Q A_(Set_2).pdf
PDF 8 KB Posted
- Attached to
- FLECS Pathfinder Federal contract opportunity
- Solicitation number
- FA2860-16-R-0014
About this file
This document contains questions and answers regarding Solicitation FA2860-16-R-0014 for maintenance and repair services of the FLECS Pathfinder system. The solicitation seeks a contractor to provide organizational level maintenance including removing and replacing parts at the Line Replaceable Unit level to meet a 30-day repair cycle for components within the continental US and 45-days for overseas components, while ensuring continuous system operation. The incumbent contractor's existing spare parts inventory will be transferred to the new contractor at no cost, consisting of various spare parts as detailed in an attached equipment inventory spreadsheet. Low voltage electronics and cabling within enclosures are covered under a separate contract and are not included. Product and service requirements, response timelines, pricing terms, federal agencies involved, and other key details are provided.
Second set of responses to questions received
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_0002.pdf | ||
| Updated_Equipment_Inventory_(7_Apr).xls | XLS spreadsheet | |
| Work_Order_Historical_Data.xlsx | XLSX spreadsheet | |
| Q A_(Set_1).pdf | ||
| Equipment_Inventory.xls | XLS spreadsheet | |
| Amend_0001.pdf | ||
| FLECS_Pathfinder_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION FA2860-16-R-0014
FLECS Pathfinder Maintenance and Repair
Questions and Answers (Set 2)
1. Can we get a list of the existing spares/equipment that will be provided?
Answer: An updated Equipment Inventory (7 Apr) spreadsheet has been attached that includes the current quantities of spare parts.
2. Will the Government provide all current equipment manuals and related documentation to the contractor upon award of the contract?
Answer: The Government DOES NOT have copies of the equipment manuals or any related documentation.
3. Will a current contact list for OEM vendors be provided upon award of the contract?
Answer: These WILL NOT be provided. The contractor will need to seek out their own vendors for parts and pricing. The Equipment Inventory spreadsheet has many of the vendors attached to the specific part.
4. Please confirm that low voltage electronics and cabling within Node Boxes and enclosures containing the 105 PLCs are maintained under a separate contract and are not to be maintained under this contract.
Answer: The 105 PLCs will be part of the resulting contract with regards to the operation of the Rated Gates. Each 105 PLC is located within each gate operator box where a Rated gate is located.
5. Please provide the current spares list to support organizational level maintenance to remove/replace at the LRU level required for the 30-day (CONUS)/45-day (OCONUS) repair cycle while assuming continuous system operation.
Answer: See attached Updated Equipment Inventory (7 Apr) spreadsheet.
6. Will the current sparing inventory be transferred to the new contractor?
Answer: Yes, the current sparing inventory will be transferred to the new contractor.
a. At who’s cost?
Answer: The Government will transfer the existing spares to the new contractor.
b. What does the inventory consist of (part descriptions and qty’s)
Answer: See attached Updated Equipment Inventory (7 Apr) spreadsheet.