FA4417-16-R-0003, Attachment 10 11 Mar 2016
WORKING TIME ANALYSIS
SEED PROJECT: FTEV 16-1018 Repair Rutting on Independence Road ESTIMATOR: Joseph A. De Stefano 884-3779
ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS
1. Mobilization 1
2. Make Req'd Submittals 10
3. Secure Material/Equipment 3
4. Perform All Work 30
5. Correct Punch List ltems 1
TOTAL ALLOWABLE CONTRACT TIME 45