This is a Questions and Answers document for federal contract FA301026R0008, issued by the Air Force for project MAHG241006 Replace Magnolia DFAC AHUs. The document clarifies technical and administrative requirements for replacing air handling units (AHUs) at a Dining Facility (DFAC).
Key staffing requirements specify that the Superintendent and QA/QC Manager roles must be performed by two separate individuals, though the Site Safety and Health Officer position may be filled by either role. A contract-specific QA/QC Plan is required; however, a separate Safety Plan is not required. Regarding equipment specifications, exhaust fans and make-up air units must be replaced in kind based on existing configurations (downblast replaced with downblast, upblast with upblast), as determined by contractor survey. All exhaust fans and kitchen supply make-up air units are to be replaced, not repaired. Current pipe sizes are specified as AHU-1 and AHU-3 (3" chilled water, 1.25" hot water) and AHU-2 (2" chilled water, 1" hot water). Fire dampers are not required for return ductwork replacements on any unit. The contractor must provide commissioning and post Test, Adjust, and Balance (TAB) of both air and water systems to prove positive pressure of the dining hall, with results submitted to the Contracting Officer upon completion. The project is not tax exempt. Contract award does not constitute Notice to Proceed; NTP will be issued separately post-award.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA301026R0008
MAHG241006 Replace Magnolia DFAC AHUs - Questions and Answers
1. In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?
A: No, per SOW: 3.7.3 The roles of Superintendent and QA/QC must be performed by two separate individuals.
2. Are contractors required to issue a contract specific QA/QC Plan?
A: QA/QC plan is required. (See technical factors listed in Section L and M)
3. Are contractors required to issue a contract specific Safety Plan?
A: Safety Plan is not required
4. Is this project tax exempt?
A: No, this project is not tax exempt.
5. The drawings schedules mention the use of direct drive exhaust fans, while the specifications mention belt drive fans. Which type of exhaust fans are desired?
A: Some are direct drive; some are belt drive dependent on size and application. Provide per equipment schedules.
6. On site, EF-5 appears to be an upblast fan and the rest downblast. The schedule on the drawings and the specifications do not mention the use of downblast or upblast exhaust fans. Are we replacing the exhaust fans on the roof with the same type as what is currently on the roof?
A: Yes, contractor is to replace in kind. If the fan is a downblast, replace with a downblast. If the fan is an upblast, replace with an upblast.
3.2.4.1.2 Replace supply and exhaust fans. The contractor shall conduct a survey of the exhaust and supply fans being replaced within the scope of the contract to determine the types to replace in kind. Refer to the Mechanical Schedule provided within the drawings.
7. For AHU-3 return ductwork, a portion of the ductwork is missing insulation by the unit.
Does the Air Force want this portion of ductwork reinsulated/replaced?
A: Yes, repair the duct and insulation.
8. The specifications mention fire dampers and the drawings do not show any fire dampers.
Is a fire damper required for the return ductwork being replaced for AHU-3? If so, then does AHU-1 and AHU-2 require fire dampers for the return ductwork as well?
A: No, fire dampers are not required for the return ductwork being replaced for AHU-1, AHU-2, nor AHU-3.
9. On M-203, is the 6” flex ductwork being replaced with flex ductwork of the same size?
A: Yes, replace with the same size.
10. A portion of the OA ductwork where the volume damper is located for AHU-1 is rusted and returning air within the mechanical space. Is replacing this portion of OA ductwork desired?
A: Yes, replace the rusted volume damper, rusted OA duct work, and rusted return ductwork for AHU-1
11. What is the current chilled water and hot water pipe sizes to the units?
A: AHU-1 Chilled Water 3"/Hot water is 1- 1/4" (1.25")
AHU-2 Chilled Water 2"/Hot water is 1"
AHU-3 Chilled Water 3"/Hot water is 1- 1/4" (1.25")
12. Please confirm acceptable for contractor to triple hat the project. i.e. Super, SSHO and Qc manager as one individual
A: No, per SOW: 3.7.3 The roles of Superintendent and QA/QC must be performed by two separate individuals. However, SSHO may be filled by either Superintendent or QA/QC personnel.
13. Please confirm all exhaust fans and make up air units are to be replaced, not repaired?
A: All exhaust fans and all kitchen supply make-up air fans, kitchen exhaust fans are to be replaced with new. Refer to Key Notes on DWG M-201:
1. INSTALL NEW KITCHEN EXHAUST FAN ON ROOF.
2. INSTALL NEW MAKE-UP AIR UNIT ON ROOF.
3. INSTALL NEW EXHAUST FAN ON ROOF.
14. Please confirm if government will be providing commissioning for this project or is contract to price to provide commissioning?
A: Contractor is to provide for the commissioning and TAB of both air and water systems. Refer to SOW: 3.2.4.4.1.5 Test, adjust and balance (TAB) the completed system to prove positive pressure of the dining hall. Submit TAB to CO upon completion as part of project closeout procedures. Refer to SPECS 23 09 00 3.6 PERFORMANCE
VERIFICATION TESTING
15. Please confirm is this project is post tab only or will be pre-tab be required?
A: A TAB was completed prior to programming this project. Existing TAB has been provided for reference. Post TAB required as per SOW. 3.2.4.4.1.5 Test, adjust and balance (TAB) the completed system to prove positive pressure of the dining hall. Submit TAB to CO upon completion as part of project closeout procedures.
16. Please confirm if award constitute as NTP or will NTP be issued at a later date?
A: Contract award does not authorize NTP. NTP will be issued as a separate document, post award.