This solicitation is for renovation work at Eglin Air Force Base in Florida. The project includes selective demolition of existing interior construction and finishes as well as modifications to supply and tool rooms. The scope also involves modifying an existing SAPF to meet new standards and converting a second SAPF into a SCIF. Additional work includes maintenance on a 270 VDC power system. The NAICS code is 236220 for commercial and institutional building construction. The estimated value is between $1 million and $5 million. This opportunity is a 100% small business set-aside utilizing best value source selection. The performance period is anticipated to be 300 days after notice to proceed. Questions regarding site visits must be sent by May 10th and proposals are due no later than June 4th through the DoD SAFE system. Funding is not presently available and the government reserves the right to cancel the solicitation.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
prepared for:
AFTC/PZIOC Eglin AFB, Florida
Final Design Submittal prepared by: January 26, 2021 Bullock Tice Associates - Pensacola, Florida
Renovate Squadron Operations Area
JSF Hangar B1412 Eglin AFB, Florida
Project No. FTFA-20CB73
BTA No. 141614.12
Specifications
This page left blank.
RENOVATE SQUADRON OPERATIONS AREA JSF HANGAR B1412 EGLIN AFB, FL FTFA-20CB73
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS - EGLIN STANDARD
01 57 20.01 SUPPLEMENTAL ENVIRONMENTAL PROTECTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
STRUCTURAL
1252021 dcarpenter Rice blank Stamp dcarpenter Text Box 1/26/21
PROJECT TABLE OF CONTENTS Page 2
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 72 00 WALLCOVERINGS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 02 INTERIOR SIGNAGE
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION
12 61 13 UPHOLSTERED AUDIENCE SEATING
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
APPENDICES
APPENDIX A 96 CS DESIGN GUIDE
APPENDIX B 270V DC O&M MANUAL
APPENDIX C 796 CE FIRE ALARM DESIGN GUIDE
APPENDIX D 96 CE DESIGN GUIDE
APPENDIX E FURNITURE, FIXTURES AND EQUIPMENT
-- End of Project Table of Contents --
L L
BAGW
E
M.
LIC N
AVID
No. 59251
SD E
AL EN
S IO
R O
F
ES
P
N
STATE OF
G
IN
E E
R
E
ADIL R
F O
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Utility Outage Requests
Utility Connection Requests
Welding Permits
Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes selective demolition of existing interior construction, finishes, amd modifications to supply and tool room areas. This work includes new openings in hanger and exterior walls for openings, replacement of one exterior canopy and new and builtin casework. Other spaces to be renovated include modifying existing SAPF to bring up to ICO 705 standards and converting other SAPF into SCIF to house the 33 FW Intel Function.
1.2.2 Location
The work is located at Hangar 1412, Eglin AFB, Florida, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 Phasing
The work shall be completed in two phases as shown on the drawings. Phase I will include all work with the exception of the east SAFF which will be completed during Phanse II
a. Phase I work will begin May 1, 2021.
l. All work in rooms 134/135 must be complete by June 15, 2021.
2. All work in the supply & support area must be complete by July 15, 2021.
3. By Nov. 1, 2021 all Phase ! work must be complete.
b. Phase II work will begin Nov. 1, 2021.
SECTION 01 11 00 Page 1
1.4 CONTRACT DRAWINGS
Five sets of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished drawings and notify the Government of any discrepancies.
1.5 WORK RESCHEDULING
Normal duty hours for work are from 7 a.m. to 4 p.m., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
a. Work within the SAFF west will be escorted each day during normal working hours. Government may be able to accomodate overtime, but noweekend or holiday work will be allowed in this area.
1.6 OCCUPANCY OF PREMISES
Portions of Building will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.7 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.8 ON-SITE PERMITS
1.8.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions tothe Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 14 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
SECTION 01 11 00 Page 2
1.8.2 Borrow, Excavation, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Excavation Permits 15 calendar days prior to work
Eglin Standard
Welding Permits 15 calendar days prior to work
Eglin Standard
Post permits at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted atoron project site.
1.9 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.9.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.10 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 10 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 3
-- End of Section --
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 State
"State" when used in reference to states of the United States also includes the Territory of Guam.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges andInstallation Access
Application for and use of badges will be as directed by the Contracting Officer. Immediately report instances of lost or stolen badges to the Contracting Officer.
1.2.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, between 7:00 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
SECTION 01 14 00 Page 1
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, exterior work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
Refer to Summary of Work regarding work hours and west SAFF hours.
1.2.4 Occupied and Existing Buildings
The Contractor shall be working in an existing building which are occupied.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the adjacent spaces during the construction period.
Relocate movable furniture as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work. Coordinate any work requiring adjacent rooms with Contracting Officers.
The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and communications services are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-04 Samples
Color Boards; G
1.3 COLOR BOARDS FOR AIR FORCE PROJECTS
Submit one set of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board. If more space is needed, more than one board per set may be submitted.
Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.4 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by law.
1.5 SUPERVISION
1.5.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work.
SECTION 01 30 00 Page 1
1.5.2 Superintendent Qualifications
The project superintendent must have a minimum of 5 years experience in construction with at least 2 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.5.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.5.3 Project Manager
Assign a Project Manager with the responsibility for the overall management of the project. The Contracting Officer may request proof of the Project Manager's qualifications at any point in the project if the performance of the Project Manager is in question.
1.5.3.1 Project Manager Qualifications
The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects of similar size and complexity.
1.5.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.6 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.7 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members
SECTION 01 30 00 Page 2 are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
SECTION 01 32 17.00 20
COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
05/18
PART 1 GENERAL
1.1 DEFINITIONS
The cost-loaded Network Analysis Schedule (NAS) is a tool to manage the project, both for Contractor and Government activities. The NAS is also used to report progress, evaluate time extensions, and provide the basis for progress payments.
For consistency, when scheduling software terminology is used in this section, the terms in Primavera's scheduling programs are used.
1.2 SCHEDULE REQUIREMENTS PRIOR TO THE START OF WORK
1.2.1 Preliminary Scheduling Meeting
Before preparation of the Project Baseline Schedule, and prior to the start of work, meet with the Contracting Officer to discuss the proposed schedule and the requirements of this section.
1.2.2 Project Baseline Schedule
Submit the Baseline NAS at the PreConstruction Meeting. Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline NAS. The acceptance of a Baseline NAS is a condition precedent to:
a. The Contractor starting demolition work or construction stage(s) of the contract.
b. Processing Contractor's invoices(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline NAS, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.2.3 Project Baseline Schedule
1.2.3.1 Baseline NAS
Submit and present the Baseline NAS at the Post-Award Kickoff (PAK) Meeting. The Baseline NAS must include detailed design activities, general (summarized) approach for the construction phase(s) of the project and required milestone activities. If the project is being Fast-Tracked or allows Early Start of construction, the Baseline NAS must include all fast-tracked design construction phases, including the required or proposed
SECTION 01 32 17.00 20 Page 1 critical path design submittals within each phase that will occur during the duration of the project. The most current updated design schedule must accompany each design submittal.
The acceptance of a Baseline NAS is a condition precedent to processing Contractor's pay request(s) for design activities/items of work.
Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline NAS. The acceptance of a Baseline NAS is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoices(s) for construction activities/items of work.
c. Review of any schedule updates.
1.2.3.2 Construction Baseline NAS
Develop the Construction Baseline Schedule, as design progresses, with detailed construction activities. If design must be completed and accepted prior to construction, submit the complete design and construction network analysis schedule and obtain acceptance prior to starting construction work. If the project is Fast-Tracked, each construction stage must be detailed and built upon the previous Fast-Tracked Baseline Schedule (including any interim updates) and accepted prior to starting that stage of the construction work. Payment for completed work is dependent on an accepted, detailed schedule for that portion of work.
Submittal of the Construction Baseline NAS, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work must be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 THREE-WEEK LOOK AHEAD SCHEDULE
1.3.1 Weekly CQC Coordination and Production Meeting
Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, for review during the weekly CQC Coordination or Production Meeting.
1.3.2 Look Ahead Schedule Requirements
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Project Network Analysis Schedule. Requirements include:
a. Key the work plans mapped to NAS activity numbers and updated each week to show the planned work for the current and following two-week period.
b. Include upcoming outages, closures, field evaluation tests, preparatory meetings, and initial meetings.
c. Identify critical path activities on the Three-Week Look Ahead Schedule.
SECTION 01 32 17.00 20 Page 2
d. The detail work plans are to be bar chart type schedules, derived from but maintained separately from the Project NAS on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer.
e. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work.
1.4 MONTHLY NETWORK ANALYSIS
1.4.1 Monthly Network Analysis Updates
Meet with Government representatives at monthly intervals to review and agree on the information presented in the updated project schedule. The submission of an acceptable, updated schedule to the Government is a condition precedent to the processing of the Contractor's invoice. Submit an acceptable, updated schedule to the Government regardless of whether a Contractor's invoice is submitted for the given period. The Contractor and Government must consent to agree on unit quantities of work completed equating to a percentage of payment for each activity progressed during the update period. Monthly update schedules must incorporate as-built events as they occurred and provide ongoing status of anticipated finish dates.
As-built events must correspond to contemporaneous records including but not limited to submittals, daily production reports and quality control reports.
Provide the following with each Schedule submittal:
a. Time-Scaled Logic Diagram.
b. Reports listed in paragraph REQUIRED TABULAR REPORTS.
c. Data disks containing the project schedule. Include the back-up native .xer program files.
1.4.2 As-Built Schedule
As a condition precedent to the release of retention and making final payment, submit an "As-Built Schedule," as the last schedule update showing all activities at 100 percent completion. This schedule must reflect the exact manner in which the project was actually constructed.
1.5 CORRESPONDENCE AND TEST REPORTS
Reference Schedule activity IDs that are being addressed in each correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) and test report (e.g., concrete, soil compaction, weld, pressure).
1.6 ADDITIONAL SCHEDULING REQUIREMENTS
References to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to the requirements of this section.
SECTION 01 32 17.00 20 Page 3
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Designated Project Scheduler; G
Baseline NAS; G
Construction Baseline NAS; G
SD-07 Certificates
Monthly Network Analysis Updates; G
SD-11 Closeout Submittals
As-Built Schedule; G
1.8 SOFTWARE
Prepare and maintain project schedules using Primavera P6 software in a version compatible with Government's current version. Importing data into P6 using data conversion techniques or third party software is cause for rejection of the submitted schedule.
1.9 DESIGNATED PROJECT SCHEDULER
Submit to the Contracting Officer for approval an individual who will serve as the Designated Project Scheduler. Include a copy of the candidate's resume with qualifications. The Contracting Officer may remove the Designated Project Scheduler, and require replacement, if the scheduler does not effectively fulfill their duties in accordance with the contract requirements. Payment request will not be processed without an approved Designated Project Scheduler.
1.9.1 Qualifications
The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules, of similar size and complexity to this contract, using Primavera P6.
1.9.2 Duties
Duties of the Designated Project Scheduler:
a. Prepare Baseline NAS.
b. Prepare monthly schedule updates.
c. Prepare tabular reports.
d. Prepare Time Impact Analysis (TIA) as necessary.
SECTION 01 32 17.00 20 Page 4
e. Provide certification that NAS and TIA submittals conform to the contract requirements.
f. Participate with the Prime Contractor and Government Representative in a monthly meeting at the job site in-person, and scheduled with sufficient time to support the Monthly Network Analysis Updates process, to discuss project status, schedule updates, critical activities, potential delays, and contract modifications impacting the schedule.
1.10 NETWORK SYSTEM FORMAT
The system must include time-scaled logic diagrams and specified reports.
Prepare the schedule in accordance with the following Primavera P6 settings and parameters. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
1.10.1 Diagrams
Provide 11 by 17 inch hard-copy of Time-scaled Logic Diagram in color and landscape-oriented. Clearly show activities on the longest path. Include the following information for each activity and include accompanying Gantt chart:
a. Activity ID
b. Activity Name
c. Original Duration in Work Days
d. Remaining duration in Work Days
e. Physical Percent Complete
f. Start Date
g. Finish Date
h. Total Float
1.10.2 Schedule Activity Properties and Level of Detail
1.10.2.1 Activity Identification and Organization
a. Identify design and construction activities planned for the project and other activities that could impact project completion if delayed in the
NAS.
b. Identify administrative type activity/milestones, including all pre-construction submittal and permit requirements prior to demolition or construction stage.
c. Include times for procurement, Contractor quality control and construction, acceptance testing and training in the schedule.
d. Include the Government approval time required for the submittals that
SECTION 01 32 17.00 20 Page 5 require Government Approval prior to construction, as indicated in Section 01 33 00 SUBMITTAL PROCEDURES Section 01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES.
e. Create separate activities for each Phase, Area, Floor Level and Location the activity is occurring.
f. Do not use construction category activity to represent non-work type reference (e.g. Serial Letter, Request for Information) in NAS. Place Non-work reference within the P6 activity details notebook.
Activity categories included in the schedule are specified below.
1.10.2.2 Activity Logic
a. With the exception of the Contract Award and Contract Completion Date (CCD) milestone activities, activity must not be open-ended; each activity must have predecessor and successor ties.
b. Activities must not have open start or open finish (dangling) logic.
c. Do not use lead or lag logic without Contracting Officer prior approval.
d. Minimize redundant logic ties.
e. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer.
(1) While an activity cannot be deleted, where said activity is no longer applicable to the schedule, but must remain within the logic stream for historical record, change the activity to a milestone and clearly label "NO LONGER REQUIRED" after the activity name. Redistribute accordingly any remaining budget associated with that activity.
(2) Document any such change in the milestone's "Notebook," including a date and explanation for the change.
(3) The ID number for a "NO LONGER REQUIRED" activity must not be re-used for another activity.
1.10.2.3 Critical and Near Critical Activity Baseline Limitation
For P6 settings, critical activities are defined as being on the Longest Path. "Near Critical" is defined as having total float, of up to 14 days more, than the greatest float value found on the Longest Path. Longest Path (Critical) and Near Critical Activities must not make up more than 20 percent of all activity within the Baseline Schedule.
1.10.2.4 Assigned Calendars
All NAS activity must be assigned calendars that reflect required and anticipated non-work days.
SECTION 01 32 17.00 20 Page 6
1.10.2.5 Activity Categories
1.10.2.5.1 Pre-construction Activities
Examples of pre-construction activities include, but are not limited to, bond approval, permits, pre-construction submittals and approvals. Include pre-construction activities that are required to be completed prior to the Contractor starting the demolition or construction stage of work.
1.10.2.5.2 Procurement Activities
Examples of procurement activities include, but are not limited to:
Material/equipment submittal preparation, submittal and approval of material/equipment; material/equipment fabrication and delivery, and material/equipment on-site. As a minimum, separate procurement activities must be provided for critical items, long lead items, items requiring Government approval and material/equipment procurement for which payment will be requested in advance of installation. Show each delivery with relationship tie to the Construction Activity specifically for the delivery.
1.10.2.5.3 Government Activities
Government and other agency activities that could impact progress must be clearly identified. Government activities include, but are not limited to;
Government approved submittal reviews, Government conducted inspections/tests, environmental permit approvals by State regulators, utility outages, Design Start, Construction Start (including Design/Construction Start for each Fast-Track Phase, and delivery of Government Furnished Material/Equipment.
1.10.2.5.4 Construction Quality Management (CQM) Activities
The Preparatory and Initial Phase meetings for each Definable Feature of Work identified in the Contractor's Quality Control Plan must be included in the Three-Week Look Ahead Schedule. Preparatory and Initial phase meetings are not required in the NAS, but can be represented by a start milestone linked to successor parent Construction Activity. The Follow-up Phase must be represented by the Construction Activities themselves in the
NAS.
1.10.2.5.5 Construction Activities
No on-site construction activity may have a duration in excess of 20 working days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, unless otherwise defined in this contract.
1.10.2.5.6 Turnover and Closeout Activities
Include activities or milestones for items on the NAVFAC Red Zone Checklist/POAM that are applicable to this project. As a minimum, include required Contractor testing, required Government acceptance inspections on equipment, Pre-Final Inspection, Punch List Completion, Final Inspection and Acceptance. Add an unconstrained start milestone for the initial NAVFAC Red Zone - Facility Turnover Planning Meeting at approximately 75 percent construction contract completion or six months prior to Contract Completion Date (CCD), whichever is sooner.
SECTION 01 32 17.00 20 Page 7
1.10.2.5.7 Testing of HVAC - DALT, TAB, and PVT Activities
Include in the baseline schedule, activities and milestones associated with Government acceptance of Duct Air Leakage Test (DALT), Testing, Adjusting, and Balancing (TAB) and Performance Verification Test (PVT) as required and in accordance with Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR
HVAC.
a. Identify the general area or location(s) for Government Acceptance Testing of DALT, TAB and PVT.
b. Incorporate into the baseline schedule, time periods required for advance notification of work, and Government submittal review in accordance with Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC, paragraph DALT AND TAB SUBMITTAL AND WORK SCHEDULE.
c. Include the following as schedule activities or milestones:
(1) Pre-DALT/TAB/PVT Meeting
(2) TAB Design Review Report, Government review
(3) TAB Pre-Field Engineering Report, Government review
(4) DALT Field Work
(5) DALT Field Acceptance Testing
(6) Certified Final DALT Report, Government review
(7) Control Contractors PVT Plan, Government review
(8) Equipment Suppliers PVT Plan, Government review
(9) Season I TAB Field Work
(10) Season I Certified Final TAB Report, Government review
(11) Endurance Testing, Government review
(12) PVT Field Work
(13) PVT Report, Government review
(14) Season I TAB Field Acceptance Testing
(15) Season II TAB Field Work
(16) Season II Certified Final TAB Report, Government review
(17) Season II TAB Field Acceptance Testing
1.10.2.5.8 Commissioning Activities
Include in the baseline schedule activities and milestones associated with Commissioning.
a. Identify the general area or location(s) of systems for Commissioning Inspection and Testing
SECTION 01 32 17.00 20 Page 8
b. Incorporate into the baseline schedule time periods for Government submittal review
1.10.2.6 Contract Milestones and Constraints
1.10.2.6.1 Project Start Date Milestones
Include as the first activity on the schedule a start milestone titled "Contract Award," which must have a Mandatory Start constraint equal to the Contract Award Date.
1.10.2.6.2 NAVFAC Red Zone - Facility Turnover Planning Meeting Milestones
See paragraph TURNOVER AND CLOSEOUT ACTIVITIES above.
1.10.2.6.3 Substantial Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Substantial Completion." Substantial Completion is defined as the point in time the Government would consider the project ready for beneficial occupancy wherein by mutual agreement of the Government and Contractor, Government use of the facility is allowed while construction access continues in order to complete remaining items (e.g. punch list and other close out submittals). Include a separate Substantial Completion Milestone for each phase if the contract requires construction to be completed in phases.
1.10.2.6.4 DD-1354 Finish Milestone
Add unconstrained finish milestone, titled "DD-1354" and scheduled 30 calendar days prior to Substantial Completion, whenever a Form DD-1354 is required in accordance with Section 01 20 00.00 20 PRICE AND PAYMENT
PROCEDURES.
1.10.2.6.5 Projected Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Projected Completion." Projected Completion is defined as the point in time all contract requirements are complete and verified by the Government with a successful Final Inspection in accordance with Section 01 45 00.00 20 QUALITY CONTROL. This milestone must have the Contract Completion Date (CCD) milestone as its only successor.
1.10.2.6.6 Contract Completion Date (CCD) Milestone
Last schedule entry must be an unconstrained finish milestone titled "Contract Completion (CCD: DD-MM-YY)." DD-MM-YYYY is the current contract completion date at data date, day-month-year corresponding to P6 Must Finish Date. NAS milestone updates of Project Completion finish date for longest path must reflect calculated float as positive or negative based on CCD. Calculation of schedule updates must be such that if the finish of the "Projected Completion" milestone falls after the contract completion date, then negative float is calculated on the longest path. If the finish of the "Projected Completion" milestone falls before the contract completion date, the float calculation must reflect positive float on the longest path.
SECTION 01 32 17.00 20 Page 9
1.10.2.7 Work Breakdown Structure & Activity Code
At a minimum, establish a Work Breakdown Structure (WBS) and provide activity codes identified as follows:
1.10.2.7.1 Work Breakdown Structure (WBS)
Group all activities and milestones within appropriate WBS categories including, at a minimum, the following:
a. Project Milestones:
(1) Management Milestones
(2) Project Administrative Meetings
(3) Permits
b. Pre-Construction Phase:
(1) Submittals and Reviews
(2) Procurement
(3) Mobilization
c. Construction Phase: Create multiple sub-sections in accordance with project specific categories of work including in WBS descending order as follows:
(1) General Area
(a) Type of Work Item
1. Location
d. Commissioning & Testing:
(1) Specific area/locations of commissioning
(2) Final Testing
(3) Training
d. Project Closeout: Include activity items such as Punchlist, Demobilization, O&M, As-built Drawings, Training, and As-built NAS.
e. Modifications: Create sub-category of Conformed and Non-Conformed under Modification WBS. Create multiple sub-sections as the project progresses identified by issue and Fragnet placed in Conformed for modifications issued prior data date, or Non-Conformed for issues not modified to contract prior data date.
f. Removed Activity: Activity "removed" by remaining within logic sequence and changing to Finish Milestone. Actualize finish date to date activity removed from schedule and provide reason(s) for removal explained in Activity Notebook.
SECTION 01 32 17.00 20 Page 10
1.10.2.7.2 Responsibility Code
All activities in the project schedule must be identified with the party responsible for completing the task. Activities must not belong to more than one responsible party.
1.10.2.7.3 Activity Category Code
Provide user defined "CAT" codes for Project Level activity codes. Use the following codes:
a. Assign "Procure" to Procurement type activity
b. Assign "Construct" Construction type activity
c. Assign "Close Out" to dedicated Commissioning, Testing & Close Out type activity.
d. Assign "Other" to other activity not otherwise designated.
1.10.2.7.4 Construction Specification Institute (CSI) Masterformat Code
Identify all activities in the project schedule with its respective Specification Section number. Activities must not belong to more than one Section number. If an activity does not have an applicable CSI Code (e.g.
Mobilize), the code must be "0000".
1.10.2.8 Anticipated Weather Lost Work Days
Use the National Oceanic and Atmospheric Administration's (NOAA) Summary of Monthly Normals report to obtain the historical average number of days each month with precipitation, using a nominal 30-year, greater than 0.10 inch precipitation amount parameter, as indicated on the Station Report for the NOAA location closest to the project site as the basis for establishing a "Weather Calendar" showing the number of anticipated non-workdays for each month due to adverse weather, in addition to Saturdays, Sundays and all Federal Holidays as non-work days.
1.10.2.9 Anticipated Restricted Delays
Unless otherwise noted or defined in Section 01 14 00 WORK RESTRICTIONS, allow in the schedule one lost workday for every two months of project duration for instances where base access is not permitted or where work areas are temporarily not accessible for security reasons which causes a delay in the work. Use Anticipated Restricted Delays as basis for establishing a "Security Calendar" showing the number of anticipated non-workdays for each month due to anticipated restrictions, in addition to anticipated adverse weather, Saturdays, Sundays and all Federal Holidays as non-work days. Assign the Security Calendar to any activity that could be impacted by restriction delays. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual lost work days if the number of actual restriction delay days exceeds the number of anticipated for the month in which the delay occurs and the restriction delayed activities are critical to contract completion. A lost workday due to restriction delay is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
SECTION 01 32 17.00 20 Page 11
1.10.2.10 Cost Loading
The Project Network Analysis Schedule (NAS) must be cost-loaded and will provide the basis for progress payments. Earned Value Reports must be derived from and correspond to cost loaded NAS. Use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications.
1.10.2.10.1 Cost Loading Activities
Assign Material and Equipment Costs, for which payment will be requested in advance of installation, to their respective procurement activity (i.e., the material/equipment on-site activity). Assign cost for material/equipment, paid for after installation; labor; and construction equipment to their respective Construction Activities. Provide breakdown of definable features of work for cost loaded activities comprising Mobilization and De-Mobilization (Lump sum not allowed). The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for Procurement and Construction Activities.
Evenly disperse overhead and profit to each activity over the duration of the project.
1.10.2.10.2 Partial Payment
Breakdown unit of measure and cost must be defined within P6 Activity Detail Expenses for partial payment of any cost loaded activity. Lump sum cost loaded activity will not be partially paid.
1.10.3 Schedule Software Settings and Restrictions
a. Activity Constraints: Date/time constraint(s), other than those required by the contract, are not allowed unless accepted by the Contracting Officer. Identify any constraints proposed and provide an explanation for the purpose of the constraint in the Narrative Report as described in paragraph REQUIRED TABULAR REPORTS.
b. Default Progress Data Disallowed: Actual Start and Actual Finish dates on the CPM schedule must match the dates on the Contractor Quality Control and Production Reports.
c. Software Settings: Handle schedule calculations and Out-of-Sequence progress (if applicable) through Retained Logic, not Progress Override. Show all activity durations and float values in days. Show activity progress using Remaining Duration. Set default activity type to "Task Dependent".
d. At a minimum, include the following settings and parameters in P6 Schedule preparation:
(1) General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
(2) Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(a) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week,
172.0 Hours/Month and 2000.0 Hours/Year.
(b) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
SECTION 01 32 17.00 20 Page 12
(3) Admin Drop-Down Menu, Admin Preferences, Earned Value Tab:
(a) Earned Value Calculation: Use "Budgeted values with current dates".
(4) Project Level, Dates Tab:
(a) Set "Must Finish By" date to "Contract Completion Date", and set "Must Finish By" time to 05:00pm.
(5) Project Level, Defaults Tab:
(a) Duration Type: Set to "Fixed Duration & Units".
(b) Percent Complete Type: Set to "Physical".
(c) Activity Type: Set to "Task Dependent".
(d) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days. Alternative calendars may be used with Contracting Officer approval.
(6) Project Level, Calculations Tab:
(a) Activity percent complete based on activity steps: Must be Checked.
(b) Reset Remaining Duration and Units to Original: Must be Checked.
(c) Subtract Actual from At Completion: Must be Checked.
(d) Recalculate Actual units and Cost when duration percent complete changes: Must be Checked.
(e) Link Actual to Date and Actual This Period Units and Cost:
Must be Checked.
(f) Price/Unit: Set to "$1/h".
(g) Update units when costs change on resource assignments: Must be Unchecked.
(7) Project Level, Settings Tab:
(a) Define Critical Activities: Check "Longest Path".
(8) Work Breakdown Structure Level, Earned Value Tab:
(a) Technique for Computing Performance Percent Complete:
"Activity percent complete" is selected.
(b) Technique for Computing Estimate to Complete (ETC): "PF = 1" is selected.
SECTION 01 32 17.00 20 Page 13
1.10.4 Required Tabular Reports
Include the following reports with the Baseline, Monthly Update and any other required schedule submittals:
a. Log Report: P6 Scheduling/Leveling Report.
b. Narrative Report: Identify and justify:
(1) Progress made in each area of the project;
(2) Longest Path;
(3) Date/time constraint(s), other than those required by the contract
(4) Listing of all changes made between the previous schedule and current updated schedule include: added or deleted activities, original and remaining durations for activities that have not started, logic (sequence constraint…