Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 18-1014 PROJECT TITLE Repair Roof Pool Bath House, B399 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCEDESIGN DRAWINGSSPECIFICATIONSDESIGN CALCULATIONSSHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATA/ MSDSTEST REPORTSFIELD REPORTSRESUMEREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal fergusog: Enter the due date from the Contractor (MM/DD/YY) fergusog: Enter the date received from the Contractor. (MM/DD/YY) fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) fergusog: Enter the date the submittal is due back from CE fergusog: Enter the Submittal Number fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

1Construction Site PlanDiv01 8-211NLT 15 Days After NTP #1
2Environmental Protection PlanDiv01 9-51NLT 15 Days After NTP #1
3Safety PlanDiv01 6-311NLT 15 Days After NTP #1
4Weather Tight PlanSoW 4.51NLT 15 Days After NTP #1
5Shop DrawingsDiv01 2-11NLT 15 Days After NTP #1Div01 2-1.4.3.2
6SDS SheetsDiv01111NLT 15 Days After NTP #1Div01 9-12.2
7Materials SpecificationsDiv01 2-1111NLT 15 Days After NTP #1Div01 2-1.4.3.3
8Key Personnel ResumesDiv01 1-6.b1NLT 15 Days After NTP #1Div01 4-3; 7-4
9Manufacturer's WarrantiesDiv01 1-21NLT 15 Days After NTP #1
10Contractor WarrantyDiv01 1-21NLT 15 Days After NTP #1
Close-Out
11Approved Draft DD 1354Div01 10-4114 Days prior to Pre-Final Inspection
12As-Built DrawingsDiv01 10-217 days before Final Inspection
13DD 1354Div01 10-41At Final Inspection
14Construction Warranty Management PlanDiv01 10-31Same Date as Project Acceptance
Schedule of Submittals, 21 Jan 2016 (SAF/AQCP)