FA4417-16-R-0003, Attachment 10 11 Mar 2016

WORKING TIME ANALYSIS

SEED PROJECT: FTEV 16-1018 Repair Rutting on Independence Road ESTIMATOR: Joseph A. De Stefano 884-3779

ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS

1. Mobilization 1

2. Make Req'd Submittals 10

3. Secure Material/Equipment 3

4. Perform All Work 30

5. Correct Punch List ltems 1

TOTAL ALLOWABLE CONTRACT TIME 45