6. Schedule of Material Submittals.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
ADAL Dog Kennel
Solicitation number
FA309921R0008
Issued by

View the file

Other files

File Type Posted
E. Utilities Detail, B139.pdf PDF
D. Sewer Detail, B117.pdf PDF
ADAL Dog Kennel Preproposal Questions and Answers - 2.pdf PDF
B. la-Security Forces Complex_Boring Locations and Logs.pdf PDF
C. la-Security Foreces-FDA.pdf PDF
Solicitation Amendment FA309921R00080002 SF 30 CO signed.pdf PDF
A. Sewer Detail, B139.pdf PDF
Solicitation Amendment FA309921R00080001 SF 30.pdf PDF
19. ADAL Dog Kennels Pre-Proposal Questions.pdf PDF
17. Past Performance Questionnaire.pdf PDF
14. Notification of Compliance with Contract Insurance Requirements.pdf PDF
8. AF IMT 3000 Material Approval Submittal.pdf PDF
2. LAFB - ADAL Dog Kennel 100_ Design Specifications.pdf PDF
4. LAFB Specific Environmental Requirements.pdf PDF
Solicitation - FA309921R0008.pdf PDF
5. Progress Schedule and Progress Report.xlsx XLSX spreadsheet
18. Entry Authority List (EAL).pdf PDF
16. Financial Institution Reference Sheet.pdf PDF
13. Wage Determination TX20210008 01Jan21.pdf PDF
15. AETC 47 - Recovered Materials Determination.pdf PDF
12. standard_design_mil_working_dog_july_2018.pdf PDF
1. LAFB - ADAL Dog Kennel 100_ Design Drawings.pdf PDF
11. Communication Design Change.pdf PDF
10. AF Form 3952 Chemical Hazardous Material Request.pdf PDF
9. AF IMT 103 Base Civil Engineering Work Clearance Request.pdf PDF
3. Division 01 Specifications.pdf PDF
7. DD Form 1354 Transfer and Acceptance of DoD Real Property.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 17-1006 PROJECT TITLE Replace/Repair Fire Detection System, B502 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALLAUGHLIN DIV 01 SPECS REFERENCESTATEMENT OF OBJECTIVES REFERENCEENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Pre-Construction Submittals
1Construction Site Plan, Laydown area12.1NLT 30 Days after NTP 1
2AF Form 1032.29.13.2.1NLT 7 Days after NTP 1
3Project Schedule6.1.19.2NLT 5 Days after NTP 1
4Contractor Health and Safety Plan3.2.2NLT 30 Days after NTP 1
5Environmental Survey & Protection Plan3.4.2.2NLT 30 Days after NTP 1
6QC Plan4.2.4NLT 30 Days after NTP 1
7QC Manager Qualifications4.2.3NLT 30 Days after NTP 1
8Safety Data Sheets10.4.53.1.2NLT 30 Days after NTP 1
9Hazardous Waste Disposal Documentation3.2.22.2, 3.1, 5.2NLT 30 Days after NTP 1
10Solid Waste Disposal Report2.2.2NLT 30 Days after NTP 1
11Records of Existing Conditions7.1.1NLT 30 Days after NTP 1
12Recycling Disposal Report5.1NLT 30 Days after NTP 1
13Shop Drawings10.4.42NLT 30 Days after NTP 1
14Specifications (UFGS)10.4.52NLT 30 Days after NTP 1
15OPSEC Training2.2NLT 30 Days after NTP 1
16Entry Access List1.8.2Every 3rd week of PoP after NTP 2
17Phase Plan2.0NLT 30 Days after NTP 1
Construction Submittals
18Progress Report6.1.25.2Bi-weekly
19Meeting Minutes6.2.1NLT 3 Days after meeting
Materials
20Samples10.4.6As Needed
21Product Data10.4.5As Needed
22Test Reports10.4.8As Needed
23Certifications10.4.9As Needed
24Field Reports10.4.11As Needed
Close-Out
25Quality Control Manager Punchlist13.41By Pre-Final Inspection
26O&M Manuals10.4.121NLT 2 weeks after Final Inspection
27Draft DD Form 135413.35.3114 Days Prior to Pre-Final Inspection
28Final DD Form 135413.35.31At the Final Inspection
29As Built Drawings/CAD Files10.4.131NLT 2 weeks after Final Inspection
30Warranty13.2NLT 2 weeks after Final Inspection
Schedule of Submittals Template, Feb 05 (SAF/AQCP)

Task Order # FA3099-16-D-0002-0002 SOW Atch 2

&"Times New Roman,Regular"&12Page &P of &N

File details come from the government source that posted it. Updated .