This document is a Questions and Answers (Q&A) file for a Wrong Way Detection solicitation by the Department of the Air Force Air Education and Training Command. The opportunity (Solicitation Number FA301025Q0033) is a re-bid of a previous contract (#FA301025Q0007) with key modifications, specifically focused on defining installation requirements. The Q&A covers technical specifications including sensor technology limitations, environmental conditions (operating from -40 to 170 degrees Fahrenheit, withstanding 100 mph winds), and installation parameters.
Key technical requirements include a solar backup system with limited operational capability, visual warning signs with flexible design specifications, and an audible alarm system that can be heard from the guard shack. Installation considerations involve mounting on existing infrastructure (subject to approval), obtaining dig permits on the base, and contractor access during M-F 0800-1630 hours. Contractors will be vetted through background checks, and installation will be coordinated to minimize traffic disruption. The government will provide as-built drawings and conduct performance testing through security force scenarios. The solicitation deadline for questions was 7 August 2025, with responses to be posted on SAM.gov.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW Wrong Way Detection 11 Aug 2025.docx | DOCX document | |
| FA301025Q00330001.pdf | ||
| SOW Wrong Way Detection 31 July 2025.pdf | ||
| Solicitation - FA301025Q0033.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A Wrong Way Detection Q&A Version 1 7 Aug 2025
| Question # | Date Received | Question | Response |
| 1 | 08/07/25 | Is this solicitation a revised version of the previous opportunity (#FA301025Q0007), which was awarded to Technologisty, LLC? If so, why is this being re-bid? | Yes, Government needed to clearly define installation. |
| 2 | 08/07/25 | By defining the sensor technology, the robustness, accuracy, and resilience to false and nuisance alarms may suffer. Will other sensor technologies be considered aside from those called out specifically (e.g., Radar, in-ground inductive loop detector, and Thermal)? | No, please see updated SOW for requirement. |
| 3 | 08/07/25 | What are the exact specifications for the solar backup system? Should it provide full operational capability during power outages, or is it intended as a limited backup? | Solar intended as a limited backup during outtages. |
| 4 | 08/07/25 | What are the specific sub-tropical temperature ranges and wind speeds the system must withstand? Are there any additional environmental conditions (e.g., humidity, salt exposure) that need to be considered? | Negative 40 to 170 degrees farenheit / 100 mph / humidity should also be considered. See updated SOW. |
| 5 | 08/07/25 | For Gate 7 (Pass Road), what is the anticipated timeline for the gate overhaul? Will the contractor be responsible for relocating the system, or will this be handled separately? | Anticipated timeline is withing the next two years. This will be a separate contract. |
6 08/07/25 What are the dimensions and design requirements for the visual warning signs? Are there specific standards for illumination, font size, or color? Currently no specific dimenions as long as it meets readability outlined in SOW.
| 7 | 08/07/25 | Are there any restrictions or guidelines for mounting solutions on existing infrastructure? For example, are there weight limits or specific materials that must be used? | If Mounting on existing infrastructure is possible, subject to approval. The proposed mounting solution must not obstruct existing security systems and must comply with safety regulations. Relocatability is essential for the system installed at Gate 7 (Pass Road) due to the planned gate overhaul. |
| 8 | 08/07/25 | What are the testing criteria for system functionality? Will the government provide a checklist or specific scenarios to test the system's performance? | Security Forces will conduct scenarios to test detection performances. |
| 9 | 08/07/25 | What are the terms and conditions for the warranty and maintenance plan? Are there specific requirements for response times, coverage, or service frequency? | Requesting a standard warranty. See updated SOW. |
| 10 | 08/07/25 | Will the contractor be responsible for obtaining any necessary permits for trenching, concrete pouring, or other installation activities? If so, will the government assist in this process? | There will be dig-permit requirements and since all the property is on base, coordination will occur with base agencies/personnel. No permits required from the city. |
| 11 | 08/07/25 | Will As-built drawings be made available for existing infrastructure, dwellings, and utilities? | Yes |
| 12 | 08/07/25 | What are the requirements for the audible alarm system? Is there a specific decibel level or sound type that must be used to ensure it is heard clearly by personnel? | Audible alarm must be heard from within the guardshack and provide a warning to entry controllers and motorists. Provide a means to adjust the volume on all the audible alarms. Provide an audible annunciator that sounds until a silence reset button is pressed. See updated SOW. |
| 13 | 08/07/25 | Are there any restrictions on the type of materials used for the freestanding structures and conduits? For example, should they be corrosion-resistant, meet specific durability standards, or Architectural Compatibility Plans (ACPs) / AF Corporate Facilities Standards (AFCFS) requirements? | Free standing should be corrosion-resistant and meet Architectural Compatibility Plans (ACPs) / AF Corporate Facilities Standards (AFCFS) requirements. See updated SOW. |
| 14 | 08/07/25 | Will the government provide access to the site during installation and testing, or are there specific hours or conditions for site access? | Contractors will be premitted access but will be vetted to ensure they meet the requirement for installation access. Those not passing a background check through the visitor center will be denied. Depending on scope of work, would coordinate installation phase with contractor to minimize stress on traffic flow for the installation. Normal operating hours are M-F 0800 – 1630. See updated SOW. |
| 15 | 08/07/25 | What are the procedures for addressing inspection findings? Will the contractor be given a specific timeframe to resolve issues before final acceptance? | Yes a timeframe will be given once issues are identified. Timeframe will be in accordance with the severity of the issue and required correction. |