ADAL Dog Kennels Pre-Proposal Questions
FA309921R0008
Questions
1. Will there be another site visit beside the site visit that was scheduled 7/12/2021?
2. Can the proposal be submitted as an email in Lieu of DOD?
3. Can CPARS be used in Lieu of Past Performance questionnaires?
4. Can previous completed PPQ’s be used in lieu of Past Performance questionnaire attached in the solicitation documents?
5. Do you have a template subcontract consent letter you can provide?
6. Do the CPARS or PPQs count towards page count in Past Performance section?
7. Solicitation states Questions are due 5 days before Site Visit? Can you extend?
8. Do you need the original Bid bond to be mailed to you along with the electronic version that will be submitted?
9. Can you provide Attachment 5 listed in the technical requirements on page 52?
10. Can you provide Attachment 16 Reference Sheet?
11. What is the Solicitation section L part II Subfactor 2 Personnel/ Team Qualifications requesting interested parties to show? Can we provide this on the resumes?
Answers
1. This is an error due to contract specialist oversight. There will be an amendment accomplished in order to update the correct dates for both the EAL due date and Site Visit date.
2. Yes, Please review Section L-10.
3. CPARS will be pulled on every proposal regardless, the PPQ gives an interested party the opportunity to share any past performance that may not be covered by CPARS.
4. No, PPQ’s must be sent to us directly from the other company/agency.
5. You can use any letter preference you would like, it just needs to state that they give consent.
6. Yes, if you submit CPARS or PPQ’s they will be counted as part of the 10 Page limit for Part III – Past Performance Information.
7. Please refer to 52.236-27, in which it states, “Any questions or any other type of Request for Information (RFIs) that arise before or after the site visit must be submitted no later than 5 days after the site visit was held.”
8. Please refer to Section 10 of the SF 1442, Item 13 states “Certified Bid Bonds with corporate seal are required in office at the time the proposal is due.”
9. Please see attachment 5. Progress Schedule and Progress Report that is attached to the solicitation in Sam.gov.
10. Please see Attachment 16. Financial Institution Reference Sheet.
11. Any relevant past performance involving construction with similar magnitude and complexity. This information can be provided on the resumes.