Attachment_1_Steam_ _Condensate_Specifications.pdf

PDF 5 MB Posted

Attached to
Steam & Condensate IDIQ Federal contract opportunity
Solicitation number
FA2835-15-R-0020
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hanscom Air Force Base

About this file

FA2835-15-R-0020 Attachment 1 Specifications

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Architectural Compatibility Guidelines March 2015 Contract Technical Specifications Edition Hanscom Air Force Base, MA

TECHNICAL SPECIFICATIONS

for

Steam and Condensate

(IDIQ)

Hanscom AFB, MA

25 Mar 2015

HANSCOM APPROVAL:

User:

Fire Department:

Security Forces:

Safety:

Communications/Telephone:

Communications/LAN:

Bioenvironmental:

Government Environmental:

Chief of Engineering:

DEPARTMENT OF THE AIR FORCE

HANSCOM AFB, MA

TOC-1

1015354727C Typewritten Text

ATTACHMENT 1 - FA2835-15-R-0020

SECTION TITLE

01 00 00 GENERAL REQUIREMENTS

01 02 50 MEASUREMENT AND PAYMENT

01 03 50 CONTRACT MODIFICATION PROCEDURES

01 04 00 PROJECT COORDINATION

01 09 00 DEFINITIONS AND STANDARDS

01 20 00 PROJECT MEETINGS

01 29 00 PAYMENT PROCEDURES

01 29 00A AF FORM 3064

01 29 00B AF FORM 3065

01 30 00 SUBMITTALS

01 30 00A SUBMITTAL LOG

01 30 00B CONTRACTOR HAZARDOUS MATERIAL REPORT

01 31 00 SCHEDULES AND REPORTS

01 33 00 SUBMITTAL PROCEDURES

01 34 00 SPECIAL CLAUSES

01 44 00 CONTRACTOR QUALITY CONTROL (CQC)

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 52 40 CONSTRUCTION WASTE MANAGEMENT

01 52 50 SAFETY REQUIREMENTS

01 52 50A CONTRACTOR SAFETY QUESTIONNAIRE

01 52 50B SUBCONTRACTOR SAFETY MANAGEMENT PLAN

01 52 50C PRE-LIFT CHECKLIST

01 54 00 PROTECTION OF PERSONS AND PROPERTY

01 59 30 SECURITY REGULATIONS

01 60 00 MATERIALS AND EQUIPMENT

01 63 00 SUBSTITUTIONS

01 63 20 PRODUCTS

01 70 00 PROJECT CLOSEOUT

01 71 00 CLEANING

01 73 10 CUTTING AND PATCHING

01 73 20 SELECTIVE DEMOLITION

01 78 00 WARRANTIES

01 99 00 SUSTAINMENT MANAGEMENT SYSTEMS

01 99 00A ATTACH #1 SMS BUILDER DATA INVENTORY AND ASSESSMENT

02 41 00 DEMOLITION

02 80 00 HAZARDOUS AND REGULATED MATERIAL REMOVAL AND

DISPOSAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 14 ASBESTOS HAZARD CONTROL ACTIVITIES

02 83 13 LEAD IN CONSTRUCTION

02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING

PCBs AND MERCURY

03 01 30.71 CONCRETE REHABILITATION

03 15 00.00 10 CONCRETE ACCESSORIES

TOC-2

** END OF TABLE OF CONTENTS**

03 30 00 CAST-IN-PLACE CONCRETE

03 45 00 PRECAST ARCHITECTURAL CONCRETE

07 84 00 FIRESTOPPING

09 90 00 PAINTS AND COATINGS

10 14 53 TRAFFIC SIGNAGE

22 14 29.00 40 SUMP PUMPS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM

23 22 13.35 40 STEAM TRAPS

23 22 23.00 40 STEAM CONDENSATE PUMPS

23 22 25 STEAM VALVES

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING

SYSTEMS

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19.00 10 INSULATED WIRE AND CABLE

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 05 83 WIRING CONNECTIONS

26 27 26 WIRING DEVICES

26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

31 00 00 EARTHWORK

31 13 17 TREE PROTECTION AND TRIMMING

31 32 11 SOIL SURFACE EROSION CONTROL

32 01 13 BITUMINOUS SEAL

32 01 17.16 SEALING OF CRACKS IN BITUMINOUS PAVEMENTS

32 11 16 SUBBASE COURSE FOR PAVING

32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE

COURSE

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS AND SIDEWALKS

32 16 13 CONCRETE SIDEWALKS

32 16 14 CURBING

32 17 24.00 10 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

33 40 00 STORM DRAINAGE UTILITIES

33 60 01 VALVES, PIPING, AND EQUIPMENT IN VALVE MANHOLES

33 61 00 PREFABRICATED UNDERGROUND COOLING DISTRIBUTION

SYSTEM

33 61 13 PRE-ENGINEERED UNDERGROUND HEAT DISTRIBUTION SYSTEM

33 61 15 HEAT DISTRIBUTION SYSTEMS IN CONCRETE TRENCHES

TOC-3

SECTION 01 00 00

GENERAL REQUIREMENTS

1.01 SCOPE OF WORK

A. The scope of work under this contract consists of furnishing all labor, materials, equipment, travel, services, demolition, hazardous materials abatement, renovation, repair, and construction of all facilities, pavements, and utilities at the locations shown in paragraph 1.02, in strict accordance with the Statement of Work (SOW), drawings, technical specifications, Hanscom Architectural Guidelines and all other contract procurement documents. A project specific “Request for Proposal” or “Task Order” will be issued in addition to the Hanscom guide specifications herein defining all requirements of the contract that shall be provided by the contractor within the awarded Period of Performance (PoP).

1.02 LOCATION:

A. The site of the work shall be at one or more of the following installation locations:

1. Hanscom Air Force Base (AFB), MA

2. Cape Cod Air Force Station (AFS), Sagamore, MA

3. Fourth Cliff Recreation Annex- Humarock, MA

4. Sagamore Hill Electronics Research Annex- Hamilton, MA

1.03 PRINCIPAL ITEMS OF WORK

A. The principal items of work listed in the advertised set contract documents in no way limit the responsibility of the contractor to perform all items of construction specified in the Statement of Work (SOW), drawings, and/or technical specifications.

B. The contractor shall perform all aspects of the contract in full accordance with the current edition of the Architectural Compatibility Guideline (ACG) of the installation the work is being performed. Final determination and direction of whether or not the work proposed/perform is in accordance with the ACG requirements in cases where interpretations of the requirement differ will be made by the Contracting Officer.

1.04 TRAFFIC AND COORDINATION OF WORK

A. The contractor shall coordinate all phases of work with Government Representative. A detailed time schedule shall be submitted within five (5) calendar days after receipt of a written Notice to Proceed. It is the intent of this contract for all work to be performed in an orderly manner with minimum disturbance and inconvenience to vehicular and pedestrian traffic. Access for fire protection shall be maintained at all times. The contractor shall coordinate and provide traffic control for any temporary altered patterns; no personnel, signage, equipment, or logistical assistance from Security Forces will be provided.

GENERAL REQUIREMENTS 01 00 00 - 1

B. Within five (5) calendar days of each Delivery Order Notice to Proceed, the contractor shall submit a schedule of anticipated requirements for road closures or traffic impacts.

This includes full road closures, partial road closures, and impacts to parking areas. This schedule shall be separate from any other construction schedule otherwise required. Each request shall have listed:

1. Anticipated date;

2. Approximate duration;

3. List of roads, facilities, and parking areas affected;

4. Reason for the shutdown (work to be accomplished during the shutdown);

5. Traffic Control Plan.

C. Twenty one (21) calendar days prior to each required road closure or traffic impact, the contractor shall make a specific request for the road closure or traffic impact. This request shall include the information listed above, plus requested time and duration of the shutdown.

D. No traffic impacts will be permitted at the Hartwell or Vandenberg gates during peak traffic times.

1. Peak AM Traffic: 0600 to 0830

2. Peak PM Traffic: 1500 to 1700

1.05 SITE CONDITIONS

A. The contractor shall be responsible for all surveys in connection with the work. Any site conditions differing from reference or design plans shall be immediately reported to the Government Representative.

1.06 WORKING HOURS

A. The normal working hours for industrial/administrative areas shall be an eight (8) hour, or less, period between the hours of 7:30 AM and 4:15 PM excluding Saturday, Sunday and Federal holidays.

B. Work in housing areas shall not commence before 8:30 AM and will terminate by 4:30

PM.

C. If the contractor intends to work other than the normal hours, they must submit a written request 72 hours in advance for the approval of the Government Representative.

1.07 PROTECTION OF WORK SITE

A. The contractor shall be responsible for protection of the work site and existing Government property. Any items of Government property damaged by the contractor's operations shall be repaired or replaced at the contractor's expense.

GENERAL REQUIREMENTS 01 00 00 - 2

1.08 CLEANUP

A. The contractor shall provide the necessary containers, bins, storage areas to facilitate effective waste management. All containers, bins, and/or storage areas shall be maintained in such manner to prevent debris from windblown. Waste and debris shall be removed off base in accordance with Federal, State, and local regulations and in a manner to prevent spillage on streets or adjacent areas.

1.09 UTILITIES

A. All utilities required for this contract shall be available to the contractor at point of source and in the vicinity of the work area. The contractor shall provide all labor and materials for the connection and disconnection of utilities as well as all required coordination with the relevant utility providers.

B. Within five (5) calendar days of each Delivery Order Notice to Proceed, the contractor shall submit a schedule of anticipated requirements for utility shutdowns. This schedule shall be separate from any other construction schedule otherwise required. Each shutdown shall have listed:

1. Anticipated date;

2. Approximate duration;

3. List of buildings (or parts of buildings) and other facilities affected;

4. Reason for the shutdown (work to be accomplished during the shutdown).

C. Fourteen (14) calendar days prior to each required shutdown, the contractor shall make a specific request for the shutdown. Thirty (30) days notification is required for electrical power shutdown that affects Bldgs 1607, 1435 and 1646. This request shall include the information listed above, plus requested time and duration of the shutdown.

D. Major utility shutdowns which would disrupt any building's occupants for an extended period shall be scheduled for a weekend or after the facility's normal hours of operation whenever possible.

1.10 BURNING

A. Burning of material and debris is not permitted.

1.11 SAFETY

A. The contractor shall comply with all current provisions of the Occupational Safety and Health Administration (OSHA) regulations and guidelines and the installation specific requirement and guidelines provided to the Contractor at the at the pre-construction meeting.

B. Contractor personnel shall be instructed in accident safety and prevention.

GENERAL REQUIREMENTS 01 00 00 - 3

1.12 CONTRACTOR STORAGE AREA

A. The contractor shall be allowed to store materials on base in an area designated and approved by the Government Representative. If a trailer is used, it must be clearly marked with the company name and phone number.

B. The contractor shall store materials only in locations designated or approved by the Government Representative. Open paint cans, drop cloths, rags, and similar items will be removed and stored at the end of each workday. All materials which might constitute a fire or safety hazard shall be placed in metal containers or removed at the end of each workday. The contractor shall comply with all applicable Federal, State and local laws and regulations regarding storage of hazardous materials and waste.

1.13 PHASING OF CONSTRUCTION WORK

A. The entire project area shall be made available to the contractor.

B. Work at the project site may commence immediately after the contractor receives the Notice to Proceed.

C. All material submittals are to be submitted to the Government Representative as specified in Section 01 30 00 SUBMITTALS and Section 01 33 00 SUBMITTAL

PROCEDURES.

D. Where required, the contractor shall coordinate access to the interior of a building with the Government Representative and User. At no time shall the contractor enter any room outside of the project area without specific approval from the Government Representative.

E. The contractor shall conduct his work to minimize disruption to the occupants of other portions of the base.

1.14 COORDINATION

A. Installation Sequencing:

1. Notify the Contracting Officer immediately of unsatisfactory conditions which hinder or restrict correct installation of the next stage or adjacent work.

2. Any completed work requiring subsequent removal or replacement due to unsatisfactory or defective workmanship or materials shall be done by the contractor at no expense to the Government.

B. Contract Document Review:

1. The contractor shall review all drawings and specifications and immediately report all potential errors, discrepancies, and/or omissions to the Contracting Officer in writing.

2. Design Intent:

a. Purpose of project drawings is to graphically depict characteristics and extent of project.

GENERAL REQUIREMENTS 01 00 00 - 4

b. Specifications included as part of the projects bid documents are provided to state material type, function and potential source of materials.

c. Reference standards are used in specifications to describe, by inference, specific materials and may include recommended methods of installation or application based on industry standards.

1.15 BARRIERS

A. Provide as required:

1. To prevent public entry to construction areas, including pedestrians and vehicles.

2. To protect adjacent facilities and properties from damage from construction operations.

1.16 PROTECTION OF INSTALLED WORK

A. Provide temporary protection for installed products. This may include but not be limited to the use of signs, barriers, warning tape, steel plates, etc. to protect the work site and to control vehicle and foot traffic in the immediate area so as to minimize the potential for damage.

B. On-site material stocks, etc, shall be coordinated with the Government Representative prior to starting any work under this contract.

1.17 REMOVAL

A. Remove temporary materials, equipment, services, and construction before substantial completion inspection.

B. Clean and repair damage caused by installation or use of temporary facilities.

C. Restore existing facilities used during construction to specified or original conditions.

1.18 FINAL CLEANING

A. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints, labels, and other foreign materials from sight-exposed interior and exterior surfaces.

B. Broom clean exterior paved surfaces and rake clean other surfaces of grounds.

C. Before final completion of occupancy, conduct inspection of sight-exposed interior and exterior surfaces and all work areas to verify entire work area is clean.

PART 2 - PRODUCTS

(Not Applicable)

PART 3 - EXECUTION

GENERAL REQUIREMENTS 01 00 00 - 5

3.01 BASE CIVIL ENGINEER WORK CLEARANCE REQUEST

A. At least 21 days prior to the start of any physical construction, the contractor must submit a completed Air Force Form 103 Base Civil Engineer Work Clearance Request.

B. This form is available at http://www.e-publishing.af.mil or upon request.

C. The contractor shall be responsible for all drawings, sketches, field markings, “Dig Safe” numbers, and/or documentation required to clearly identify the area of work attached to the work clearance request.

D. The Contractor shall remain the responsible agent for the coordination, completion, and approval of the work clearance request. The Project Manager will provide support of the contractor’s efforts as appropriate.

**END OF SECTION**

GENERAL REQUIREMENTS 01 00 00 - 6

SECTION 01 02 50

MEASUREMENT AND PAYMENT

PART 1 – GENERAL

1.01 RELATED SECTIONS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

B. Related Sections include the following:

1. Section 01 29 00 PAYMENT PROCEDURES for administrative procedures

2. Section 01 03 50 CONTRACT MODIFICATION PROCEDURES for handling changes to the Contract.

3. Section 01 31 00 SCHEDULES AND REPORTS for administrative requirements governing preparation and submittal of Contractor's Construction Schedule and Submittals Schedule.

1.02 GENERAL

A. This Section describes methods of measurement and payment for all Work completed under this contract.

B. Payment for all work shall be in compliance with the Contract Documents, and shall be in accordance with the accepted Schedule of Values, as described in Section 01 29 00.

Work for which there is not a separate item will be considered incidental to the contract and no additional compensation will be allowed.

C. Work: Payment shall also fully compensate the Contractor for any other work which is not specified or shown, but which is necessary to complete the Work.

1.03 LUMP SUM ITEMS

A. Payment of the lump sum shall be full compensation for all labor and materials.

1.04 MOBILIZATION

A. Payment will be made at the price shown in the bid schedule for mobilization and demobilization. This item shall include initial submittals specified in Sections 01 30 00 SUBMITTALS, all costs related to establishing construction offices for the Contractor and his Subcontractors, communications, other temporary utilities the Contractor and Subcontractors may require, and transportation of construction equipment to the site that will be utilized in the performance of the Work. Payment shall include compensation for all construction permits, and site preparation required for temporary facilities and utilities.

B. The total price for mobilization shall not exceed three percent (3%) of the Contract Price.

MEASUREMENT AND PAYMENT 01 02 50 - 1

Hanscom Air Force Base, MA

PART 2 - PRODUCTS

(Not Applicable)

PART 3 – EXECUTION

**END OF SECTION **

MEASUREMENT AND PAYMENT 01 02 50 - 2

SECTION 01 03 50

CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including other Specification Sections apply to this Section.

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections include but are not limited to the following:

1. Section 01 63 00 SUBSTITUTIONS for administrative procedures for handling requests for substitutions made after Contract award.

1.03 MINOR CHANGES IN THE WORK

A. The Government Representative will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.

1.04 PROPOSAL REQUESTS

A. Government-Initiated Proposal Requests: The Government Representative will issue a detailed description of proposed changes in the proposed revised Statement of Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by the Contracting Officer are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within seven (7) days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish

CONTRACT MODIFICATION PROCEDURES 01 03 50 - 1

Hanscom Air Force Base, MA times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

d. Indicate milestone date for required Change Order approval needed to maintain proposed updated schedule.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to the Contracting Officer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

a. Indicate milestone date for required Change Order approval needed to maintain proposed updated schedule.

5. Comply with requirements in Section 01 63 20 PRODUCTS if the proposed change requires substitution of one product or system for product or system specified.

1.05 CHANGE ORDER PROCEDURES

A. Upon the Government's approval of a Proposal Request, the Contracting Officer will issue a Change Order to the contractor for signature indicating their acceptance of the associated terms and conditions.

1.06 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: The Contracting Officer may issue a Construction Change Directive. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work.

It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

CONTRACT MODIFICATION PROCEDURES 01 03 50 - 2

Hanscom Air Force Base, MA

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

CONTRACT MODIFICATION PROCEDURES 01 03 50 - 3

SECTION 01 04 00

PROJECT COORDINATION

1.01 SUMMARY

A. The information of this section is for summary of submittal requirements only and not inclusive. Specified requirements are as indicated in the referenced technical specification sections.

1.02 DESRIPTION OF WORK

A. This section specifies general administrative procedures and performance required, including but not limited to the following:

1. Coordination and meetings

2. Administrative/supervisory personnel

3. Surveys and records or reports

4. Limitations for use of site

5. Special reports

6. Trades people and workmanship standards

7. Inspections test and reports

8. Overtime work, suspension of work

9. General installation provisions

10. Cutting and patching

11. Cleaning and protection

12. Environmental protection

13. Requests for Information (RFI)

1.03 COORDINATION AND MEETINGS

A. General: Prepare and distribute to each entity performing work at project site, a written memorandum of instructions on required coordination activities, including required notices, reports and attendance meetings. Prepare similar memorandum for separate contractors where interfacing of work is required.

PROJECT COORDINATION 01 04 00 - 1

Hanscom Air Force Base, MA

B. Coordination drawings: Refer to clause “Shop Drawings, Coordination Drawings, and Schedules,” of “Contract Clauses,” for general requirements.

1. Work by Separate Entities: Where work by separate entities requires off-site fabrication of products and materials which must be accurately interfaced and closely intermeshed to produce required results, prepare coordination drawings to indicate how work shown on separate shop drawings will be interfaced, intermeshed, and sequenced for installation. Comply with submittal requirements of Section 01 30 00 SUBMITTALS.

2. Sleeves and Inserts: Before any sleeves or inserts are set or any mechanical or electrical equipment or foundations or other work is installed, the contractor shall prepare and submit for approval by the Government Representative composite coordination drawings for all equipment rooms, spaces and other areas in which work of two or more trades or subcontractors is to be installed and in which the probability of interface exists, as determined by either the contractor or the Government Representative. Drawings shall show work of all trades covered, shall be drawn to a scale no smaller than ½” = 1’-0”, and shall clearly illustrate in both plan and elevation that all work can be installed without interference.

3. Work installed without prior approval: Work installed prior to approval of coordination drawings shall be at the Contractor’s risk. Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government Representative will decide which work shall be relocated regardless of which was installed first.

C. Coordination of Trades: Coordinate work of different trades so that interference between mechanical, electrical, architectural, and structural work, including existing services, will be avoided and within limits indicated the maximum practical space for operation, repair, removal, and testing of equipment is provided. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to minimize the space affected. Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices.

D. Preconstruction Meeting: the Government Representative will conduct a meeting to discuss administrative procedures with the contractor which will be scheduled to occur between the Contract Award and Notice to Proceed. See Section 01 52 50 SAFETY REQUIREMENTS for requirements of preconstruction safety meeting.

E. Weekly Coordination Meeting: In addition to specific preinstallation meetings and coordination meetings for each major element of work, and regular project meetings for other purposes (as indicated elsewhere in the contract documents), weekly or as required by the Government Representative, schedule general project coordination meetings at regular scheduled times which are convenient for everyone involved. Request representation at each meeting by every entity currently involved in coordination or planning for work of the entire project. Conduct meetings in a manner which will resolve coordination problems. Record results of meetings and distribute meeting minutes to everyone in attendance and to others affected by decisions or actions resulting from each meeting.

1.04 ADMINISTRATIVE/SUPERVISORY PERSONNEL

PROJECT COORDINATION 01 04 00 - 2

Hanscom Air Force Base, MA

A. General: In addition to a General Superintendent and other administrative and supervisory personnel required for performance of the work, provide specific coordinating personnel as specified herein.

B. Environmental Control Officer: The Contractor shall designate an “Environmental Control Officer” whose duties shall include responsibility for enforcing the environmental protection provisions of these specifications including safety and health; the requirements of the Occupational Safety and Health Act; the requirements of the Occupational Safety and Health Act, and other applicable Federal, state and local standards. As outlined in the applicable sections of this specification, submit for approval by the Government Representative the proposed traffic flow plan, security plan, program for temporary structures, housecleaning plan, erosion control plan, demolition program, and safety and health plan. After approval of the Government Representative, the implementation and enforcement of these programs shall become the responsibility of the Environmental Control Officer. Any changes in the programs must be requested by the Contractor’s Environmental Control Officer for written concurrence by the Government Representative.

C. Project Coordinator: Provide a full time Project Coordinator, who is experienced in administration and supervision of site and building construction (including mechanical and electrical work), and who is hereby authorized to act as the general coordinator of interfaces between units of work. For purpose of this provision, “interface” is defined to include the scheduling and sequencing of work, sharing of access to work spaces, installations, protection of each trades work, cutting and patching, tolerances, cleaning, selections for compatibility, preparation of coordination drawings, inspections, test, and temporary facilities and services.

D. Submittal of Project-Related Staff Names and Duties: Within fifteen (15) days of the Notice to Proceed, submit a listing of Contractor’s principal staff assignments and consultants, naming persons and listing their address and telephone numbers.

1.05 LIMITATIONS FOR USE OF SITE

A. General: In addition to site utilization limitations and requirements shown on the drawings, and indicated by other contract documents, administer allocation of available space equitably among entities needing access and space so as to produce the best overall efficiency in performance of total project work. Schedule deliveries so as to minimize space and time requirements for storage of materials and equipment on site.

B. Use of Equipment by Government: See “General Conditions.”

C. Vacation of Premises: The Government will vacate the premises during the performance of work under the contract. Spaces beyond the limit of work shall be considered occupied.

D. Parking facilities: Except as noted or specified, there will be parking available at the site during normal working hours. The Contractor shall confirm arrangements for vehicle parking with the Government Representative. Parking for Contractor vehicles will be permitted, when prior arrangements are made, in a general area as designated by the Government Representative, not in reserved parking spaces.

E. Loading Dock Facilities: Confirm availability of loading dock and staging facilities with the Government Representative.

PROJECT COORDINATION 01 04 00 - 3

F. Materials on Site: Materials and equipment that are removed and not reused or salvaged under this contract shall be disposed of as required by applicable law and statues, unless otherwise noted or specified.

G. Storage or Sale of Equipment on Site: Storage or sale of excess salvageable material on the site is not permitted. Remove from site.

1.06 SPECIAL REPORTS

A. General: Except as otherwise indicated, submit special reports to the Contracting Officer within one day of occurrence requiring special report, with copy to others affected by occurrence.

B. Reporting Accidents: Refer to Section 01 52 50 SAFETY REQUIREMENTS.

C. Reporting Unusual Events: When an event of unusual and significant nature occurs at the site (examples: visit by news media; extraordinary weather phenomenon), prepare and submit a special report listing chain of events, persons participating, response by Contractor’s personnel, evaluation of results or effects, and similar pertinent information.

When such events are known or predictable in advance, advise Contracting Officer in advance at the earliest possible date.

1.07 TRADESPERSONS AND WORKMANSHIP STANDARDS

A. General: Initiate and maintain procedures to ensure that persons performing work at the site are skilled and knowledgeable in methods of craftsmanship needed to produce required quality levels for workmanship in completed work. Remove and replace work which does not comply with workmanship standards as specified and as recognized in the construction industry for applications indicated. Remove and replace other work damaged or deteriorated by faulty workmanship or its replacement.

B. Availability of Tradespersons: At each progress or coordination meeting, review availability of tradespersons and projected needs to accomplish work as scheduled.

Require each entity employing personnel to report on events which might affect the progress of work. Where possible, consider alternatives and take actions to avoid disputes and delays.

1.08 INSPECTIONS, TEST AND REPORTS

A. General: Required inspection and testing services are intended to assist in determination of probable compliances of work with requirements, but do not relieve Contractor of responsibilities for those compliances, or for general fulfillment of requirements of the contract documents. Specified inspections and test are not intended to limit Contractor’s quality control program. Afford reasonable access to agencies performing test and inspections.

B. Qualification of Testing Agencies: Except as otherwise indicated and except where manufacturer’s testing facilities are indicated as acceptable, engage independent testing laboratories specialized in required services and acceptable to the Government Representative.

PROJECT COORDINATION 01 04 00 - 4

C. Reports: Refer to Section 01 30 00 SUBMITTALS and Section 01 44 00 CONTRACTOR

QUALITY CONTROL.

1.09 ENVIRONMENTAL PROTECTION

A. The work of this section consist of furnishing all labor, materials and equipment and performing all work required for the prevention of environmental pollution during and as a result of construction operations under this contract. Environmental pollution is defined as the presence of chemical, physical or biological elements or agents which can adversely affect human health or welfare, or unfavorably alter ecological balances of importance to human kind. The control of environmental pollution requires consideration of air, water and land.

1.10 APPLICABLE REGULATIONS

A. In order to prevent and to provide for abatement and control of any environmental pollution arising from construction activities, the Contractor and their subcontractors in the performance of this contract, shall comply with all applicable Federal, State and local laws and regulations concerning environmental pollution control and abatement.

1.11 NOTIFICATIONS

A. The Contracting Officer will notify the Contractor in writing of any noncompliance with foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or the authorized representative at the site of work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop order shall be made the subject of any claim for extension of time or for excess cost or damage by the Contractor.

1.12 SUBCONTRACTORS

A. Compliance of the provisions of this section by subcontractors will be the responsibility of the Contractor.

1.13 IMPLEMENTATION

A. Prior to commencement of the work the Contractor shall submit in writing for approval, proposals for implementing this section for environmental pollution control. The Contractor shall meet with the Government Representative to develop a mutual understanding relative to compliance with the provisions and administration of the environmental pollution control program.

PART 2 - MATERIALS

PART 3 - EXECUTION

3.01 GENERAL INSTALLATION PROVISIONS

PROJECT COORDINATION 01 04 00 - 5

A. Pre-Installation Conferences: Where preinstallation conferences are specified in technical sections, well in advance of installation meet at project site with installers and representatives of manufacturers and fabricators who are involved in or affected by unit of work, and its coordination or integration with other work which has preceded or will follow.

Advise the Government Representative of scheduled meeting dates. At each meeting review progress of other work and preparations for particular work under consideration, including requirements of contract documents, options, related change orders, purchases, deliveries, shop drawings, product data; quality control samples, possible conflicts, compatibility problems, time schedules, weather limitations, temporary facilities, space and access limitations, structural limitations, governing regulations, safety, inspection and testing requirements, required performance results, recording requirements, and protection.

The Contractor shall record significant discussions of each conference, record agreements and disagreements, along with the final plan of action.

Distribute record of meeting promptly, but no later than five (5) working days of initial meeting, to everyone concerned.

1. Do not proceed with the work if associated preinstallation conference cannot be concluded successfully. Instigate actions to resolve impediments to performance of the work, and reconvene conference at earliest date feasible.

B. Installer’s Inspection of Conditions: Require installer of each major unit of work to inspect substrate to receive work, and conditions under which work will be performed, and to report (in writing to the Contractor) unsatisfactory conditions. Do not proceed with the work until unsatisfactory conditions have been corrected in a manner acceptable to the installer.

C. Manufacturer’s Instructions: Where installations include manufactured products, comply with manufacturer’s applicable instructions and recommendations for installation, to extent that these are more explicit or more stringent than requirements indicated in the contract documents.

D. Inspect each item of materials or equipment immediately prior to installation, and reject damaged and defective items.

E. Install work during conditions of temperature, humidity, exposure, forecasted weather, and status of project completion which will ensure best possible results for each unit of work, in coordination with entire work. Isolate each unit of work from non-compatible work, as required to prevent deterioration.

F. Coordinate enclosure (closing-in) of work with required inspections and test, so as to minimize necessity of uncovering work for that purpose.

G. Mounting Heights: Where mounting heights are not indicated, mount individual units of work at industry recognized standard mounting heights for applications indicated. Refer questionable mounting height choices to the Government Representative for final decision.

3.02 Cutting and patching

A. General: Do not cut-and-patch structural work in a manner resulting in reduction of load carrying capacity or load/deflection ratio; submit proposed cutting and patching to the Government Representative for structural approval before proceeding. Do not cut-and

PROJECT COORDINATION 01 04 00 - 6

Hanscom Air Force Base, MA patch operational elements and safety related components in a manner resulting in reduction of capacities to perform in a manner intended or resulting in decreased operation of life, increased maintenance, or decreased safety.

1. Engage original Fabricator/Installer to perform cutting-and-patching of structural work, operational/safety related components, and visually exposed work; or if not available, engage only recognize experts; employ only proven methods.

B. Materials: Except as otherwise indicated or approved by the Government Representative, provide materials for cutting-and-patching which will result in equal or better work than being cut-and-patched; in terms of performance characteristics and including visual effect where applicable. Use materials identical to original materials where feasible and where recognized that satisfactory results can be produced.

C. Temporary Support and Protection: Provide adequate temporary support for work to be cut, to prevent failure. Do not endanger other work. Provide adequate protection of other work during cutting and patching, to prevent damage; and provide protection of the work from adverse weather exposure.

D. Cut work by methods least likely to damage work to be retained and adjacent work.

E. Patch with methods which are durable and as invisible as possible. Comply with specified tolerances for the work.

F. Restore exposed finishes of patched areas; and, where necessary extend finish restoration onto retained work adjoining, in a manner which will eliminate evidence of patching. Where patch occurs in a painted surface, extend paint coats over entire unbroken surface containing patch.

3.03 CLEANING AND PROTECTION

A. General: During handling and installation of work at project site clean and protect work in progress and adjoining work on a basis of perpetual maintenance. Apply suitable protective covering on newly installed work where reasonably required to ensure prevention of damage or deterioration; otherwise, clean and perform maintenance on newly installed work as frequently as necessary through remainder of construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

B. Limiting Exposures of Work: To extent possible through reasonable control and protection methods, supervise performance of work in a manner and by means which will ensure that none of the work, whether completed or in progress, will be subjected to harmful, dangerous, damaging, or otherwise deleterious exposures during construction period. Such exposures include (where applicable, but not by way of limitation) static loading, dynamic loading, humidity, air contamination or pollution, water, ice, solvents, chemicals, light, radiation, puncture, abrasion, heavy traffic, soiling, bacteria, insect infestation, combustion, electrical current, high speed operation, improper lubrication, unusual wear, misuse, incompatible interface, destructive testing, misalignment, excessive weathering, unprotected storage, improper shipping/handling, theft and vandalism.

3.04 ENVIRONMENTAL PROTECTION

PROJECT COORDINATION 01 04 00 - 7

Hanscom Air Force Base, MA

A. Solid, Liquid and Gaseous Contaminants: Contractor shall be responsible for the proper handling and disposal of all solid, liquid, and gaseous contaminants in accordance with all local codes and regulations, together with the following requirements:

1. Liquid contaminants shall be contained in approved vessels for disposal at approved sites.

B. Disposal of Refuse: Remove refuse resulting from construction operations from the site.

The site shall be cleaned daily. Rubbish must be stored in covered containers or removed from the site each night.

C. Trucking: Load all trucks leaving the site with earthen materials or loose debris in a manner that will prevent dropping of materials on streets. Fasten suitable tarpaulins over the load before they enter surrounding paved streets. Trucking materials over paved streets to the site shall be similarly loaded and covered. The Contractor shall conform to all local regulations regarding load limitations and use.

D. Construction Site Maintenance: Store all supplies and equipment on the project site so as to preclude mechanical and climatic damage. Maintain site in a neat and orderly manner. The Contractor shall be responsible for maintaining the temporary structures and construction enclosure in good repair and visually pleasant condition. The Contractor shall provide adequate security to prevent the presence of unauthorized persons on the site, and to keep gates or doors secured when not in actual use to insure the integrity of the barrier as well as the property security.

E. Noise Control: Comply with applicable state and local laws, ordinances, and regulations relative to noise control.

3.05 REQUESTS FOR INFORMATION (RFI)

A. Requests for Information (RFI’s) should be submitted to the Contracting Officer by the Contractor in any events that include, but are not limited to, where a clarification of the contract documents is required, where additional information or direction is required for the execution of the work, or where an unforeseen problem arises.

B. The RFI package should be in writing and include a concise description of the question or problem, and, if necessary, a suggested resolution, potential costs and any additional time requirements.

C. The Contracting Officer shall review the RFI and respond to the Contractor in writing no more than seven (7) calendar days from receipt of the request. The response shall include clarification as necessary to address the Contractors questions and/or concerns. In the event that a review of the RFI yields the finding that change to the contract may be required, the Contractor will be directed to proceed with the formal contract modification process outlined in Section 01 03 50 CONTRACT MODIFCATION PROCEDURES.

PROJECT COORDINATION 01 04 00 - 8

SECTION 01 09 00

DEFINITIONS AND STANDARDS

1.01 DEFINITIONS:

A. General Explanation: A substantial amount of specification language consists of definitions of terms found in other contract documents, including drawings. (Drawings are recognized as being diagrammatic in nature and not completely descriptive of requirements indicated thereon). Certain terms used in contract documents are defined in this article.

Definitions and explanations contained in this section are not necessarily either complete or exclusive, but are general for the work to the extent that they are not stated more explicitly in another element of contract documents.

B. Special Conditions: Wherever the term "Special Conditions" or "Section, Special Conditions" is used in the specifications, it refers collectively to all of the sections in Division 1, General Requirements, and to any other “Special Conditions” so defined in the Contract Documents.

C. Indicated: The term "Indicated" is a cross-reference to graphic representations, notes or schedules on drawings, to other paragraphs or schedules in the specifications, and to similar means of recording requirements in contract documents. Where terms such as "shown", "noted", "scheduled", and "specified" are used in lieu of "indicated", it is for purpose of helping reader locate cross-reference, and no limitation of location is intended except as specifically noted.

D. Directed, Requested, etc.: Where not otherwise explained, terms such as "directed", "requested", "authorized", "selected", "approved", "required", "accepted", and "permitted" mean "directed by the Government Representative", "requested by the Government Representative and similar phrases. However, no such implied meaning will be interpreted to extend the Government Representative’s responsibility into Contractor's area of construction supervision.

E. Approve: Only the Contracting Officer, or an individual designated by them in writing, can approve or disapprove contract actions. Even if the specifications indicate that an individual other than the Contracting Officer (such as the "Architect" or "Construction Engineer") will approve or disapprove an action, it is understood that only the Contracting Officer has this authority unless the individual is so designated by them in writing. Even when an individual is so designated, the Contractor may appeal the action to the Contracting Officer and the Contracting Officers’s decision shall be final. In no case will "approval" by the Government Representative be interpreted as a release of the Contractor from responsibility to fulfill requirements of contract documents.

F. Government Representative: A government employee, or contracted consultant, assigned to manage activities for the Government during the course of the project.

G. Contracting Officer: A government employee with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

DEFINITIONS AND STANDARDS 01 09 00 - 1

Hanscom Air Force Base, MA

H. Project Area: The space available to Contractor for performance of the work, either exclusively or in conjunction with others performing other work as part of the project. The extent of project area is shown on drawings.

I. Furnish: Except as otherwise defined in greater detail, term "furnish" is used to mean supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, etc., as applicable in each instance.

J. Install: Except as otherwise defined in greater detail, term "install" is used to describe operations at project site including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations, as applicable in each instance.

K. Provide: Except as otherwise defined in greater detail, term "provide" means furnish and install, complete and ready for intended use, as applicable in each instance.

L. Installer: The term "Installer" is defined as the entity (person or firm) engaged by the Contractor or its subcontractor or sub-subcontractor for performance of a particular unit of work at the project site, including installation, erection, application and similar required operations. Installers shall be skilled in the work they are to perform.

M. Specialist: The term "Specialist" means an individual or firm of established reputation (or, if newly organized, whose personnel have previously established a reputation in the same field), which is regularly engaged in, and which maintains a regular force of workmen skilled in either (as applicable) manufacturing or fabricating items required by the contract, installing items required by the contract, or otherwise performing work required by the contract. Where the contract specification requires installation by a specialist, that term shall also be deemed to mean either the manufacturer of the item, an individual or firm licensed by the manufacturer, or an individual or firm who will perform the work under the manufacturer's direct supervision.

N. Testing Laboratory: The terms "testing laboratory" or "independent laboratory" are interchangeable, and are defined as an independent entity engaged by the Contractor to perform specific inspections or tests of the work, either at project site or elsewhere; and to report results of those inspections or tests.

O. Nationally Recognized Testing Laboratories: The term "nationally recognized testing laboratory (NRTL)" shall mean a firm or organization which is recognized by OSHA in accordance with 29 CFR Part 1910.7 to test and approve (i.e., certify, label or list) equipment or materials as being…