This document is a Questions and Answers (Q&A) file related to a federal contract opportunity for the installation of new carpet in three rooms within Building 210 on Schriever Space Force Base. The carpet is currently in serviceable condition but there is some normal wear and tear. No furniture removal will be needed, and the facility was built in 2000 so there are no asbestos or other hazardous material concerns.
The solicitation is a firm fixed-price requirement under the USAF Carpet Program, with Mohawk as the Tier 1 manufacturer. The Tier 2 contract will be a 100% small business set-aside. No security clearances are required for personnel accessing the facility, and normal business hours (0700-1600 M-F) can be accommodated, with the option for work outside those hours. The base around the bottom of the wall will be installed per the revised Performance Work Statement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FA255024Q0061 - 50 CONS Carpet QnA | ||
| QUESTIONS | Date Received | ANSWERS |
| How much furniture and what type of furniture needs to be removed? | 16-Sep | No furniture removal will be needed for this effort, PWS has been updated to remove any langauge stating furniture needs to be moved/removed. |
| What is the current condition of the carpet? (e.g. glue down, stretch-in, wear and tear) Is it carpet tile or sheet? | 16-Sep | Current carpet is in servicable condition, meaning no rips, tears etc, but there is a bit of normal traffic wear for 20 year old carpet tiles. Carpet tiles are glue down, 24"x24" |
| Is there any need for asbestos abatement or other hazardous material removal? | 16-Sep | No, this facility was built in 2000. |
| Before submitting a formal proposal, will a pre-bid site visit be allowed to assess the project area, furniture, and overall logistics? | 16-Sep | |
| What are the security and access requirements for the base, and will there be any restrictions on the working hours or personnel entry? | 16-Sep | No clearance required for work in the building/offices, the facility is not in the Restricted Area of base or in a secure facility. After contract award, Contracting Officer will work with contractor to obtain base entry. Government will provide an on-site POC for normal business hours (0700-1600 M-F) work, and can provide an on-site POC for work outside of norma business hours upon request. |
| Are security clearances required for our personnel to work on-site? If so, could you provide details on the level of clearance needed and the process for obtaining it? | 16-Sep | No clearance required for work in the building/offices. |
| Are there any specific working hour restrictions or security clearance requirements for personnel accessing Schriever SFB? | 16-Sep | No clearance required for work in the building/offices, the facility is not in the Restricted Area of base or in a secure facility. After contract award, Contracting Officer will work with contractor to obtain base entry. Government will provide an on-site POC for normal business hours (0700-1600 M-F) work, and can provide an on-site POC for work outside of norma business hours upon request. |
| What will the base be around the bottom of the wall? | 20-Sep | This will be IAW line 7 in the Revised PWS in the solicitation. |