RFP Fiber Amended.pdf

PDF 122 KB Posted

Attached to
Fiber Installation for C-64D Federal contract opportunity
Solicitation number
FA282322Q0012
Issued by
Department of the Air Force Materiel Command Test Center

View the file

Other files for this federal contract opportunity

Other files attached to Fiber Installation for C-64D, newest first.
File Type Posted
Attachment 12 Proposed Floor Plan.pdf PDF
Attachment 14 Proposed Comm Room Details.pdf PDF
Solicitation Amendment FA282322Q00120004 SF 30.pdf PDF
Attachment 13 Proposed Site Plan.pdf PDF
Attachment 15 Questions and Answers 5.11.22.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120002 SF 30.pdf PDF
Attachment 10 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended 5.2.22.pdf PDF
Attachment 11 Questions and Answers 05.02.22 22Q0012.pdf PDF
Solicitation Amendment FA282322Q00120001 SF 30.pdf PDF
Attachment 9 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 3 Addendum to FAR 52 212-2 Amended 4.27.22.pdf PDF
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended.pdf PDF
Attachment 6 Design Guide.pdf PDF
Attachment 9 Base Access Memo.pdf PDF
Attachment 8 WD 2015-4531 R19 3.15.22.txt TXT text file
Attachment 2 Addendum to FAR 52 212-1 and-3.pdf PDF
Attachment 4 PWS 3.3.pdf PDF
Attachment 1 Cover_Sheet.pdf PDF
Attachment 7 Dec 2021 Reps Certs.pdf PDF
Solicitation - FA282322Q0012.pdf PDF
Attachment 5 90percent Design Drawings 2020.pdf PDF
Attachment 3 Addendum to FAR 52 212-2 (NOV 2021).pdf PDF
Attachment SVL.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

NETWORK OPERATIONS & INFRASTRUCTURE SOLUTION

(Site C-64) LRSF Fiber Optic Cable installation

The contractor shall provide all equipment, parts, tools, and labor to engineer, furnish, install and test. The Project is for the installation of a 144SM FOC to a distribution hand-hole by new LRSF facility being built on range C-64. A 24 strand fiber will be spliced and installed / terminated in the LRSF from the distribution hand-hole. The 144SM FOC will be installed in an existing 2-Way 4” Manhole Duct system from B9620 to new facility being built 1.37 miles east of B9620. This project is required for communication capabilities to AFRL personnel. The Contractor shall engineer, furnish, install and test (EFI&T) the following requirement. All equipment, supplies, and materials provided shall be new and not refurbished. Period of performance shall be 180 calendar days.

This RFP is not authorization to begin performance, and in no way obligates the Government for any costs incurred by the contractor for this requirement. The Government reserves the right not to award a task order in response to this RFP. Prior to commencement of any activities associated with performance of this requirement, the Government will issue a written directive or contractual document signed by the Contracting Officer with appropriate consideration established.

This procurement will be a 100% Small business Set Aside.

RECOMMENDED SITE VISIT INFORMATION

Email stephanie.aiken@us.af.mil to RSVP for the site visit by 22 April 2022 NLT 11:59 PM Central Time. If personnel have a CAC or access to base, then send the name and personal contact information (Cell Phone) only in the RSVP and specify they already have access. If your personnel need a base pass, please send their name, birth date, and personal contact information (Cell Phone). Upon receipt of list of names, birth dates, and contact information (cell phone), the Contract Specialist will submit the information to Security Forces, which takes approximately 3-5 days for approval.

The site visit is scheduled for 4 May 2022 at 9:00 AM Central Time. The site visit will begin at building B9620 Site C-64ABC Range Rd 213. Personnel needing a pass should report to the West Gate (Shalimar near Hospital) Visitor Center with picture ID. If you need directions once on base, please contact the Contract Specialist.

DEADLINE INFORMATION

Questions regarding this RFP are due no later than 4 May 2022 NLT and shall be submitted to the Contract Specialist, Stephanie Aiken, at stephanie.aiken@us.af.mil

Delivery Terms are FOB Destination with delivery to Eglin AFB, FL.

Period of Performance is as follows: 180 Days ADC

The following attachments/documents are provided for preparation of a proposal and access to the site visit:

1. Removed

2. Addendum to 52.212-1&3

3. Addendum to 52.212-2

4. Performance Work Statement 3.3.22

5. 90% Design Drawings

6. 96 CS Design Guide

7. Dec 2021 Reps and Certs

8. Wage Determination 2015-4532 REV 19 mailto:stephanie.aiken@us.af.mil

REQUEST FOR PROPOSAL

NETWORK OPERATIONS & INFRASTRUCTURE SOLUTION

9. Request for Base Pass Memo

10. Offeror Schedule

This procurement will be a 100% Small business Set Aside. RECOMMENDED SITE VISIT INFORMATION