Addendum 2 1412 Renovation Phasing.docx

DOCX document 25 KB Posted

Attached to
Renovate Squadron Operations Area, JSF Hangar B1412, Eglin Air Force Base
Solicitation number
FA282321R0016-Solicitation
Issued by

About this file

This document includes an addendum to construction plans and a federal contract solicitation for renovation work. The addendum provides updates to room numbering and general notes on construction phasing plans. The solicitation seeks proposals to renovate squadron operations areas in Hangar B1412 at Eglin Air Force Base, Florida. Renovations include selective demolition, finishes modifications, upgrades to secure areas, and maintenance of power systems. The total small business set-aside contract value is estimated between $1-5 million. Proposals are due by June 4, 2021 through the DoD SAFE system. The performance period is anticipated to be 300 days following notice to proceed.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #2

FTFA20CB73, Renovate JSF Squadron Ops Hangar, Bldg 1412

29 June 2021

1. Sheet A-110: The legend for Rm 166 and 167 shall be the same as CONSTRUCTION LIMITS PHASE 1 as indicated in GRAPHIC LEGEND.

2. Sheet A-120: The legend noted as GENERAL NOTE 2 for Rm 166 and 167 shall be the same as CONSTRUCTION LIMITS PHASE 1 as indicated in GRAPHIC LEGEND. This area shall be noted as GENERAL NOTE 1.

3. Sheet A-120, General Notes:

Note 1 shall read as “CONSTRUCTION (PHASE I) SHALL BE COMPLETE WITHIN TWO HUDREND (200) DAYS FROM NTP”.

Note 2 shall read as “CONSTRUCTION (PHASE II) SHALL START NO EARLIER THAN 1 NOVEMBER 2021 OR AFTER CURRENT OCCUPANTS DEPART EGLIN AFB, WHICHEVER DATE IS LATER” as stated in Addendum #1.

Note 3 shall read as “ALL WORK IN ROOM 134/135 MUST BE COMPLETE WITHIN NINETY (90) DAYS FROM NTP”.

Note 4 shall read as “ALL WORK IN SUPPORT AND SUPPLY ROOMS, INCLUDING EXTERIOR CANOPY WORK MUST BE COMPLETE WITHIN ONE HUNDREN AND FIVE (105) DAYS FROM NTP”.

Page | 1 of 1