This is a Questions and Answers document for the 2026 Charleston Airshow Sound RFQ (FA441826Q0014). The document clarifies four key aspects of the solicitation regarding sound, video, and jumbotron system requirements.
The government clarified that sound, video, and jumbotron systems must be proposed together rather than independently. Regarding speaker system design, there is no strict requirement for line-array speakers; contractors must simply ensure adequate coverage of the show line and crowd audio while meeting all contract requirements and providing a premium sound product for guests. Alternative speaker system designs are acceptable provided they meet overall performance and coverage requirements. For scheduling, delivery and setup may commence as early as 0700 on April 29th, with removal starting at 1730 on May 3rd. Overnight access to the base is not permitted, and the latest allowable entry time is 1959 hours.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 2026 Charleston Airshow Sound
FA441826Q0014
1. Can the sound system portion of the RFQ be separated from the video and/or jumbotron requirements, allowing audio and video to be proposed independently?
No. We would prefer to keep them together.
2. What is the specific operational or performance requirement driving the need for line-array speaker systems in this application?
No actual requirement for it to be a line array. Just need to ensure the show line is adequately covered and that the audio in the crowd supports the contract requirements.
We want to be able to provide a premium sound product for our guests.
3. Can the RFQ requirements be modified to allow alternative speaker system designs that do not include line-array speakers, provided they meet the overall performance and coverage requirements?
See question 2.
4. When is the earliest that delivery and setting can start? When is the earliest that the removal can start? Is overnight access permitted?
The 29th at 0700 A is the earliest delivery and setting - up can start. Removal can start at 1730 on May 3rd. Overnight access is not permitted. The latest you will be allowed to enter the base is 1959.