Attachment 11 Questions and Answers 05.02.22 22Q0012.pdf

PDF 116 KB Posted

Attached to
Fiber Installation for C-64D
Solicitation number
FA282322Q0012
Issued by

View the file

Other files

File Type Posted
Attachment 12 Proposed Floor Plan.pdf PDF
Solicitation Amendment FA282322Q00120004 SF 30.pdf PDF
Attachment 14 Proposed Comm Room Details.pdf PDF
Attachment 15 Questions and Answers 5.11.22.pdf PDF
Attachment 13 Proposed Site Plan.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120003 SF 30.pdf PDF
Solicitation Amendment FA282322Q00120002 SF 30.pdf PDF
Attachment 10 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended 5.2.22.pdf PDF
RFP Fiber Amended.pdf PDF
Solicitation Amendment FA282322Q00120001 SF 30.pdf PDF
Attachment 9 OFFEROR SCHEDULE.xlsx XLSX spreadsheet
Attachment 3 Addendum to FAR 52 212-2 Amended 4.27.22.pdf PDF
Attachment 2 Addendum to 52.212-1 & 52.212-3 Amended.pdf PDF
Attachment 7 Dec 2021 Reps Certs.pdf PDF
Attachment 6 Design Guide.pdf PDF
Attachment 9 Base Access Memo.pdf PDF
Attachment 8 WD 2015-4531 R19 3.15.22.txt TXT text file
Attachment 4 PWS 3.3.pdf PDF
Attachment 2 Addendum to FAR 52 212-1 and-3.pdf PDF
Attachment 1 Cover_Sheet.pdf PDF
Solicitation - FA282322Q0012.pdf PDF
Attachment 5 90percent Design Drawings 2020.pdf PDF
Attachment 3 Addendum to FAR 52 212-2 (NOV 2021).pdf PDF
Attachment SVL.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q1 Would the Government please confirm the Offeror schedule is Attachment 9 and not Attachment 10 or Attachment 2 as listed in Solicitation/Amendment 0001 and Attachment 2 Addendum 52.212-1 respectively? (Reference Attachment 2 Part I – Price Proposal)

A1 – The attachment “Attachment 9 OFFEROR SCHEDULE” the file uploaded was incorrectly name and should have been named “Attachment 10 OFFEROR SCHEDULE” It is the same file.

The reference to “Attachment 2” in regards to the solicitation is a listing of the documents removed and added.

The documents listed on the SF30:

List of Attachments The following attachments were added:

Addendum 52.212-1,52.212-3 Amended 4.27.22 Attachment 3 Addendum to 52.212-2 Amended 4.27.22 Offeror Schedule RFQ detail The following attachments were deleted:

Attachment 1 Coversheet Attachment 2 Addendum to 52.212-1 & 52.212-3 Attachment 3 Addendum to 52.212-2 Miscellaneous text in this section has been modified to:

Attachment 1 Removed Attachment 2 Addendum to 52.212-1 & 52.212-3 Attachment 3 Addendum to 52.212-2 Attachment 4 PWS Attachment 5 90% Design Drawings Attachment 6 96th Design Guide Attachment 7 Dec 2021 Reps and Certs Attachment 8 WD 2015-4531 R19 3.15.22 Attachment 9 Request for Base Pass Attachment 10 Offeror Schedule Attachment 11 RFP

Q2 Would the government confirm the referenced paragraphs b and c requirements can be included in th Attachment 2 Part I – Price Proposal paragraphs b and c

A2. The Government confirms the referenced paragraphs b can c requirements can be included in the cover letter.

Q3 Would the government please clarify that the cover letter can be submitted as a separate attachment a Part I Price Proposal? Attachment 2 Part I – Price Proposal paragraph d Cover Letter

A3 The Government confirms that the cover letter is a separate attachment and not considered Part I Price Proposal.

Q4 Would the government please define what “contract number” they are requesting to be included in the cover letter? Attachment 2 Part I – Price Proposal paragraph d Cover Letter

A4. No contract number is needed on the cover letter. Please review updated Attachment 2 Addendum to 52.212-1 and 52.212-3.

Q5. Would the government confirm if there is a page limit to PART II – Technical Acceptability?

A5. The Government confirms that there is no page limit specified for PART II technical Acceptability.

Q6. Would the government clarify the pricing difference between Option A and Option B Item CLINs 0001AA, 0002AA, and 0003AA Supplies or Services?

A6 – Option B is for if the contractor wants to submit alternate approach.

Q7 Due to the site survey and questions both due on May 4th and with the proposal due date of May 9th would the government please consider extending the proposal due date?

A7. Please see updated solicitation.