This is a Questions and Answers document for solicitation FA441725Q0029 for barrier maintenance services at Air Force Special Operations Command. The document addresses 20 questions from potential offerors regarding equipment specifications, contract terms, and submission requirements.
Key details include: The incumbent contractor is Nasatka Barrier, Inc. (1CEE3). The contract covers maintenance of RSS-2000 Electric Wedge barriers at multiple gates (Main Gate, Soundside Gate, East Gate, and CVI Gate) with a total of 17 barrier units, plus associated controls, lights, signals, and drop arms. The base period runs from March 30, 2025 to March 29, 2026, with four one-year options through March 29, 2030. Technical proposals are limited to 20 pages. The contractor must be certified by the AVB manufacturer. Quarterly preventive maintenance is required. Additional in-scope work will require submission and approval of service orders. All barriers are currently operational (green status), and any repairs identified will fall under additional in-scope work rather than the fixed-price preventive maintenance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation - FA441725Q0029 Barrier Mx.pdf | ||
| Attachment 1 - PWS Barriers - 16 Oct 2024.docx | DOCX document | |
| Attachment 2 - Wage Det. Rev 29, Dec 23, 2024.pdf | ||
| Attachment 3 - Instructions To Offerors - Barrier Mx.docx | DOCX document | |
| Attachment 4 - Evaluation Criteria - Barrier Mx.docx | DOCX document | |
| Attachment 5 - Past Performance Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA441725Q0029/Barrier Maintenance Questions and Answers Sheet
1. Is this a brand new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?
Previous contract number is FA441720F0256 and awarded off MAC IDIQ -
FA800319DA001.
2. Is there an equipment list per gate/ACP for all the barriers that are to be covered under this solicitation?
See question 12 for list.
3. Can you provide make and model for all barriers to be covered?
RSS-2000 Electric Wedge
4. Is there an incumbent service provider and can you provide their name?
Currently, Nasatka Barrier, Inc. – 1CEE3 is the service provider for barrier repairs.
5. Is there a preferred method for pricing the “Additional In-scope Work” CLIN X004 or shall this remain blank since it will be issued as mods to the contract on an as-needed basis?
No preferred method for pricing CLINX004. SOs will have to be submitted for approval. Funds may be set aside on this CLIN for SO repairs but will have to be approved.
6. Please confirm the contract Base Year and Option Year dates Base Yr: 30 Mar 25 - 29 Mar 26 Opt 1: 30 Mar 26 - 29 Mar 27 Opt 2: 30 Mar 27 - 29 Mar 28 Opt 3: 30 Mar 28 - 29 Mar 29 Opt 4: 30 Mar 29 - 29 Mar 30
7. Please confirm if there will be set aside funds for CLIN X004.
Funds will be set aside but a SO will still need to be submitted and approved.
8. Please confirm an equivalent brand preference due to Grip-Tite paint is no longer manufactured.
Any brand equivalent adhesive paint as stated in the PWS (1.3.1.6.)
9. Please confirm CLIN X005 will not be utilized in this contract.
CLIN X005 will not be utilized
10. Please confirm if the subject line total number of emails count pertains to only the series or all emails forwarded regarding FA441725Q0029. For example, RFI emails are a series, then a new count starts for the RFP.
The subject line total number of emails count pertains to submission of offer emails only.
11. Please confirm that a letter is only required from a potential Subcontractor if the Prime will be relying on the Subcontractor’s Past Performances.
• Per the addendum to 52.212-1 Instructions to Offerors:
1) 3. Subcontractor past performance cannot be disclosed to the prime quoter without the subcontractor's consent. Provide a letter from all subcontractors that will perform major or critical aspects of the requirement, consenting to the release of their past performance information to the prime contractor, only if it is being used as part of the past performance evaluation;
2) If a teaming arrangement/Joint Venture is contemplated, provide complete information as to the arrangement, including up to five (5) recent and relevant past/present performance information on previous arrangements with same partner or as this entity (CAGE). If this is a first-time joint effort, each party to the arrangement must submit separate past performance information. Subcontractor past performance may only be disclosed for use by the prime contractor if a letter of consent to release past performance information to the prime is completed by the subcontractor and included with the past performance.
• Per the addendum to 52.212-2 Evaluation of Offers: If a Teaming Agreement is submitted as part of the proposal, each teaming offeror's past performance will be evaluated separately using the same evaluation methods described above. The Prime Contractor's past performance will be weighted slightly more than equal based on their overall responsibility for contract management. The separate ratings of each party in the Teaming Agreement will be combined to determine an aggregate PERFORMANCE
ASSESSMENT CONFIDENCE RATING.
12. Please confirm below is a complete barrier/equipment list that will be included in contract.
o Main Gate Inbound: 4-Quantity Wedge Electric RSS 2000 o Main Gate Outbound: 3-Quantity Wedge Electric RSS 2000 o Soundside Gate Inbound: 2 Quantity Wedge Electric RSS 2000 o Soundside Gate Outbound: 2 Quantity Wedge Electric RSS 2000 o East Gate Inbound: 2-Quantity Wedge Electric RSS 2000 o East Gate Outbound: 2-Quantity Wedge Electric RSS 2000 o CVI Gate Inbound: 1-Quantity Wedge Electric RSS 2000 o CVI Gate Outbound: 1-Quantity Wedge Electric RSS 2000 o All above listed Gates entire barrier system including associated controls, lights, signals, and drop arms o No Wrong Way, Overspeed Detections, RFID, or IVUS
Below barriers are no longer maintain and not included in this contract.
o Building 1 Inbound: 1-Quantity Wedge Electric RSS 2000 o Building 1 Outbound: 1-Quantity Wedge Electric RSS 2000 o Command Post Inbound: 1-Quantity Wedge Electric RSS 2000 o Command Post Outbound: 1-Quantity Wedge Electric RSS 2000
13. What is the date of the last preventive maintenance (PM) service? What type of service was it (monthly, quarterly, semi-annual, annual)? If not an annual PM, when was the last annual PM conducted for scheduling purposes?
Quarterly March 2025, December 2024, September 2024, June 2024
14. Is the contractor required to be certified by the AVB manufacturer.
Yes.
See PWS (3.2 and 3.3)
15. I am requesting a list of barriers that will fall under Solicitation No. FA441725Q0029.
Main Gate Inbound: 4-Quantity Wedge Electric RSS 2000 Main Gate Outbound: 3-Quantity Wedge Electric RSS 2000 Soundside Gate Inbound: 2 Quantity Wedge Electric RSS 2000 Soundside Gate Outbound: 2 Quantity Wedge Electric RSS 2000 East Gate Inbound: 2-Quantity Wedge Electric RSS 2000 East Gate Outbound: 2-Quantity Wedge Electric RSS 2000 CVI Gate Inbound: 1-Quantity Wedge Electric RSS 2000 CVI Gate Outbound: 1-Quantity Wedge Electric RSS 2000
16. Can you please provide a list of the equipment on site that require maintenance for the RFP/ soliitation?
See response on question 12.
17. The instructions to offerors, under Part II – Technical Capability Submission, states, “Limited to no more than fifty (20) pages..” Please clarify the page limit.
Correction should be: no more than twenty (20) pages.
18. We do not read Part III - Past Performance Information Submission to mean submission of questionnaire’s by customers as mandatory, but this section states, “The Government highly recommends the submission of completed questionnaires prior to the solicitation closing date and time.”
As there were 30 or so bases put out for bid under the previous IDIQ contract and over 100 more that could potentially come out individually, the requirement for customers to fill out and send questionnaires for each base can be overwhelming.
As at least 17 bases have already gone out to bid with this PWS, we respectfully request consideration for any bidder for whom customers are unable to make the additional time to reply.
The Government will remain with, ‘highly recommends the submission of completed questionnaires prior to the solicitation closing date and time.”
19. The PWS does not include information on the locations, makes, models, and quantities of the barriers. Please provide a breakdown by gate of the quantity of barriers installed at each gate by make/model and whether the SDDCTEA Safety Scheme is installed at each respective gate, including overspeed, wrong way detection, etc.
See response on question 12.
20. APPENDIX F: BARRIER SYSTEM RATING CRITERIA of the PWS indicates that a significant amount of existing equipment is either inoperable (red) or in need of repair (yellow). Please confirm repair of this equipment will not be included in the firm fixed price for preventative maintenance and if repair will be requested as additional in-scope work or outside the maintenance contract.
APPENDIX F: BARRIER SYSTEM RATING CRITERIA is a reporting guidance.
All Barriers on this contract are operational (green).
If any repairs are identified they will fall under the additional in-scope work.