BLANK_3052_PNQS 25-1844 Repair Maxwell Traffic Lights.pdf

PDF 103 KB Posted

Attached to
PNQS 25-1844 Repair Maxwell Traffic Lights Solicitation (Amendment 0001)
Solicitation number
FA330025R0037
Issued by

About this file

This document is a Construction Cost Estimate Breakdown for a traffic signal repair project at Maxwell Air Force Base in Alabama. The project, identified by Purchase Request Number PNQS 25-1844, involves multiple electrical and traffic signal improvement tasks across three divisions: General Requirements, Site Work, and Electrical/Fire System/Communications. Specific work items include administrative tasks, outages and permits, removal of existing signals, traffic controller unit installation, LED traffic signal light installations (3-section and 5-section), pedestrian LED traffic light signals, pedestrian push buttons, LED luminaires, 8-phase controller installation, and intersection detector installation. The cost estimate template includes line items for material costs, labor costs, taxes, insurance, overhead, profit, and bonding, with standard percentage allocations for various cost categories (10% overhead, 10% profit, 2.5% bonds).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT MATERIAL/EQUIP. COSTS LABOR RATES OTHER

LINE ITEM OF QUANTITY d Manhours AVERAGE DIRECT LINE

NO. MEASURE UNIT TOTAL RATE TOTAL COSTS TOTAL

Division 1 (General Requirements) 1 Administrative EA 2 Outages and Permits EA

Division 2 (Site Work) 3 Removal Of Exisiting Signals EA

Division 16 (ELECTRICAL/FIRE SYSTEM/COMMUNICATIONS) 4 Traffic Controller Unit Installation EA 5 3-Section Yellow LED Traffic Signal Light EA 6 5-Section Yellow LED Traffic Signal Light EA 7 Pedestrian LED Traffic Light Signal EA 8 Pedestrian Push Buttons EA 9 LED Luminares Traffic Light Signal EA 10 8-Phase Controller EA 11 Install Intersection Detectors EA

12 TOTAL

13 Material Costs 14 Tax on Materials 10%

15 TOTAL MATERIAL COST

16 Labor Cost 17 Insurance & Tax on Labor 10%

18 TOTAL LABOR COST

19 Total Other Direct Costs 20 Total Material, Labor, Tax & Insurance

21 TOTAL DIRECT COSTS

22 Overhead 10% 23 Subtotal 24 Profit 10% 25 Bonds 2.5%

26 TOTAL

Signature: ______________________________________

PNQS 25-1844 FAC# 2036 MAXWELL AFB

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

REPAIR TRAFFIC SIGNALS, MAXWELL

PURCHASE REQUEST NUMBER PROJECT NUMBER/WORK ORDER WORK LOCATION

CONSTRUCTION COST ESTIMATE BREAKDOWN

OMB No. 0704-0193

CONTRACTOR DATE

ADDRESS

400 Cannon Street Maxwell Air Force Base Alabama

File details come from the government source that posted it. Updated .