This is an addendum to the contract documents for a construction project at Keesler Air Force Base in Mississippi. Addendum #1, dated May 11, 2026, modifies the scope of work for Project B8568 (MAHG251001), titled "Construct New School Drop-Off Lane."
The original scope involved relocating an existing fire hydrant and capping the old water line. Upon further investigation, the water lines are suspected to be Asbestos Cement Pipe, requiring additional work. The fire hydrant lateral line is 6 inches in diameter, and the main water line is 10 inches, though the exact depth cannot be confirmed. The addendum expands the scope to require the contractor to abate approximately 17 feet of the hydrant lateral and install new 6-inch PVC pipe connecting to the existing 10-inch water main. No changes to the drawings have been made. The specifications have been updated to include UFGS 02 82 00 – Asbestos Remediation, with updated specification documents provided as attachments. This addendum takes precedence over conflicting conditions in the specifications and other contract documents and must be acknowledged by the contractor.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM # 1 Date: 5/11/2026
PROJECT NAME: Construct New School Drop-Off Lane, B8568
LOCATION: Keesler AFB, Mississippi
PROJECT NUMBER: MAHG251001
This Addendum is hereby part of the Contract Documents and as must be acknowledged with the Contract. The following conditions take precedence over conflict conditions in the Specifications, on the Drawings, and in any other Contract Document.
When a change is called for on a Drawing, this change shall carry through all applicable drawings, including all related architectural, civil, structural, mechanical, plumbing, and electrical drawings. The Contract Documents are hereby amended in the following particulars:
Changes to the Scope of Work:
Changes to the original Scope:
The original scope was to relocate an existing fire hydrant and cap the old water line.
After further investigation, it is suspected that the water lines are Asbestos Cement Pipe. The existing fire hydrant lateral line is 6-inches, and the main water line is 10-inches. The depth of the pipes cannot be confirmed.
The addendum will include the following changes:
1) Contractor to abate +/- 17 feet hydrant lateral.
2) Contractor to install new 6-inch PVC pipe connecting to the existing 10-inch water main.
Changes to the Drawing:
No changes to the drawings
Changes to the Specifications:
UFGS 02 82 00 – Asbestos Remediation
ATTACHMENTS:
Updated SPECs
END OF ADDENDUM # 1