Attachment 4 PWS 3.3.pdf

PDF 854 KB Posted

Attached to
Fiber Installation for C-64D Federal contract opportunity
Solicitation number
FA282322Q0012
Issued by
Department of the Air Force Materiel Command Test Center

View the file

Other files for this federal contract opportunity

Other files attached to Fiber Installation for C-64D, newest first.
File Type Posted
Attachment 14 Proposed Comm Room Details.pdf PDF
Solicitation Amendment FA282322Q00120004 SF 30.pdf PDF
Attachment 13 Proposed Site Plan.pdf PDF
Attachment 15 Questions and Answers 5.11.22.pdf PDF
Attachment 12 Proposed Floor Plan.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120002 SF 30.pdf PDF
Attachment 10 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended 5.2.22.pdf PDF
Attachment 11 Questions and Answers 05.02.22 22Q0012.pdf PDF
Attachment 3 Addendum to FAR 52 212-2 Amended 4.27.22.pdf PDF
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended.pdf PDF
RFP Fiber Amended.pdf PDF
Solicitation Amendment FA282322Q00120001 SF 30.pdf PDF
Attachment 9 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 2 Addendum to FAR 52 212-1 and-3.pdf PDF
Attachment 1 Cover_Sheet.pdf PDF
Attachment 7 Dec 2021 Reps Certs.pdf PDF
Solicitation - FA282322Q0012.pdf PDF
Attachment 5 90percent Design Drawings 2020.pdf PDF
Attachment 3 Addendum to FAR 52 212-2 (NOV 2021).pdf PDF
Attachment SVL.pdf PDF
Attachment 6 Design Guide.pdf PDF
Attachment 9 Base Access Memo.pdf PDF
Attachment 8 WD 2015-4531 R19 3.15.22.txt TXT text file
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement 6 RTB IASO/IMO (Bldg. 6006) Project Eglin AFB, FL

(Site C-64) LRSF Fiber Optic Cable installation Project Eglin AFB, FL

3 March 2022

Performance Work Statement

Name: Mr. Ken Coleman

Organization: 96 CS/SCXP

Address: 101 Griffin Way Eglin AFB, FL 32542 Building 1425 Room 131

Executive Summary

The Project is for the installation of a 144SM FOC to a distribution hand-hole by new LRSF facility being built on range C-64. A 24 strand fiber will be spliced and installed / terminated in the LRSF from the distribution hand-hole. The 144SM FOC will be installed in an existing 2-Way 4” Manhole Duct system from B9620 to new facility being built 1.37 miles east of B9620. This project is required for communication capabilities to AFRL personnel. The Contractor shall engineer, furnish, install and test (EFI&T) the following requirement. All equipment, supplies, and materials provided shall be new and not refurbished. Period of performance shall be 180 calendar days.

PWS

1. SCOPE

SCOPE. This PWS defines the requirements for the Telecommunications Contractor to engineer, furnish, install and test (EFI&T) a 144SM FOC from building 9620 to a distribution hand-hole by the new LRSF facility and a 24 SM FOC from the distribution hand-hole to the new LRSF facility. Phase One (CLIN 0001) will include the design. Phase two (CLIN 0002) the contractor shall install, splice, terminate and test the fiber cable to support the new LRSF building per this PWS. Phase three (CLIN 0003) will be the deliverables for this contract per this PWS. The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, On-site quality assurance, management, and other incidentals necessary to meet the requirements as stated in this PWS. All equipment, supplies, and materials provided shall be new and not refurbished.

2. REQUIREMENTS

2.1. GENERAL REQUIREMENTS

2.1.1. Safety Requirements

2.1.2. Site Coordination The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.

2.1.2.1. Confined Space

2.1.2.2. The Contractors and Sub-contractors entering spaces on Eglin AFB are responsible for the safety of their personnel and for their own permit space program as outlined in OSHA 1910.146 and AFI 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.

2.1.2.3. Accident/Incident Reporting and Investigation

The Contractor shall record and report all available facts relating to each instance of injury to the Base Safety Office. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.2.4. Work Area(s)

At day’s end, the Contractor shall remove all debris and surplus materials from the work place.

Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. Contractor shall be responsible for containing any dust or debris that may be exuded during construction work that could affect the existing electronic equipment in the existing communications racks in building 9620. Contractor shall ensure dust protection materials for electronic equipment will be situated in a manner that will not suffocate or cause the electronic equipment to overheat.

2.1.2.5. Traffic control

In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall make appropriate notifications NLT 14 calendar days in advance to 96 CS/SCXP of the planned disruptions.

2.1.3. Security Requirements

The Contractor shall process and provide a Site Visit Request Letter to 96 CS/SCXP within 5 calendar days after contract award. This spreadsheet shall identify the names ( as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this PWS, company name, address, phone number and contract number, start date and end date. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

2.1.3.1. Security Clearances

Stated work and associated products shall be performed at the UNCLASSIFIED level. However, if some of this work will take place in secure areas, Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least 24 hours ahead of time with the 96 CS/SCXP program manager. It is the Government's responsibility to provide escorts.

2.1.4. Environmental Compliance

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Eglin AFB.

2.1.5. Permits

The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole or hand-hole. For example:

- Work Clearance Request “Digging permit”, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.

- Confine space entry permit, AF Form 1024 shall be coordinated through base safety office.

The Contractor shall be prepared to provide proof of their Confined Space Training Program along with the AF Form 1024 to base safety.

- Base Civil Engineering Work Clearance Request, AF Form 332 shall be submitted through BCE 14 calendar days in advance of planned work.

NOTE: The contractor shall maintain all utility markings (flags, paint etc.) after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage. (See 96 CS Design Guide for specifics)

2.1.6. Integrated Process Team (IPT)

The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the 96 CS/SCXP Project Manager (PM), and other base personnel as required. The Contractor shall provide an agenda and a worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees. (CDRL A004)

2.1.7. Quality Assurance

The Contractor shall provide On-site Quality Assurance Support for the life of the project. The Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and /or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.

(CDRL A003)

2.1.8. Contractor Personnel

2.1.8.1. Project Management

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.

2.1.8.2. Site Point of Contact (POC)

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

2.1.8.2.1. Project Engineer

The Contractor shall provide a BICSI certified RCDD or equivalent engineer on staff during the duration of the project.

2.1.8.3. Personnel Requirements

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English. All reporting and documentation shall be in English.

2.1.9. Electronic Contractor Manpower Reporting Application (ECMRA)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Eglin AFB 24 strand, single mode (SM) fiber optic cable (FOC) from Building 6069 to Building 6006. The contractor is required to completely fill in all required data fields using the following web address http://www.ecmra.mil. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September

30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the ECMRA help desk.

2.1.10. Warranty

The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty.

The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2.2. SPECIFIC REQUIREMENTS

The Contractor shall engineer, furnish, install and test (EFI&T) the following requirement in a three phased approach. Phase One (CLIN 0001) the contractor must engineer and submit a design to 96CS/SCXP. Once reviewed and accepted by 96 CS/SCXP, Phase Two (CLIN 0002) installation may begin.

After Phase Two is complete, Phase Three (CLIN 0003) may begin as stated in this PWS.

The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this PWS. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards (Current Time of Design). All equipment, supplies, and materials provided shall be new and not refurbished:

In brief. The Contractor shall conduct an in-brief with the site POC or designated representative and other site personnel before the start of implementation. The in-brief shall familiarize the customer with the purpose of the Contractor's visit and coordinate the project schedule (e.g.

arrange for required escorts; Base POC schedule; etc.).

Out-brief. The Contractor shall conduct an out brief with the site POC or designated representative and other site personnel at the conclusion of the implementation. The implementation out-brief shall inform the customer of implementation results and necessary maintenance issues.

Site Survey. The contractor shall start project with an engineering/design phase. Interior and exterior telecommunications infrastructure shall be design by a Register Communications Distribution Designer using current industry standards (Current time of Design). After completing, a comprehensive rod and rope survey a design package shall be submitted to and review conducted with the 96 CS/SCXP for approval. (CDRL A007)

- Design Package shall include Site survey findings/details in word format

- Rack elevation drawings and As‐built drawings IAW 96th Communications Squadron Cyber

Infrastructure Design Guide

- LOM and product submittals for review and approval by the 96CS/SCOW.

2.2.1. Maintenance Holes (MHs)

The Contractor shall pump out water as required. Water shall be drained IAW BCE and base environmental requirements.

2.2.2. Measurements

Any distances provided in this PWS are approximations and should NOT be used for ordering materials or determining duct lengths.

2.2.3. Splice Conductors and Fiber Strands

All fiber splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable. The fusion splice method shall be used for all splicing and terminations of fiber optic cable. Fiber optic cables shall be terminated via fusion splice to LC cassette pigtails. As per 96th Communications Squadron Cyber Infrastructure Design Guide Dated February 2020 section 2.2.9. Fiber Optic Distribution Panels.

Note: If any contract requires that existing dark fiber strands are to be spliced to as part of the work being provided, then the contractor shall be responsible to test the strands that they are splicing into as well as the entire strand count of the strands housed in the existing splice case.

Example: If the requirement is to splice into 12 existing dark strands of fiber located in MH-X 144L8.3F, 1-132+A:133-144 then strands 133 to 144 shall be tested from the beginning (ITB) to the end building node in both directions. Since strands 1-, 132 are enclosed in the same splice case then strands 1-132 shall be tested using an OTDR in at least one direction from the ITB toward the end building node(s). Clarification on this requirement can be provided by 96 CS /SCOW personnel upon request.

2.2.4. Cable Racks and Cable Rack Supports

Cable racks shall be installed in Maintenance Holes as required – this includes new and existing Maintenance Holes. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.

2.2.5. Labeling

The Contractor shall label all equipment and cables they install and cables identified for re-use IAW TIA-606-B-2012, ANSI/TIA 606-C-2017 and as directed by the base communications organization. New ducts shall be permanently labeled on the wall of each building/Maintenance Hole indicating the connecting building/Maintenance Hole at the other end of the duct (for example, “To MH-200”). Tagging and labeling of new cables shall be IAW the following:

A48L8.3F

FO 1234-5678, 1-12

Line One: A = Armored Sheath (otherwise leave blank) 48 = Fiber Count. L = Loose Tube Buffer or T = Tight Tube Buffer. 8.3 = Single Mode. F = Filled core (otherwise leave blank).

Line Two: 1234-5678 = From-To Building numbers. 1-12 = Cable/strand Count.

2.2.6. Cable Tags

All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all Maintenance Holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a Maintenance Hole a tag will be placed on the cable approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. See Para 2.2.5 (above) for nomenclature for tagging.

2.2.7. Pulling Tape

All newly installed ducts left vacant shall be provided with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the Maintenance Holes and be secured to a cable rack or pulling iron, etc.

2.2.8. Cable Terminations

Fiber optic cables shall be terminated via fusion splice to splice cassettes with LC connectors.

The pigtails shall be sized the same as the OSP fiber they are spliced to, i.e., 125/8.3 micron to 125/8.3 micron. The pigtails shall be duplex (or simplex) unless otherwise agreed to by 96

CS/SCXP.

2.2.9. FOC Maintenance Loop(s)

The Contractor shall install a minimum of a 50 foot fiber optic cable maintenance loop at the first Maintenance Hole from the building, at every splice point Maintenance Hole location and at every 3rd Maintenance Hole in the route. The maintenance loop slack shall be properly labeled, securely supported to the cable ladder and off the Maintenance Hole floor.

2.2.10. New Maintenance Holes

Maintenance Holes (MHs) installed under this contract shall have an American Association of State Highway and Transportation Officials (AASHTO) rating of H-20 or equivalent. As stated in this PWS, MHs shall have minimum interior dimensions of 3 feet W x 5 feet L x 4 feet H (Width, Length, and Height), unless identified in PWS. MHs shall be furnished with a lockable MH cover, ladder, cable racks hardware, pulling irons, a sump, water resistance gaskets, bonding ribbon and a grounding system. MH shall meet the requirements of TIA-758-B, paragraph 4.2.1.

MH covers shall be labeled with 1/8 inch raised letters stating “COMMUNICATIONS”.

Maintenance Holes shall be pre-cast reinforced concrete, splayed, multi-directional type with cast-in multiple plastic terminators to accept the conduits. Thin concrete knockout sections may be provided for terminating multiple-bore conduits. Furnish with cable racks and sump with drain.

Maintenance holes shall be equipped with torsion assisted rectangular diamond plate covers and self-latching stainless steel slam locks. Polymer concrete (i.e., Quazite) construction is NOT authorized. Coordinate numbering/labeling of new MH with 96 CS/SCOW.

2.2.11. Grounding

Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.

necessary to properly bond/ground the cable in MHs shall be provided by the Contractor.

Reference ANSI/TIA 607-C-2017.

2.2.12. Underground Conduit System

The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. The Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Directional drilling shall be used for major road crossings, taxiways, runways, etc. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces (i.e., concrete encasement).

2.2.12.1. Composition.

2.2.12.1.1. Typical Situations

The ducts shall be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell-end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.

2.2.12.1.2. Unique/Site Specific Situations

The ducts shall be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-80-PVC (Schedule 80) IAW NEMA TC-2; high density polyethylene (HDPE) SIDR 13.5, Galvanized Iron Pipe (GIP) or “Thick wall” stainless steel. Schedule 80 PVC shall be limited to risers, all above ground conduit and under the roadway/parking pavement. High density polyethylene (HDPE) SIDR 11.5 shall be used when directional boring is used. GIP or stainless steel shall be used under major roadways, taxiways, and runways. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell-end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirement.

2.2.12.2. Installation

Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. In a MH with knockouts, ducts shall start at the bottom knockout, allowing for upward expansion in the MH. All ducts not installed under roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts shall be accomplished IAW RUS Bulletin 1751F-643. All conduits shall be continuous between MH (i.e., no breaks or separations in the conduit runs between MH).

2.2.12.3. Bends and Sealing

All bends between MHs shall be a minimum of ten times (10X) the diameter of the duct size (i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees, where practical. Coordinate with 96 CS/SCXP if runs have bends that total more than 90 degrees is required. Ducts shall have bell-ends and enter a MH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH shall be sealed.

Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid 12” long test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.

2.2.12.4. Utility Separation

When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.

2.2.12.5. Spacers and Tracer Wire

Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals and cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message. Trace-Safe, water blocking tracer wire shall be installed as a means of providing traceability for each new duct bank. Install the ‘Trace-Safe’ 24“below finished grade directly over the duct banks and 12” below the ‘marking/warning tape’.

All new Trace-Safe systems installed for this project shall use a Trace-Safe approved splice, termination end, etc. connectors where needed and an approved label installed at all wire ends, and those wire ends secured to the maintenance hole walls within 6 inches of the top of the maintenance hole, accessible without having to enter the maintenance hole and not connected to grounds. The tracer will be secured to the maintenance whole wall and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wire entering any facility shall be grounded IAW applicable standards. (Follow the 96 CS Design Guide)

2.2.12.6. Entrance Conduits into Existing Maintenance Holes

When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if a knockout does not exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the Maintenance Hole. New ducts will be a minimum of 18 inches from either the Maintenance Hole floor or ceiling, if practical. The minimum bending radius for entry conduit/ducts shall be no less than 10 times the inside diameter of the conduit. Ducts and openings around ducts shall be sealed to prevent moisture from entering the Maintenance Holes.

2.2.12.7. Excavation/Building Penetrations

All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.

2.2.13. Outside Plant Installation

This section describes the underground cables, flexible geotextile multiple cell fabric, innerduct and MH plus conduit system installation requirements. The Contractor shall design and install Customer-Owned, Outside Plant Telecommunications Infrastructure in accordance with ANSI/TIA-758-B and 96th Communications Squadron Cyber Infrastructure Design Guide. Each cable installation shall be coordinated with 96 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

NOTE: A Request for Information (RFI) may be used as a streamlined method for the contractor to formally request or recommend a contract change, or to ask for a clarification of contract terms and conditions after contract award. The RFI shall be submitted in the format provided, and shall be sent from the Prime Contractor to the Contract Administrator for review, distribution to technical representatives/customers, and tracking through to resolution. A finalized RFI will be provided to all parties after the final review is provided by the Contracting Officer and the copy has the CO signature on the RFI form. No change to the contract shall be implemented, regardless of the finalized RFI distribution, until a signed/executed modification or other notification in writing from the CO is received by all parties.

2.2.13.1. Infrastructure Installation

Phase One (CLIN 0001) - Site Survey and Design

Phase One: Shall consist of the site survey and design to be approved by 96 CS/SCXP.

The survey and design shall be accomplished after contract award. The survey will consist of onsite inspection of existing infrastructure to verify condition and availability of existing and the need for new infrastructure to meet the requirements of this PWS. After details are gathered the contractor shall have their registered RCDD Engineer use the collected data to engineer the design to meet all requirements of the project. After design is complete the contractor shall conduct a design review with the 96 CS/SCOW and SCXP for approval. One soft and one (RCDD Stamped) hard copy of the design package shall be sent to the 96 CS/SCXP project manager one work week before the review so, it can be previewed before the design meeting.

The design package shall consist of a design/survey report, as-built drawings and installation, test and cutover plan to be used on this project. After design review has been completed and the 96 CS/SCXP accepts the design, Phase Two shall begin.

NOTE: Communications Systems Engineering and Design shall be performed by a BICSI Registered Communications Distribution Designer (RCDD). The shop drawings shall be Stamped and Signed by the "RCDD" certifying compliance with the applicable EIA/TIA standards as required.

Where there is a conflict between the PWS and building codes or standards, the more stringent, and of those, the most current directive(s) or regulation(s) shall apply.

Phase Two (CLIN 0002) - Infrastructure Installation

Phase Two:

2.2.13.2. Maintenance Holes (MH)

2.2.13.2.1. The Contractor shall install the following new infrastructure:

Phase Two (CLIN 0002) Building Requirements

2.2.13.3. Building 9620. Install one new 288-port FODP in network cabinet in comm. rm.

of B9620. Terminating only 144 strands. Coordinate with 96 CS/SCOIV for location and if needed.

2.2.13.4. New LRSF Building. Install one new wall mount network cabinet in comm. rm.

Per the 96 CS Design guide dated 2020. Coordinate with 96 CS/SCOIV for location and if needed.

2.2.13.5. Install one new 24-port FODP in new network cabinet in comm. rm. Coordinate with 96 CS/SCOIV for location and if needed.

2.2.13.6. Fiber Optic Cable Installation

The Contractor shall install outside plant (OSP), all-dielectric, loose buffer tube, single mode, water blocked optical fiber cable suitable for underground applications. All Fiber Optic cable runs shall be home run from building to building unless approved by the 96CS/ SCOW. The call shall met RUS 7 CFR 1755.900 criteria; shall comply with industry standards with regard to manufacturer’s cable marking, jacket, rip cords, water blocking, fiber color-coding, jacket materials, etc. In addition, the fibers shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550 nm. Each cable installation shall be coordinated with the 96 CS/SCXP so that the impact on the building users has been properly coordinated. The sequence of installation shall be coordinated with 96 CS/SCXP.

Phase Three (CLIN 0003) Fiber Cable Requirements

Install, splice and terminate approx. 7,700 ft. of new 144 strand SM FOC (144F8.3 SM) from new FODP in B9620, through approx.11 existing manholes to distribution HH outside of new LRSF facility.

Install, splice and terminate approx. 75 feet of 24 SM FOC from the distribution hand-hole to the new LRSF facility.

Follow 96 CS Design Guide

Note: Distances are to be verified by the installation contractor before ordering material.

CLIN Deliverables

2.2.13.6.1.

Deliverable # 1 CLIN 0001: Phase One - Engineered Design/Product Submittal plan provided by the contractor and approved by the 96 CS/SCXP.

Deliverable # 2 CLIN 0002: Phase Two: Install NETWORK EQUIPMENT INSIDE Bldg 9620

& newly constructed LRSF building

Deliverable # 3 CLIN 0003: Phase Three: All required cables installed spliced, terminated and tested Inspection Timeline: 10%, 35%, 65%, 100%.

Provide 96 CS/SCXP GIS Shape files/As-Built, Rack Elevation and MH Butterfly Drawings

(Per 96 CS Design Guide)

2.2.13.6.2. Site Restoration/Debris Removal

The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. Base grounds restoration requirements shall be complied with. Common use areas shall be restored to their original condition. The Contractor shall be responsible for disposing of all residues from this project off base and in accordance with Federal, state and base environmental laws and regulations. All residue produced by directional drilling operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal, state, local and Eglin AFB environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Eglin AFB.

2.2.14. Authorized Service Interruption (ASI) / Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 14 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

2.2.15. Identification/Marking

The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5 inches x 11 inches) on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.

2.2.16. Installation Schedules

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. (CDRL A002)

2.2.17. Weekly Status Reports

The Contractor shall prepare a Weekly Status Report in English and shall distribute. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements. (CDRL A003)

2.2.18. As-Built Drawings

The Contractor shall submit red line drawings showing the “as-built” configuration in format specified by base 96CS/SCXP project manager. The base communications squadron will provide baseline drawings. The Contractor shall provide accurate As-Built documentation of the entire install (i.e. rack elevations, cable route drawings “T-Sheets”). (CDRL A001)

2.2.19. Test and Acceptance/Installation Test Plan

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested to demonstrate to the Government that the system is fully operational ready to be placed into service. The Contractor shall test the system to demonstrate to the Government quality assurance representative. These tests shall be accomplished prior to the system being placed into service. Copper cabling shall be tested 100% (All Pairs) for DC loop resistance, shorts, opens, intermittent faults, and polarity between conductors, and between conductors and shield, if cable has overall shield. Test operation of shorting bars in connection blocks. Test cables after termination but prior to being cross-connected.

For single-mode and multi-mode optical fiber, perform 100% (All Strands) optical fiber end-to-end attenuation tests in accordance with OFSTP-14, OFSTP-7, TIA-568-C.3 and TIA 526-7 using tier one, Optical Power Meter and Light Source or tier two, and OTDR for single-mode optical fiber in a bi-directional. Perform verification acceptance tests.

NOTE: Optical fibers or copper cable(s) found with damage or defective strands or pairs, shall be replaced (from end to end) and will not be accepted by 96 CS/QAR. Review 96 CS Design Guide for testing requirements (CDRL A005)

2.2.20. Acceptance/Installation Test Report

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan IAW (CDRL A006).

2.2.21. Final Acceptance

The Contractor shall schedule a final project walk-through with the 96 CS/SCXP. This should be scheduled 10 calendar days prior to acceptance.

2.2.22. As-Built Documentation and CVC

Shape Files. The installer shall provide Global Positioning System (GPS) collected OSP infrastructure features and communications pathways attribute, metadata, and location information shall be converted to, stored, and submitted in an Environmental Systems Research Institute (ESRI) Shape File format. The shape files must be compatible with the Cyberspace

Infrastructure Planning System (CIPS) Visualization Component (CVC) web-based application. The shape files shall have a geospatial reference (.prj, .dbf, .shp, .shx and .cor) files included that specifies the parameters of the coordinate system.

NOTE: Installer(s) shall coordinate with the 96 CS/SCOW office through a Request for Information (RFI) to ensure they have the latest data dictionary before accomplishing any project GIS actions.

(a) Local Geospatial Data Format:

Coordinate system: UTM Zone: 16 North Datum: NAD 1983(conus) Coordinate units: Meters Altitude units: Meters Altitude Reference: HAE

Cable Route - The outside plant communications cable shall be depicted ‘as-installed, showing street/road locations and names, building ‘foot-prints’ accurately oriented as actually located. Maintenance Holes shall be depicted accurately oriented as located in reference to buildings and streets/roads. Extraneous information of other utility disciplines shall NOT be accepted on the as-built drawings. The information on the as-built drawings shall pertain to COMM specific.

Sample Cable Route Drawing

Butterfly - Drawing of the interior of individual Maintenance Holes that were installed, passed through, or modified in any way

Sample of MH Butterfly with GIS Metadata

Geographic Information Systems (GIS) data - Provide technical/field services necessary to locate and perform Geographic Information System (GIS) data collection of Outside Plant (OSP) cable infrastructure and communications pathways for government entry into the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC). Additionally, the Contractor shall enter into all communication "containers", to include communication Vaults, Maintenance-Holes (MH), Hand-Holes (HH), and Pedestals in order to record/document detailed container information by means of field drawings. Outside plant features/containers include vaults, maintenance-holes, hand-holes, pedestals, underground cables, direct buried splices, terminals, etc. The communications pathways include duct routes, aerial and direct-buried cable, trench routes, communication pathway entry points on building exterior walls that lead to interior building entry terminals, etc. The Installer shall augment the GPS survey by using conventional land surveying equipment and electronic cable locating (underground utility toning) equipment to meet requirements. The Installer shall ensure collected/provided data is compatible with the

CVC. (CDRL A001)

NOTE: Installer(s) shall coordinate with the 96 CS/SCOW office through and Request for Information (RFI) to ensure they have the latest data dictionary before accomplishing any project GIS actions.

2.2.22.1. Entities, Attributes, and Domain Values for Recording Required Communication Feature Data

GPS_ MAINTENANCE HOLE

Definition. An enclosed structure (maintenance hole, hand-hole or pull box). A butterfly layout is used that shows the floor and walls flattened out so that duct openings can be drawn on the walls. This must be represented as one polygon (one row in the table). The point is used to show the center of the maintenance hole/hand-hole cover.

Geometry type. Site (Point).

Attributes.

Column Name

SDSFIE

Common

Name Description

Data Type

Use Domain Table

MH_NAME Identifier Name The standard identifier name (e.g. MH-19).

Char(60) Required

MATERIAL Used to describe the material composition of the maintenance hole.

Menu Required Pre Cast Concrete Fiberglass Quazite Unknown Other

SIZE Dimension of the structure

The width, length, and height (or depth) of the

Char(30) Required

Column Name

SDSFIE

Common

Name Description

Data Type

Use Domain Table structure measured from the inside.

LID Shape of the structure lid

Menu Required Round Clamshell Rectangle Other

DRAINAGE_TYPE Menu Required Sump Hole Seepage Pit Other None

SPLICE_RACK Support braces on the side of the structure

Menu Required Yes No

LOCK_PRESENT Is the structure able to be locked

Menu Required Yes No

SPLICE_PRESENT Type of splice case is in the structure

Menu Required Copper Fiber Optics Both None

COMM_PATH_SEGMENT

Definition. Link that represents an enclosure path of comm., items outside of a building, maintenance hole, General Container, or other enclosed structure. For duct banks, comm. path segment can represent the virtual path, ductbank, duct, and innerducts. For ducts, comm. path segment can represent the virtual path, duct, and innerducts. For direct-buried cables at road-crossings, comm.- path segment can represent the virtual path, road-crossing duct, and direct-buried cables. It can also represent the path of aerial cable, cable-bridges, and cable-troughs.

Geometry type. Polyline Attributes:

Column Name

SDSFIE

Common

Name Description

Data Type

Use Domain Table

CABLE_ID A field that describes the originating and end structure this segment is representing.

Char(60) Required

Column Name

SDSFIE

Common

Name Description

Data Type

Use Domain Table

INSTALL_TYPE Type of path Menu Required Duct Duct Bank Direct Buried

NUMBER_OF_DUCTS Condition, Install_Type = Duct Bank

Numeric Min=1 Max=20 Default=1

DUCT_SIZE Dimension of the duct measured in inches

Numeric Min=1 Max=12 Default=4

Required

MATERIAL Composition of the Duct

Required Schedule 40 PVC Schedule 80 PVC

HDPE

DEPTH The minimum depth of this part of the path from grade, in inches.

Numeric Required

COMMENTS

3. GENERAL INFORMATION

3.1. Period of Performance

The period of performance for the project shall be determined based on the proposed schedule and actual contract award date.

3.2. Place of Performance

The place of performance is Eglin AFB, FL.

3.3. Hours of Operation

The Contractor shall routinely work during normal duty hours of the site. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 96 CS/SCXP and approved by the Contracting Officer at least 10 calendar days in advance.

3.4. Holidays/Down Days

The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the CO and coordinated with the 96 CS/SCXP Project Manager.

3.5. Base Support

The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.

3.6. Minimum Contractor Qualifications.

All work shall be performed by an experienced Telecommunications Contractor. The telecommunications contractor shall be a firm which is regularly and professionally engaged in the business of the applications, installation, and testing of the specified telecommunications systems and equipment. The Telecommunications Contractor shall demonstrate experience in providing successful telecommunications systems within the past 3 years of similar scope and size. Submit documentation for a minimum of three and a maximum of five successful telecommunication system installations for the Telecommunications Contractor.

Provide key personnel who are regularly and professionally engaged in the business of the application, installation and testing of the specified telecommunications systems and equipment.

There may be one key person or more key persons proposed for this solicitation depending upon how many of the key roles each has successfully provided. Each of the key personnel shall demonstrate experience in providing successful telecommunications systems within the past 3 years. Supervisors and installers assigned to the installation of this system or any of its components shall be Building Industry Consulting Services International (BICSI) Registered Cabling Installers level two, or Technician Level. Submit documentation of current BICSI certification for each of the key personnel.

In lieu of BICSI certification:

Supervisors and installers assigned to the installation of this system or any of its components shall have a minimum of 3 years' experience in the installation of the specified maintenance holes/duct systems, copper and fiber optic cabling and components. They shall have factory or factory approved certification from each equipment manufacturer indicating that they are qualified to install and test the provided products. Submit documentation for a minimum of three and a maximum of five successful telecommunication system installations for each of the key personnel. Documentation for each key person shall include at least two successful system installations provided that are equivalent in system size and in construction complexity to the telecommunications system proposed for this solicitation. Include specific experience in installing and testing telecommunications systems and provide the names and locations of at least two project installations

4. 4.2 Program Management

The contractor shall identify a Program Manager who shall be the primary representative responsible for all work awarded under this contract, participating in Program Management Reviews and ensuring all standards referenced herein are adhered to.

APPENDIX A: APPLICABLE STANDARDS

The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards

96th Communications Squadron Cyber Infrastructure Design Guide dated: Feb 2020

AFI 91-203 – Air Force Consolidated Occupational Safety Instruction

OSHA CFR 29 Part 1910-268 – Telecommunications

NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit

ANSI/TIA-606-B Administration Standard for Telecommunications Infrastructure

TIA-568-C Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling Standard

ANSI/TIA-607-B Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications

TIA-569-C - Commercial Building Standard for Telecommunications Pathways and Spaces

TIA-570-C –Residential Telecommunications Infrastructure Standard

TIA-758 B - Customer-owned Outside Plant Telecommunication Infrastructure Standard

BICSI TDM Manual - Building Industries Consulting Services International Telecommunications Distribution Methods (TDM) Manual

BICSI – Outside Plan Design Reference Manual

RUS Bulletin 1751F-643 - Underground Plant Design

RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering Shield Continuity and Construction Manual (TE&CM) 451.2

RUS Bulletin 1751F-801 – Electrical Protection Fundamentals

RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable Installation

NFPA 70 - National Electric Code

FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy

Unified Facilities Criteria 3-260-01

Unified Facilities Criteria 3-580-01

ASTM C 478, Standard Specification for Precast Reinforced Concrete maintenance hole Sections

ASTM C 857, Standard Practice for Minimum Structural Design Loading for Underground Precast Utility Structures

ASTM C 858, Standard Specification for Underground Precast Utility Structures

ASTM C 891, Standard Specification for Installation of Underground Precast Concrete Utility Structures

ASTM C 1037, Standard Practice for Inspection of Underground Precast Concrete Utility Structures

RUS Bulletin 1751F-640, Design of Buried Plant-Physical Considerations

RUS Bulletin 1751F-641, Construction of Buried Plant

RUS Bulletin 1751F-642, Construction Route Planning of Buried Plant

RUS Form 515a, Specifications and Drawings for Construction of a Direct Buried Plant

RUS Form 515c, Specifications and Drawings for Conduit and maintenance hole Construction

RUS Form 515d, Specifications and Drawings for Underground Cable Installation

APPENDIX B: LIST OF DELIVERABLES

All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this PWS. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:

CDRL Data Item Title Data Item Title

A001 As Built and CVC DI-DRPR-80151A/T

A002 Work Schedule DI-MISC-81382/T

A003 Status Report DI-MGMT-80368A

A004 Meeting Minutes DI-ADMIN-81505/T

A005 Test Plan DI-NDTI-80566A/T

A006 Test and QA Reports DI-QCIC-80512

A007 Project Design Package

APPENDIX C: LIST OF ACRONYMS

AASHTO American Association of State Highway and Transportation Officials AFM Airfield Management (BaseOPS) Approx Approximately ATC Air Traffic Control Tower ATCALS Air Traffic Control and Landing Systems BCE Base Civil Engineering CDRL Contract Deliverable CFE Contractor-Furnished Equipment CFP Contractor-Furnished Property CIP Common Installation Picture CIPS Cyberspace Infrastructure Planning System CMA Controlled Movement Area CMHDS Communications Maintenance Hole Duct System CO Contracting Officer Comm Communications CS Communications Squadron CSI-B Cyberspace Integrator-Base CVC CIPS Visualization Component ECMRA Contractor Manpower Reporting Application EFI&T Engineer, Furnish, Install and Test FOC Fiber Optic Cable FODP Fiber Optic Distribution Panels FOUO For Official Use Only FY Fiscal Year HDPE High Density Polyethylene IAW In Accordance With ID Inside Diameter ILS Instrument Landing System IPT Integrated Process Team LMR Land Mobile Radio MH Maintenance Hole MHDS Maintenance Hole Duct System NLT No Later Than NPDES National Pollution Discharge Elimination System OEM Original Equipment Manufacturer OPSEC Operational Security OSHA Occupational Safety & Health Administration OSP Outside Plant OSS Operations Support Squadron OTDR Optical Time Domain Reflectometer PDF Portable Document Format PM Project Manager POC Point Of Contact Prime Prime Contractor

PSI Pounds per Square Inch

APPENDIX C: LIST OF ACRONYMS

PVC Polyvinyl Chloride PWS Performance Work Statement QAE Quality Assurance Evaluator QCM Quality Control Manager Qty Quantity RUS Rural Utilities Service Bulletin SCOW Supply Chain Operations Wing SCX Scheduler Planner SE System Engineer SM Single Mode Sub Sub-Contractor SWPPP Storm Water Pollution Prevention Plan TIA Telecommunications Industry Association TMGB Telecommunication Main Ground Bus-Bar TRD Technical Requirements Document

ATTACHMENT 1 – ROUTE

APPENDIX E: INFRASTRUCTURE SOLUTIONS STANDARDS & REFERENCES

Purpose:

The following…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .