FA4417-16-R-0003, Attachment 7 22 Jan 2016
WORKING TIME ANALYSIS
Technical SAMPLE PROJECT: Repave Asphalt Area ESTIMATOR: Joseph A. De Stefano 884-3779
ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS
1. Mobilization 1
2. Make Req'd Submittals 10
3. Secure Material/Equipment 30
4. Perform All Work 45
5. Correct Punch List ltems 3
6. Other 0
TOTAL ALLOWABLE CONTRACT TIME 89