gravel conforming to ASTM C33/C33M coarse aggregate grading size 57, 67, or 7 fill consisting of Type I material as specified in Table 1.
SECTION 31 23 00.00 20 Page 12
Type I [Gradation E
ASTM C33/C33M
Type II Gradation 57
ASTM C33/C33M
ASTM D422 Sieve Size Percent Passing
Percent Passing
1.5 inches -- 100
1 inch -- 90 - 100
3/8 inch 100 25 - 60
No. 4 95 - 100 5 - 40
No. 8 -- 0 - 20
No. 16 45 - 80 --
No. 50 10 - 30 --
No. 100 0 - 10 --
2.7 FILTER FABRIC
Provide a pervious sheet of polyester, nylon, glass or polypropylene, ultraviolet resistant filaments woven, spun bonded, fused, or otherwise manufactured into a nonraveling fabric with uniform thickness and strength.
Fabric shall have the following manufacturer certified minimum average roll properties as determined by ASTM D4759:
Class A Class B
a. Grab tensile strength (ASTM D4632/D4632M) machine and transversed direction min. 180 80 lbs.
b. Grab elongation (ASTM D4632/D4632M) machine and transverse direction min. 15 15 percent
c. Puncture resistance (ASTM D4833/D4833M) min. 80 25 lbs.
d. Mullen burst strength (ASTM D3786/D3786M) min. 290 130 psi
e. Trapezoidal Tear (ASTM D4533/D4533M) min. 50 25 lbs.
SECTION 31 23 00.00 20 Page 13
Class A Class B
(1) Soil with 50 percent or less particles by weight passing US No. 200 Sieve, AOS greater than #30 US Std. Sieve
(2) Soil with more than 50 percent particles by weight passing US No. 200 Sieve, AOS greater than #50 US Std. Sieve
g. Permeability (ASTM D4491/D4491M) k fabric greater than k Soil
h. Ultraviolet Degradation (ASTM D4355/D4355M) 70 percent Strength retained at 150 hours
2.8 MATERIAL FOR PIPE CASING
2.8.1 Casing Pipe
ASTM A139/A139M, Grade B, or ASTM A252, Grade 2, smooth wall pipe. Casing size shall be of the outside diameter and wall thickness as indicated.
Protective coating is not required on casing pipe.
2.8.2 Wood Supports
Treated Yellow Pine or Douglas Fir, rough, structural grade. Provide wood with nonleaching water-borne pressure preservative (ACA or CCA) and treatment conforming to AWPA P5 and AWPA C2, respectively. Secure wood supports to carrier pipe with stainless steel or zinc-coated steel bands.
2.9 MATERIAL FOR RIP-RAP
Bedding material, Grout, Filter fabric and rock conforming to CALTRANS State Standard for construction indicated.
2.9.1 Bedding Material
Consisting of sand, gravel, or crushed rock, well graded, with a maximum particle size of 2 inches. Material shall be composed of tough, durable particles. Fines passing the No. 200 standard sieve shall have a plasticity index less than six.
2.9.2 Grout
Composed of cement, water, an air-entraining admixture, and sand mixed in proportions of one part portland cement to two parts of sand, sufficient water to produce a workable mixture, and an amount of admixture which will entrain sufficient air to produce durable grout, as determined by the Contracting Officer. Mix grout in a concrete mixer. Mixing time shall be sufficient to produce a mixture having a consistency permitting gravity flow into the interstices of the rip-rap with limited spading and brooming.
2.9.3 Rock
Rock fragments sufficiently durable to ensure permanence in the structure and the environment in which it is to be used. Rock fragments shall be
SECTION 31 23 00.00 20 Page 14 free from cracks, seams, and other defects that would increase the risk of deterioration from natural causes. The size of the fragments shall be such that no individual fragment exceeds a weight of 150 pounds and that no more than 10 percent of the mixture, by weight, consists of fragments weighing 2 pounds or less each. Specific gravity of the rock shall be a minimum of
2.50. The inclusion of more than trace 1 percent quantities of dirt, sand, clay, and rock fines will not be permitted.
2.10 BURIED WARNING AND IDENTIFICATION TAPE
Polyethylene plastic and metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines.
Provide tape on rolls, 3 inch minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Color and printing shall be permanent, unaffected by moisture or soil.
Warning Tape Color Codes
Red: Electric
Yellow: Gas, Oil; Dangerous Materials
Orange: Telephone and Other Communications
Blue: Potable Water Systems
Green: Sewer Systems
White: Steam Systems
Gray: Compressed Air
Purple: Non Potable, Reclaimed Water, Irrigation and Slurry lines
2.10.1 Warning Tape for Metallic Piping
Acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of tape shall be 0.003 inch. Tape shall have a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.10.2 Detectable Warning Tape for Non-Metallic Piping
Polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of the tape shall be 0.004 inch. Tape shall have a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Tape shall be manufactured with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.11 DETECTION WIRE FOR NON-METALLIC PIPING
SECTION 31 23 00.00 20 Page 15
Detection wire shall be insulated single strand, solid copper with a minimum of 12 AWG.
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Shoring and Sheeting
Provide shoring bracing, cribbing, trench boxes, underpinning and sheeting where indicated. In addition to Section 25 A and B of EM 385-1-1 and other requirements set forth in this contract, include provisions in the shoring and sheeting plan that will accomplish the following:
a. Prevent undermining of pavements, foundations and slabs.
b. Prevent slippage or movement in banks or slopes adjacent to the excavation.
c. Allow for the abandonment of shoring and sheeting materials in place in critical areas as the work is completed. In these areas, backfill the excavation to the elevation indicated within 3 feet of the finished grade and remove the remaining exposed portion of the shoring before completing the backfill.
3.1.2 Drainage and Dewatering
Provide for the collection and disposal of surface and subsurface water encountered during construction.
3.1.2.1 Drainage
So that construction operations progress successfully, completely drain construction site during periods of construction to keep soil materials sufficiently dry. The Contractor shall establish/construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and/or provide temporary ditches, dikes swales, and other drainage features and equipment as required to maintain dry soils, prevent erosion and undermining of foundations. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed. Excavated slopes and backfill surfaces shall be protected to prevent erosion and sloughing. Excavation shall be performed so that the site, the area immediately surrounding the site, and the area affecting operations at the site shall be continually and effectively drained.
3.1.2.2 Dewatering
Groundwater flowing toward or into excavations shall be controlled to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. French drains, sumps, ditches or trenches will not be permitted within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Control measures shall be taken by the time the excavation reaches the water level in order to
SECTION 31 23 00.00 20 Page 16 maintain the integrity of the in situ material. While the excavation is open, the water level shall be maintained continuously, at least 1 feet below the working level.
Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly.
Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.
3.1.3 Underground Utilities
Location of the existing utilities indicated is approximate. The Contractor shall physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor shall contact the Underground Service Alert (USA) for assistance in locating existing utilities. The Contractor shall scan the construction site with electromagnetic and sonic equipment and mark the surface of the ground where existing underground utilities are discovered. Machinery and Equipment
Movement of construction machinery and equipment over pipes during construction shall be at the Contractor's risk. Repair, or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged.
3.2 SURFACE PREPARATION
3.2.1 Clearing and Grubbing
Unless indicated otherwise, remove trees, stumps, logs, shrubs, brush and vegetation and other items that would interfere with construction operations within the clearing limits 5 feet outside of each building and structure line. Remove stumps entirely. Grub out matted roots and roots over 2 inches in diameter to at least 18 inches below existing surface.
3.2.2 Stripping
Strip suitable soil from the site where excavation or grading is indicated and stockpile separately from other excavated material. Material unsuitable for use as topsoil shall be stockpiled and used for backfilling. Locate topsoil so that the material can be used readily for the finished grading. Where sufficient existing topsoil conforming to the material requirements is not available on site, provide borrow materials suitable for use as topsoil. Protect topsoil and keep in segregated piles until needed.
3.2.3 Unsuitable Material
Remove vegetation, debris, decayed vegetable matter, sod, mulch, and rubbish underneath paved areas or concrete slabs.
3.3 EXCAVATION
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water.
Excavate soil disturbed or weakened by Contractor's operations, soils softened or made unsuitable for subsequent construction due to exposure to weather. Excavations below indicated depths will not be permitted except to
SECTION 31 23 00.00 20 Page 17 remove unsatisfactory material. Unsatisfactory material encountered below the grades shown shall be removed as directed. Refill with select material and compact to 90 percent of ASTM D698 ASTM D1557 maximum density. Unless specified otherwise, refill excavations cut below indicated depth with select material porous fill and compact to 90 percent of ASTM D698 ASTM D1557 maximum density. Satisfactory material removed below the depths indicated, without specific direction of the Contracting Officer, shall be replaced with satisfactory materials to the indicated excavation grade;
except as specified for spread footings. Determination of elevations and measurements of approved overdepth excavation of unsatisfactory material below grades indicated shall be done under the direction of the Contracting Officer.
3.3.1 Structures With Spread Footings
Ensure that footing subgrades have been inspected and approved by the Contracting Officer prior to concrete placement. Fill over excavations with concrete during foundation placement.
3.3.2 Pile Cap Excavation and Backfilling
Excavate to bottom of pile cap prior to placing or driving piles, unless authorized otherwise by the Contracting Officer. Backfill and compact overexcavations and changes in grade due to pile driving operations to 95 percent of ASTM D698 maximum density.
3.3.3 Pipe Trenches
Excavate to the dimension indicated. Grade bottom of trenches to provide uniform support for each section of pipe after pipe bedding placement. Tamp if necessary to provide a firm pipe bed. Recesses shall be excavated to accommodate bells and joints so that pipe will be uniformly supported for the entire length. Rock, where encountered, shall be excavated to a depth of at least 6 inches below the bottom of the pipe.
3.3.4 Hard Material and Rock Excavation
Remove hard material and rock to elevations indicated in a manner that will leave foundation material in an unshattered and solid condition.
Roughen level surfaces and cut sloped surfaces into benches for bond with concrete. Protect shale from conditions causing decomposition along joints or cleavage planes and other types of erosion. Removal of hard material and rock beyond lines and grades indicated will not be grounds for a claim for additional payment unless previously authorized by the Contracting Officer. Excavation of the material claimed as rock shall not be performed until the material has been cross sectioned by the Contractor and approved by the Contracting Officer. Common excavation shall consist of all excavation not classified as rock excavation.
3.3.5 Excavated Materials
Satisfactory excavated material required for fill or backfill shall be placed in the proper section of the permanent work required or shall be separately stockpiled if it cannot be readily placed. Satisfactory material in excess of that required for the permanent work and all unsatisfactory material shall be disposed of as specified in Paragraph "DISPOSITION OF
SURPLUS MATERIAL."
3.3.6 Final Grade of Surfaces to Support Concrete
SECTION 31 23 00.00 20 Page 18
Excavation to final grade shall not be made until just before concrete is to be placed. For pile foundations, the excavation shall be stopped at an elevation 6 to 12 inches above the bottom of the footing before driving piles. After pile driving has been completed, the remainder of the excavation shall be completed to the elevations shown. Only excavation methods that will leave the foundation rock in a solid and unshattered condition shall be used. Approximately level surfaces shall be roughened, and sloped surfaces shall be cut as indicated into rough steps or benches to provide a satisfactory bond. Shales shall be protected from slaking and all surfaces shall be protected from erosion resulting from ponding or flow of water.
3.4 SUBGRADE PREPARATION
Unsatisfactory material in surfaces to receive fill or in excavated areas shall be removed and replaced with satisfactory materials as directed by the Contracting Officer. The surface shall be scarified to a depth of 6 inches before the fill is started. Sloped surfaces steeper than 1 vertical to 4 horizontal shall be plowed, stepped, benched, or broken up so that the fill material will bond with the existing material. When subgrades are less than the specified density, the ground surface shall be broken up to a minimum depth of 6 inches, pulverized, and compacted to the specified density. When the subgrade is part fill and part excavation or natural ground, the excavated or natural ground portion shall be scarified to a depth of 12 inches and compacted as specified for the adjacent fill.
Material shall not be placed on surfaces that are muddy, frozen, or contain frost. Compaction shall be accomplished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Material shall be moistened or aerated as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment use. Minimum subgrade density shall be as specified herein.
3.4.1 Proof Rolling
Proof rolling shall be done on an exposed subgrade free of surface water (wet conditions resulting from rainfall) which would promote degradation of an otherwise acceptable subgrade. After stripping, proof roll the existing subgrade with six passes of a 15 ton, pneumatic-tired roller.
Operate the roller in a systematic manner to ensure the number of passes over all areas, and at speeds between 2 1/2 to 3 1/2 miles per hour.
When proof rolling under buildings, the building subgrade shall be considered to extend 5 feet beyond the building lines, and one-half of the passes made with the roller shall be in a direction perpendicular to the other passes. Notify the Contracting Officer a minimum of 3 days prior to proof rolling. Proof rolling shall be performed in the presence of the Contracting Officer. Rutting or pumping of material shall be undercut as directed by the Contracting Officer to a depth of 12 inches and replaced with select material.
3.5 SUBGRADE FILTER FABRIC
Place synthetic fiber filter fabric as indicated directly on prepared subgrade free of vegetation, stumps, rocks larger than 2 inches diameter and other debris which may puncture or otherwise damage the fabric.
Repair damaged fabric by placing an additional layer of fabric to cover the damaged area a minimum of 3 feet overlap in all directions. Overlap fabric at joints a minimum of 3 feet. Obtain approval of filter fabric installation before placing fill or backfill. Place fill or backfill on fabric in the direction of overlaps and compact as specified herein.
Follow manufacturer's recommended installation procedures.
SECTION 31 23 00.00 20 Page 19
3.6 FILLING AND BACKFILLING
Fill and backfill to contours, elevations, and dimensions indicated.
Compact each lift before placing overlaying lift.
3.6.1 Common Fill Placement
Provide for general site and under porous fill of pile-supported structures.Use satisfactory materials. Place in 6 inch lifts. Compact areas not accessible to rollers or compactors with mechanical hand tampers. Aerate material excessively moistened by rain to a satisfactory moisture content. Finish to a smooth surface by blading, rolling with a smooth roller, or both.
3.6.2 Backfill and Fill Material Placement
Provide for paved areas and under concrete slabs, except where select material is provided. Place in 6 inch lifts. Do not place over wet or frozen areas. Place backfill material adjacent to structures as the structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against the structure.
3.6.3 Select Material Placement
Provide under porous fill of structures not pile supported. Place in 6 inch lifts. Do not place over wet or frozen areas. Backfill adjacent to structures shall be placed as structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against structure.
3.6.4 Backfill and Fill Material Placement Over Pipes and at Walls
Backfilling shall not begin until construction below finish grade has been approved, underground utilities systems have been inspected, tested and approved, forms removed, and the excavation cleaned of trash and debris.
Backfill shall be brought to indicated finish grade and shall include backfill for outside grease interceptors and underground fuel tanks.
Where pipe is coated or wrapped for protection against corrosion, the backfill material up to an elevation 2 feet above sewer lines and 1 foot above other utility lines shall be free from stones larger than 1 inch in any dimension. Heavy equipment for spreading and compacting backfill shall not be operated closer to foundation or retaining walls than a distance equal to the height of backfill above the top of footing; the area remaining shall be compacted in layers not more than 4 inches in compacted thickness with power-driven hand tampers suitable for the material being compacted. Backfill shall be placed carefully around pipes or tanks to avoid damage to coatings, wrappings, or tanks. Backfill shall not be placed against foundation walls prior to 7 days after completion of the walls. As far as practicable, backfill shall be brought up evenly on each side of the wall and sloped to drain away from the wall.
3.6.5 Porous Fill Placement
Provide under floor and area-way slabs on a compacted subgrade. Place in 4 inch lifts with a minimum of two passes of a hand-operated plate-type vibratory compactor.
3.6.6 Trench Backfilling
SECTION 31 23 00.00 20 Page 20
Backfill as rapidly as construction, testing, and acceptance of work permits. Place and compact backfill under structures and paved areas in 6 inch lifts to top of trench and in 6 inch lifts to one foot over pipe outside structures and paved areas.
3.7 BORROW
Where satisfactory materials are not available in sufficient quantity from required excavations, approved borrow materials shall be obtained as specified herein.
3.8 BURIED WARNING AND IDENTIFICATION TAPE
Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inches below top of subgrade.
3.9 BURIED DETECTION WIRE
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. The wire shall extend continuously and unbroken, from manhole to manhole. The ends of the wire shall terminate inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. The wire shall remain insulated over its entire length. The wire shall enter manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, the wire shall terminate in the valve pit at the pump station end of the pipe.
3.10 COMPACTION
Determine in-place density of existing subgrade; if required density exists, no compaction of existing subgrade will be required. Density requirements specified herein are for cohesionless materials. When cohesive materials are encountered or used, density requirements may be reduced by 5 percent.
3.10.1 General Site
Compact underneath areas designated for vegetation and areas outside the 5 foot line of the paved area or structure to 90 percent of ASTM D698 ASTM D1557. Compact expansive materials to not less than 85 percent.
3.10.2 Structures, Spread Footings, and Concrete Slabs
Compact top 12 inches of subgrades to 95 percent of ASTM D698 ASTM D1557. Compact select material to 95 percent of ASTM D698 ASTM D1557.
3.10.3 Adjacent Area
Compact areas within 5 feet of structures to 90 percent of ASTM D698 ASTM D1557.
3.10.4 Paved Areas
Compact top 12 inches of subgrades to 95 percent of ASTM D698 ASTM D1557.
Compact fill and backfill materials to 95 percent of ASTM D698 ASTM D1557.
3.10.5 Airfield Pavements
Compact top 24 inches below finished pavement or 12 inches of subgrades, SECTION 31 23 00.00 20 Page 21 whichever is greater, to 100 percent of ASTM D1557; compact fill and backfill material to 100 percent of ASTM D1557.
3.11 PIPELINE CASING UNDER PAVEMENT
Provide new smooth wall steel pipeline casing under existing railroad and pavement by the boring and jacking method of installation. Provide each new pipeline casing, where indicated and to the lengths and dimensions shown, complete and suitable for use with the new piped utility as indicated.
3.11.1 Earthwork for Pipeline Casings
Provide excavation, sheet piling, shoring, dewatering, and backfilling for pipeline casings under this section.
3.11.2 Steel Cased Pipelines
Excavate and place bedding and backfill as indicated. Install pipeline casing by dry boring and jacking method as follows:
3.11.2.1 Hole for Pipeline Casing
Mechanically bore holes and case through the soil with a cutting head on a continuous auger mounted inside the casing pipe. Weld lengths of pipe together in accordance with AWS D1.1/D1.1M. Do not use water or other fluids in connection with the boring operation.
3.11.2.2 Cleaning
Clean inside of the pipeline casing of dirt, weld splatters, and other foreign matter which would interfere with insertion of the piped utilities by attaching a pipe cleaning plug to the boring rig and passing it through the pipe.
3.11.2.3 Piped Utilities
Provide in casing using wood supports adjusted to obtained grades and elevations indicated.
3.11.2.4 End Seals
After installation of piped utilities in pipeline casing, provide watertight end seals at each end of pipeline casing between pipeline casing and piping utilities. Provide watertight end seals as indicated.
3.12 SPECIAL EARTHWORK REQUIREMENTS FOR SUBSURFACE DRAINS
Excavate to dimensions indicated. Provide a bedding surface of no more than one inch of Type I subdrain backfill material and place on compacted native soil as indicated. Backfill french drains around and over the pipes after pipe installation has been approved. Place special granular filter material in 6 inch lifts and compact with mechanical, vibrating plate tampers or rammers until no further consolidation can be achieved. Compact backfill overlying the special granular filter material as specified for adjacent or overlying work.
3.12.1 Granular Backfill Without Filter Fabric
3.12.1.1 Perforated or Slotted Wall Pipe
SECTION 31 23 00.00 20 Page 22
Place granular material as pipe is laid and extend fit for a minimum of one pipe diameter on each side of and 18 inches above the top of the pipe. Place a layer of kraft paper on top of granular filter before continuing with the backfill.
3.12.1.2 Open-Joint Pipe
Place both types of granular material specified as pipe is laid forming an aggregate filter around the pipe. Provide Type II material to envelope the pipe a minimum of one-half the pipe diameter or twice the maximum aggregate size, whichever is larger, on each side and on top of the pipe.
Place Type I material next to and on top of the Type II material to provide a total fill extending at least one pipe diameter on each side of and 18 inches above the top of the pipe. Place a layer of kraft paper on top of the granular filter before continuing with the backfill.
3.12.2 Granular Backfill Using Filter Fabric
3.12.2.1 Perforated or Slotted Wall Pipes
Wrap one layer of filter fabric around pipe in such a manner that longitudinal overlaps are in unperforated or unslotted quadrants of the pipe. Overlap fabric a minimum of 2 inches. Secure fabric to pipe so that backfill material does not infiltrate through overlaps. Place granular material and extend it for one pipe diameter, minimum of 6 inches on each side of and 18 inches above top of pipe. Place a layer of filter fabric on top of granular filter before continuing with backfill.
3.12.2.2 Open-Joint Pipe
Wrap one layer of filter fabric around pipe joints overlapping a minimum of 2 inches in the longitudinal direction and extending at least 6 inches on both sides of the joint. Secure fabric to pipe so that backfill material does not infiltrate through overlaps. Place granular material specified and extend it for a minimum of one pipe diameter on each side of and 18 inches above top of pipe. Place a layer of filter fabric on top of granular filter before continuing with backfill.
3.12.2.3 Blind or French Drains
Install filter cloth in trenches with smoothly graded sides and bottom, free of cavities or projecting rocks. Lay the cloth flat but not stretched and secure with anchor pins. Place filter cloth so that drain water must pass through the cloth into the specified granular filter material. Overlap ends at least of 12 inches. Place backfill on filter cloth in the direction of overlaps. Where fabric is damaged, place a new piece of filter cloth over damaged area and overlap at least of 12 inches in every direction.
3.13 EARTHWORK REQUIREMENTS FOR SEWAGE ABSORPTION PITS
Provide sewage absorption pit as indicated. Grade trenches uniformly downward to ends of laterals. Place pre-cast concrete base ring for pit sections at the elevation indicated. Assemble succeeding sections as indicated and as recommended by manufacturer. Place porous fill around and over pipe around absorption pit as indicated. Take special care to prevent displacement of or damage to pipe and pit walls. Cover porous fill with kraft paper filter fabric as indicated before continuing with backfill for adjacent or overlying work.
3.14 RIP-RAP CONSTRUCTION
SECTION 31 23 00.00 20 Page 23
Construct rip-rap on bedding material with grout in accordance with
SECTION 31 00 00 EATHERWORK.
3.14.1 Preparation
Trim and dress indicated areas to conform to cross sections, lines and grades shown within a tolerance of 0.1 foot.
3.14.2 Bedding Placement
Spread bedding material uniformly to a thickness of at least 3 inches on prepared subgrade as indicated. Compaction of bedding is not required.
Finish bedding to present even surface free from mounds and windrows.
3.14.3 Stone Placement
Place rock for rip-rap on prepared bedding material to produce a well graded mass with the minimum practicable percentage of voids in conformance with lines and grades indicated. Distribute larger rock fragments, with dimensions extending the full depth of the rip-rap throughout the entire mass and eliminate "pockets" of small rock fragments. Rearrange individual pieces by mechanical equipment or by hand as necessary to obtain the distribution of fragment sizes specified above.
For grouted rip-rap, hand-place surface rock with open joints to facilitate grouting and do not fill smaller spaces between surface rock with finer material. Provide at least one "weep hole" through grouted rip-rap for every 50 square feet of finished surface. Weep holes shall consist of columns of bedding material, 4 inches in diameter, extending up to the rip-rap surface without grout.
3.14.4 Grouting
Prio…